Asset Register
|
Work Name
|
(2101006073/FP/8016) Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 |
Nature of Work |
Flood Control
|
WorkStatus
|
Completed
|
Scope of Work
|
Start Status |
End Status |
Weak Embankment |
Construction of Embankment for community |
|
Location
|
Start Location |
Padubah |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 2101006073/FP/8016 ,
16/07/2019
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
12.8395
|
Estimated Completion Time (in Months)
|
2 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
804100 |
0 |
0 |
479850 |
0 |
1283950 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
4300 |
344 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
936(26180),937(26180),938(26180),939(26180),940(26180), 941(26180),942(26180),943(26180),944(15708),945(26180), 946(26180),947(26180),948(26180),949(26180),950(26180), 951(26180),952(26180),953(15708),2307(26180),2308(26180), 2309(26180),2310(26180),2311(26180),2312(26180),2313(26180), 2314(26180),2315(15708),2316(14960),2317(14960),2318(14960), 2319(14960),2320(14960),2321(14960),2322(14960),2323(14960), 2324(8976),
|
Work start date |
09/05/2019 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
Completed Work
|
|
|
|
|