State: MEGHALAYA District: SOUTH WEST GARO HILLS Block: DAMALGRE Panchayat: MISIKONA
Work Code: 2105016658/AV/3340 (const of RCC Anganwadi Building at village Misikona in convergence with Social Welfare)
Work Category: Anganvany
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2020-2021 Execution Level : GP
Execution Agency : Gram Panchayat (3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 5/7/2020 Work start date : 24/9/2020
Present status : NEW Proposed Status : Constr of Anganwadi for community
Tech Sanction Details
Technical Sanction No. : RDB//199-A Sanction Date : 12/7/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
SK/SemiSK Est. Skilled Cost Est. Semi-Skilled Cost Block Rural Infrastructure Fund Block Rural Infrastructure Fund scheme3 Total
176204 315476 1520 6800 0 200000 0 524000 0 700000
Financial Sanction Details
Financial\Administrative Sanction No: RDB//199-A Financial\Administrative Sanction Date 12/7/2020
Fin. Sanc. Amt. (in Rs) NREGA:500000 Block Rural Infrastructure Fund
0
Block Rural Infrastructure Fund
200000
Scheme 3
0
Total
700000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Cement concrete [1:4:8] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete1700000700000
Total Activity 700000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod4.5650029250
212 mm -  M.S. rod4.5650029250
316 mm -  M.S. rod1.8650011700
420 mm -  M.S. rod165006500
5Bamboo142002800
6Barbed wire91501350
7Blade1310130
8Boltu Washer000
9Boulder Stone4.51500067500
10Brick50001365000
11Cement (Star)175610106750
12Centering and Shuttering2270015400
13Measuring Tap000
14Nail7120840
15Paint000
16Paint Brush000
17Planks000
18Project Management Cost000
19River Sand4.5700031500
20Semi Skilled Labour000
21Signboard150005000
22Skilled Labour000
23Stone aggregate1.51500022500
24Stone Chips430000120000
25Timber000
26Transportation charges000
27Vent pipe000
Total Material 516000