Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-07-004-027-004/172 Family Id: 172
Name of Head of Household: Charm Timung
Name of Father/Husband: NA
Category: ST
Date of Registration: 8/11/2014
Address:
Villages:
Panchayat: Umsamlem
Block: UMSNING
District: RI BHOI (MEGHALAYA)
Whether BPL Family: NO Family Id: 172
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 Charm Timung Male 26 Meghalaya Rural Bank
2 Shailin Bey Female 20 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 11481 Charm Timung 15/09/2014~~27/09/2014~~13 12
2 11501 Shailin Bey 15/09/2014~~24/09/2014~~10 9
3 71412 Charm Timung 16/12/2014~~30/12/2014~~15 12
4 71462 Shailin Bey 16/12/2014~~30/12/2014~~15 12
5 100518 Charm Timung 12/09/2016~~24/09/2016~~13 12
6 100519 Shailin Bey 12/09/2016~~24/09/2016~~13 12
7 130283 Charm Timung 13/10/2016~~26/10/2016~~14 12
8 130284 Shailin Bey 13/10/2016~~26/10/2016~~14 12
9 150948 Charm Timung 02/11/2016~~15/11/2016~~14 12
10 150949 Shailin Bey 02/11/2016~~15/11/2016~~14 12
11 180522 Charm Timung 12/12/2016~~24/12/2016~~13 12
12 180589 Shailin Bey 12/12/2016~~24/12/2016~~13 12
13 52537 Charm Timung 24/07/2017~~05/08/2017~~13 12
14 52538 Shailin Bey 24/07/2017~~05/08/2017~~13 12
15 77734 Charm Timung 30/08/2017~~26/09/2017~~28 24
16 77735 Shailin Bey 30/08/2017~~26/09/2017~~28 24
17 100185 Charm Timung 28/09/2017~~11/10/2017~~14 12
18 100186 Shailin Bey 28/09/2017~~11/10/2017~~14 12
19 147571 Charm Timung 15/11/2017~~23/11/2017~~9 8
20 75658 31/10/2018~~13/11/2018~~14 12
21 75659 Shailin Bey 31/10/2018~~13/11/2018~~14 12
22 93831 Charm Timung 19/11/2018~~01/12/2018~~13 12
23 93833 Shailin Bey 19/11/2018~~01/12/2018~~13 12
24 104164 Charm Timung 03/12/2018~~15/12/2018~~13 12
25 104165 Shailin Bey 03/12/2018~~15/12/2018~~13 12
26 138738 Charm Timung 21/01/2019~~25/01/2019~~5 5
27 138739 Shailin Bey 21/01/2019~~25/01/2019~~5 5
28 189234 Charm Timung 28/02/2019~~09/03/2019~~10 9
29 189235 Shailin Bey 28/02/2019~~09/03/2019~~10 9
30 108438 Charm Timung 25/10/2019~~07/11/2019~~14 12
31 108439 Shailin Bey 25/10/2019~~07/11/2019~~14 12
32 128709 Charm Timung 15/11/2019~~15/11/2019~~1 1
33 128710 Shailin Bey 15/11/2019~~15/11/2019~~1 1
34 129782 Charm Timung 16/11/2019~~23/11/2019~~8 7
35 129783 Shailin Bey 16/11/2019~~23/11/2019~~8 7
36 153838 Charm Timung 06/12/2019~~07/12/2019~~2 2
37 153839 Shailin Bey 06/12/2019~~07/12/2019~~2 2
38 184951 Charm Timung 05/02/2020~~05/02/2020~~1 1
39 184952 Shailin Bey 05/02/2020~~05/02/2020~~1 1
40 219751 Charm Timung 28/02/2020~~12/03/2020~~14 12
41 219752 Shailin Bey 28/02/2020~~12/03/2020~~14 12
42 246424 Charm Timung 16/03/2020~~18/03/2020~~3 3
43 245829 Shailin Bey 16/03/2020~~28/03/2020~~13 12
44 16938 Charm Timung 11/05/2020~~23/05/2020~~13 12
45 16941 Shailin Bey 11/05/2020~~23/05/2020~~13 12
46 41352 Charm Timung 28/05/2020~~10/06/2020~~14 12
47 41353 Shailin Bey 28/05/2020~~10/06/2020~~14 12
48 84323 Charm Timung 02/07/2020~~15/07/2020~~14 12
49 84324 Shailin Bey 02/07/2020~~15/07/2020~~14 12
50 129055 Charm Timung 10/08/2020~~17/08/2020~~8 7
51 129056 Shailin Bey 10/08/2020~~17/08/2020~~8 7
52 193620 Charm Timung 28/09/2020~~01/10/2020~~4 4
53 193621 Shailin Bey 28/09/2020~~01/10/2020~~4 4
