State: MEGHALAYA District: SOUTH WEST GARO HILLS Block: BETASING Panchayat: CHIGITCHAGRE
Work Code: 2105016504/WC/15095 (CONST OF SPRING CHAMBER 1 NOS AT VILLAGE CHIGITCHAGRE DABANDI GITTIM)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2019-2020 Execution Level : GP
Execution Agency : Gram Panchayat (3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 4/4/2019 Work start date : 20/10/2019
Present status : Non-existent Proposed Status : Construction of Mini Percolation Tank for Comm
Tech Sanction Details
Technical Sanction No. : BBE.59/385 Sanction Date : 3/10/2019
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
164934 227698 0 0 0 0 0 228000 0 392632
Financial Sanction Details
Financial\Administrative Sanction No: BBE.59/385 Financial\Administrative Sanction Date 3/10/2019
Fin. Sanc. Amt. (in Rs) NREGA:392632 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
393000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Cement concrete [1:4:8] using 40mm sizeB.H.G. metal including all cost conveyancetaxes,royalit,watering curring, etc. complete1392632392632
2Earth work in stony earth and gravels mixed with stone and boulders not exceeding 0.014 cum in vol. within all lead and lift including rough dressing and breaking clods to maximum 5 cm to 7 cm and laying in layer not exceeding 0.3 m in depth and as per specification approved by the dept.111
Total Activity 393000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod4640025600
212 mm -  M.S. rod000
36 mm -  M.S. rod2640012800
48 mm -  M.S. rod000
5Bamboo103003000
6Barbed wire3100300
7Boulder Stone31450043500
8Cements5055027500
9Centering and Shuttering3065019500
10GI Pipe000
11Nail5100500
12Plank 1000
13Project Management Cost176987698
14River Sand3600018000
15Semi Skilled Labour000
16Signboard150005000
17Skilled Labour223828404
18Soling Stone000
19Stone Chips22800056000
20Transportation charges000
Total Material 228000