Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 18-Oct-2021 04:32:23 PM 
Back  
State: MEGHALAYA District: SOUTH WEST GARO HILLS Block: DAMALGRE Panchayat: MALJANGGRI
Work Code: 2105019625/RC/39711 (Construction of RCC Slab Culvert of span 1.5 m at Kosak gitim at village Maljanggre)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2019-2020 Execution Level : GP
Execution Agency : Gram Panchayat (3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 7/2/2020 Work start date : 22/2/2020
Present status : Cement concrete Proposed Status : Constr of Cement Concrete Roads for Comm
Tech Sanction Details
Technical Sanction No. : RDB/2019-20/443 Sanction Date : 14/2/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
190740 152200 1900 1700 0 0 0 156000 0 346540
Financial Sanction Details
Financial\Administrative Sanction No: RDB/2019-20/443 Financial\Administrative Sanction Date 14/2/2020
Fin. Sanc. Amt. (in Rs) NREGA:346540 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
347000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Cement concrete [1:4:8] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete1347000347000
Total Activity 347000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod164006400
212 mm -  M.S. rod1.6640010240
316 mm -  M.S. rod1.464008960
470 mm metal000
5Bamboo112502750
6Binding wire8100800
7Black Paint000
8Boulder Stone11400014000
9Bricks000
10Cement4555024750
11Centering and Shuttering2565016250
12Karai rah cement000
13Nail2100200
14Paint000
15Paint (white)000
16Paint Brush000
17Plank000
18Project Management Cost168006800
19River Sand2700014000
20Semi Skilled Labour000
21Signboard150005000
22Skilled Labour000
23Spade000
24Stone Chips1.52800042000
25Stone metal000
26Timber000
27Transportation charges000
Total Material 153000