54 238151 Charm Timung 09/11/2020~~15/11/2020~~7 6
55 34708 23/07/2021~~05/08/2021~~14 12
56 34709 Shailin Bey 23/07/2021~~05/08/2021~~14 12
57 155867 Charm Timung 01/12/2021~~14/12/2021~~14 12
58 155868 Shailin Bey 01/12/2021~~14/12/2021~~14 12
59 201950 Charm Timung 02/02/2022~~15/02/2022~~14 12
60 201951 Shailin Bey 02/02/2022~~15/02/2022~~14 12
61 233423 Charm Timung 07/03/2022~~20/03/2022~~14 12
62 233424 Shailin Bey 07/03/2022~~20/03/2022~~14 12
63 17780 Charm Timung 13/06/2022~~26/06/2022~~14 12
64 17781 Shailin Bey 13/06/2022~~26/06/2022~~14 12

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 11481 Charm Timung 15/09/2014~~27/09/2014~~13 12 Const of Footpath from vill Rd to Drinking Well- Rongphyrkong
2 11501 Shailin Bey 15/09/2014~~24/09/2014~~10 9 Const of Footpath from vill Rd to Drinking Well- Rongphyrkong
3 71412 Charm Timung 16/12/2014~~30/12/2014~~15 12 Construction of approach road from Lad lum jinhtep to Umnget
4 71462 Shailin Bey 16/12/2014~~30/12/2014~~15 12 Construction of approach road from Lad lum jinhtep to Umnget
5 100518 Charm Timung 12/09/2016~~24/09/2016~~13 12 Water Conservation and Water harvesting-Rongphyr-kong
6 100519 Shailin Bey 12/09/2016~~24/09/2016~~13 12 Water Conservation and Water harvesting-Rongphyr-kong
7 130283 Charm Timung 13/10/2016~~26/10/2016~~14 12 Water Conservation and Water harvesting-Rongphyr-kong
8 130284 Shailin Bey 13/10/2016~~26/10/2016~~14 12 Water Conservation and Water harvesting-Rongphyr-kong
9 150948 Charm Timung 02/11/2016~~15/11/2016~~14 12 Water Conservation and Water harvesting-Rongphyr-kong
10 150949 Shailin Bey 02/11/2016~~15/11/2016~~14 12 Water Conservation and Water harvesting-Rongphyr-kong
11 180522 Charm Timung 12/12/2016~~24/12/2016~~13 12 Water Conservation and Water harvesting-Rongphyr-kong
12 180589 Shailin Bey 12/12/2016~~24/12/2016~~13 12 Water Conservation and Water harvesting-Rongphyr-kong
13 52537 Charm Timung 24/07/2017~~05/08/2017~~13 12 const. 0f motorable road _ rongphyrkong
14 52538 Shailin Bey 24/07/2017~~05/08/2017~~13 12 const. 0f motorable road _ rongphyrkong
15 77734 Charm Timung 30/08/2017~~26/09/2017~~28 24 const. 0f motorable road _ rongphyrkong
16 77735 Shailin Bey 30/08/2017~~26/09/2017~~28 24 const. 0f motorable road _ rongphyrkong
17 100185 Charm Timung 28/09/2017~~11/10/2017~~14 12 const. 0f motorable road _ rongphyrkong
18 100186 Shailin Bey 28/09/2017~~11/10/2017~~14 12 const. 0f motorable road _ rongphyrkong
19 147571 Charm Timung 15/11/2017~~23/11/2017~~9 8 const. 0f motorable road _ rongphyrkong
20 75658 31/10/2018~~13/11/2018~~14 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
21 75659 Shailin Bey 31/10/2018~~13/11/2018~~14 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
22 93831 Charm Timung 19/11/2018~~01/12/2018~~13 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
23 93833 Shailin Bey 19/11/2018~~01/12/2018~~13 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
24 104164 Charm Timung 03/12/2018~~15/12/2018~~13 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
25 104165 Shailin Bey 03/12/2018~~15/12/2018~~13 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
26 138738 Charm Timung 21/01/2019~~25/01/2019~~5 5 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
27 138739 Shailin Bey 21/01/2019~~25/01/2019~~5 5 Construction of cc motorable road from Sawlad to Rongman Rongpharkong
28 189234 Charm Timung 28/02/2019~~09/03/2019~~10 9 Construction of cc footpath from sawlad to sangam Rongpharkong
29 189235 Shailin Bey 28/02/2019~~09/03/2019~~10 9 Construction of cc footpath from sawlad to sangam Rongpharkong
30 108438 Charm Timung 25/10/2019~~07/11/2019~~14 12 CONST. OF STORAGE WATER TANK WITH FENCING
31 108439 Shailin Bey 25/10/2019~~07/11/2019~~14 12 CONST. OF STORAGE WATER TANK WITH FENCING
32 128709 Charm Timung 15/11/2019~~15/11/2019~~1 1 Kitchen garden at rongpharkong vec
33 128710 Shailin Bey 15/11/2019~~15/11/2019~~1 1 Kitchen garden at rongpharkong vec
34 129782 Charm Timung 16/11/2019~~23/11/2019~~8 7 Const of cc motorable road
35 129783 Shailin Bey 16/11/2019~~23/11/2019~~8 7 Const of cc motorable road
36 153838 Charm Timung 06/12/2019~~07/12/2019~~2 2 CONST. OF STORAGE WATER TANK WITH FENCING
37 153839 Shailin Bey 06/12/2019~~07/12/2019~~2 2 CONST. OF STORAGE WATER TANK WITH FENCING
38 184951 Charm Timung 05/02/2020~~05/02/2020~~1 1 Const of checkdam
39 184952 Shailin Bey 05/02/2020~~05/02/2020~~1 1 Const of checkdam
40 219751 Charm Timung 28/02/2020~~12/03/2020~~14 12 Const of cc motorable road
41 219752 Shailin Bey 28/02/2020~~12/03/2020~~14 12 Const of cc motorable road
42 246424 Charm Timung 16/03/2020~~18/03/2020~~3 3 Const of cc motorable road
43 245829 Shailin Bey 16/03/2020~~28/03/2020~~13 12 constuction of water tank with bathing place and washing platform
44 16938 Charm Timung 11/05/2020~~23/05/2020~~13 12 constuction of water tank with bathing place and washing platform
45 16941 Shailin Bey 11/05/2020~~23/05/2020~~13 12 constuction of water tank with bathing place and washing platform
46 41352 Charm Timung 28/05/2020~~10/06/2020~~14 12 Construction of approach road from Mawphor to Rongman
47 41353 Shailin Bey 28/05/2020~~10/06/2020~~14 12 Construction of approach road from Mawphor to Rongman
48 84323 Charm Timung 02/07/2020~~15/07/2020~~14 12 Construction of approach road na sawlad sha jaka sum
49 84324 Shailin Bey 02/07/2020~~15/07/2020~~14 12 Construction of approach road na sawlad sha jaka sum
50 129055 Charm Timung 10/08/2020~~17/08/2020~~8 7 Construction of approach road from Mawphor to Rongman
51 129056 Shailin Bey 10/08/2020~~17/08/2020~~8 7 Construction of approach road from Mawphor to Rongman
52 193620 Charm Timung 28/09/2020~~01/10/2020~~4 4 Construction of approach road na sawlad sha jaka sum
53 193621 Shailin Bey 28/09/2020~~01/10/2020~~4 4 Construction of approach road na sawlad sha jaka sum
54 238151 Charm Timung 09/11/2020~~15/11/2020~~7 6 Construction of water storage tank with washing platform at dong Mawtari
55 34708 23/07/2021~~05/08/2021~~14 12 Construction of check dam with fencing
56 34709 Shailin Bey 23/07/2021~~05/08/2021~~14 12 Construction of check dam with fencing
57 155867 Charm Timung 01/12/2021~~14/12/2021~~14 12 construction of approach road from lad skul to lum mawker
58 155868 Shailin Bey 01/12/2021~~14/12/2021~~14 12 construction of approach road from lad skul to lum mawker
59 201950 Charm Timung 02/02/2022~~15/02/2022~~14 12 construction of approach road from lad skul to lum mawker
60 201951 Shailin Bey 02/02/2022~~15/02/2022~~14 12 construction of approach road from lad skul to lum mawker
61 233423 Charm Timung 07/03/2022~~20/03/2022~~14 12 construction of fishery pond at Rongpharkong
62 233424 Shailin Bey 07/03/2022~~20/03/2022~~14 12 construction of fishery pond at Rongpharkong
63 17780 Charm Timung 13/06/2022~~26/06/2022~~14 12 construction of fishery pond at Rongpharkong
64 17781 Shailin Bey 13/06/2022~~26/06/2022~~14 12 construction of fishery pond at Rongpharkong

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 Charm Timung 15/09/2014 12 Const of Footpath from vill Rd to Drinking Well- Rongphyrkong 670 1836 0
2 Shailin Bey 15/09/2014 9 Const of Footpath from vill Rd to Drinking Well- Rongphyrkong 670 1377 0
3 Charm Timung 16/12/2014 12 Construction of approach road from Lad lum jinhtep to Umnget 2961 1836 0
4 Shailin Bey 16/12/2014 12 Construction of approach road from Lad lum jinhtep to Umnget 2961 1836 0
Sub Total FY 1415 45 6885 0
5 Charm Timung 12/09/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 5823 2028 0
6 Shailin Bey 12/09/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 5823 2028 0
7 Charm Timung 13/10/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 7508 2028 0
8 Shailin Bey 13/10/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 7508 2028 0
9 Charm Timung 02/11/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 8458 2028 2028
10 Shailin Bey 02/11/2016 12 Water Conservation and Water harvesting-Rongphyr-kong 8458 2028 2028
11 Charm Timung 12/12/2016 5 Water Conservation and Water harvesting-Rongphyr-kong 9969 845 0
12 Shailin Bey 12/12/2016 5 Water Conservation and Water harvesting-Rongphyr-kong 9969 845 0
Sub Total FY 1617 82 13858 4056
13 Charm Timung 24/07/2017 12 const. 0f motorable road _ rongphyrkong 2800 2100 0
14 Shailin Bey 24/07/2017 12 const. 0f motorable road _ rongphyrkong 2800 2100 0
15 Charm Timung 30/08/2017 12 const. 0f motorable road _ rongphyrkong 4140 2100 0
16 Shailin Bey 30/08/2017 12 const. 0f motorable road _ rongphyrkong 4140 2100 0
17 Charm Timung 30/08/2017 12 const. 0f motorable road _ rongphyrkong 4167 2100 0
18 Shailin Bey 30/08/2017 12 const. 0f motorable road _ rongphyrkong 4167 2100 0
19 Charm Timung 28/09/2017 10 const. 0f motorable road _ rongphyrkong 4986 1750 0
20 Shailin Bey 28/09/2017 10 const. 0f motorable road _ rongphyrkong 4986 1750 0
21 Charm Timung 15/11/2017 8 const. 0f motorable road _ rongphyrkong 6924 1400 0
Sub Total FY 1718 100 17500 0
22 Charm Timung 31/10/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2105 2172 0
23 Shailin Bey 31/10/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2105 2172 0
24 Charm Timung 19/11/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2317 2172 0
25 Shailin Bey 19/11/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2317 2172 0
26 Charm Timung 03/12/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2533 2172 0
27 Shailin Bey 03/12/2018 12 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 2533 2172 0
28 Charm Timung 21/01/2019 5 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 3637 905 0
29 Shailin Bey 21/01/2019 5 Construction of cc motorable road from Sawlad to Rongman Rongpharkong 3637 905 0
30 Charm Timung 28/02/2019 9 Construction of cc footpath from sawlad to sangam Rongpharkong 6105 1629 0
31 Shailin Bey 28/02/2019 9 Construction of cc footpath from sawlad to sangam Rongpharkong 6105 1629 0
Sub Total FY 1819 100 18100 0
32 Charm Timung 25/10/2019 12 CONST. OF STORAGE WATER TANK WITH FENCING 3355 2244 0
33 Shailin Bey 25/10/2019 12 CONST. OF STORAGE WATER TANK WITH FENCING 3355 2244 0
34 Charm Timung 15/11/2019 1 Kitchen garden at rongpharkong vec 3963 187 0
35 Shailin Bey 15/11/2019 1 Kitchen garden at rongpharkong vec 3963 187 0
36 Charm Timung 16/11/2019 7 Const of cc motorable road 4021 1309 0
37 Shailin Bey 16/11/2019 7 Const of cc motorable road 4021 1309 0
38 Charm Timung 06/12/2019 2 CONST. OF STORAGE WATER TANK WITH FENCING 4844 374 0
39 Shailin Bey 06/12/2019 2 CONST. OF STORAGE WATER TANK WITH FENCING 4844 374 0
40 Charm Timung 05/02/2020 1 Const of checkdam 6115 187 0
41 Shailin Bey 05/02/2020 1 Const of checkdam 6115 187 0
42 Charm Timung 28/02/2020 12 Const of cc motorable road 7408 2244 0
43 Shailin Bey 28/02/2020 12 Const of cc motorable road 7408 2244 0
44 Charm Timung 16/03/2020 3 Const of cc motorable road 8757 561 0
45 Shailin Bey 16/03/2020 8 constuction of water tank with bathing place and washing platform 8716 1496 0
Sub Total FY 1920 81 15147 0
46 Charm Timung 11/05/2020 12 constuction of water tank with bathing place and washing platform 569 2436 0
47 Shailin Bey 11/05/2020 12 constuction of water tank with bathing place and washing platform 569 2436 0
48 Charm Timung 28/05/2020 12 Construction of approach road from Mawphor to Rongman 1480 2436 0
49 Shailin Bey 28/05/2020 12 Construction of approach road from Mawphor to Rongman 1480 2436 0
50 Charm Timung 02/07/2020 12 Construction of approach road na sawlad sha jaka sum 3510 2436 0
51 Shailin Bey 02/07/2020 12 Construction of approach road na sawlad sha jaka sum 3510 2436 0
52 Charm Timung 10/08/2020 7 Construction of approach road from Mawphor to Rongman 4980 1421 0
53 Shailin Bey 10/08/2020 7 Construction of approach road from Mawphor to Rongman 4980 1421 0
54 Charm Timung 28/09/2020 4 Construction of approach road na sawlad sha jaka sum 7144 812 0
55 Shailin Bey 28/09/2020 4 Construction of approach road na sawlad sha jaka sum 7144 812 0
56 Charm Timung 09/11/2020 6 Construction of water storage tank with washing platform at dong Mawtari 8739 1218 0
Sub Total FY 2021 100 20300 0
57 Charm Timung 23/07/2021 4 Construction of check dam with fencing 1680 904 0
58 Shailin Bey 23/07/2021 4 Construction of check dam with fencing 1680 904 0
59 Charm Timung 01/12/2021 12 construction of approach road from lad skul to lum mawker 4574 2712 0
60 Shailin Bey 01/12/2021 12 construction of approach road from lad skul to lum mawker 4574 2712 0
61 Charm Timung 02/02/2022 12 construction of approach road from lad skul to lum mawker 6056 2712 0
62 Shailin Bey 02/02/2022 12 construction of approach road from lad skul to lum mawker 6056 2712 0
63 Charm Timung 07/03/2022 12 construction of fishery pond at Rongpharkong 7757 2712 0
64 Shailin Bey 07/03/2022 12 construction of fishery pond at Rongpharkong 7757 2712 0
Sub Total FY 2122 80 18080 0