Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-009-014-002/241 Family Id: 241
Name of Head of Household: Temple Rymbai
Name of Father/Husband: (L) K pyrtuh
Category: ST
Date of Registration: 8/9/2007
Address:
Villages:
Panchayat: Moodymmai
Block: THADLASKEIN
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 241
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 Temple Rymbai Female 36 State Bank of India
2 Iaraptre Rymbai Male 19


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 37227 Iaraptre Rymbai 18/12/2008~~19/12/2008~~2 2
2 38627 Temple Rymbai 23/03/2009~~28/03/2009~~6 6
3 38772 30/03/2009~~31/03/2009~~2 2
4 62637 Iaraptre Rymbai 07/12/2009~~12/12/2009~~6 6
5 61934 14/12/2009~~19/12/2009~~6 6
6 61668 Temple Rymbai 01/02/2010~~06/02/2010~~6 6
7 1187 01/04/2010~~04/04/2010~~4 4
8 1187 01/04/2010~~04/04/2010~~4 4
9 5566 09/04/2010~~13/04/2010~~5 5
10 5566 09/04/2010~~13/04/2010~~5 5
11 18306 01/05/2010~~04/05/2010~~4 4
12 18306 01/05/2010~~04/05/2010~~4 4
13 19550 08/05/2010~~12/05/2010~~5 5
14 19550 08/05/2010~~12/05/2010~~5 5
15 10434 15/05/2010~~19/05/2010~~5 5
16 10434 15/05/2010~~19/05/2010~~5 5
17 13922 22/05/2010~~22/05/2010~~1 1
18 13922 22/05/2010~~22/05/2010~~1 1
19 26305 18/06/2010~~23/06/2010~~6 6
20 26305 18/06/2010~~23/06/2010~~6 6
21 26926 25/06/2010~~30/06/2010~~6 6
22 26926 25/06/2010~~30/06/2010~~6 6
23 27722 19/07/2010~~22/07/2010~~4 4
24 27722 19/07/2010~~22/07/2010~~4 4
25 33720 Iaraptre Rymbai 26/07/2010~~31/07/2010~~6 6
26 33720 26/07/2010~~31/07/2010~~6 6
27 31129 Temple Rymbai 26/07/2010~~31/07/2010~~6 6
28 31129 26/07/2010~~31/07/2010~~6 6
29 39542 Iaraptre Rymbai 02/08/2010~~07/08/2010~~6 6
30 39542 02/08/2010~~07/08/2010~~6 6
31 36556 Temple Rymbai 02/08/2010~~07/08/2010~~6 6
32 36556 02/08/2010~~07/08/2010~~6 6
33 47120 09/08/2010~~14/08/2010~~6 6
34 47120 09/08/2010~~14/08/2010~~6 6
35 46588 Iaraptre Rymbai 16/08/2010~~21/08/2010~~6 6
36 46588 16/08/2010~~21/08/2010~~6 6
37 57115 Temple Rymbai 21/09/2010~~26/09/2010~~6 6
38 57115 21/09/2010~~26/09/2010~~6 6
39 53805 04/10/2010~~09/10/2010~~6 6
40 53805 04/10/2010~~09/10/2010~~6 6
41 58047 11/10/2010~~16/10/2010~~6 6
42 58047 11/10/2010~~16/10/2010~~6 6
43 58303 18/10/2010~~19/10/2010~~2 2
44 58303 18/10/2010~~19/10/2010~~2 2
45 80589 13/12/2010~~18/12/2010~~6 6
46 79492 03/01/2011~~06/01/2011~~4 4
47 2370 04/04/2011~~05/04/2011~~2 2
48 2019 18/04/2011~~21/04/2011~~4 4
49 1831 25/04/2011~~26/04/2011~~2 2
50 12185 13/06/2011~~14/06/2011~~2 2
51 27385 05/09/2011~~10/09/2011~~6 6
52 26694 12/09/2011~~13/09/2011~~2 2
53 18311 19/09/2011~~20/09/2011~~2 2
54 25521 05/10/2011~~10/10/2011~~6 6
55 42517 07/11/2011~~12/11/2011~~6 6
56 42251 14/11/2011~~14/11/2011~~1 1
57 46736 16/01/2012~~20/01/2012~~5 5
58 29999 03/11/2012~~09/11/2012~~7 7
59 30164 12/11/2012~~13/11/2012~~2 2
60 16886 08/07/2013~~11/07/2013~~4 4
61 16524 16/07/2013~~17/07/2013~~2 2
62 89216 16/01/2014~~21/01/2014~~6 6
63 88996 24/01/2014~~29/01/2014~~6 6
64 9887 05/08/2014~~23/08/2014~~19 17
65 67234 04/10/2017~~19/10/2017~~16 14
66 122165 20/11/2018~~05/12/2018~~16 14
67 140213 14/12/2018~~29/12/2018~~16 14
68 151543 08/01/2019~~23/01/2019~~16 14
69 179803 04/02/2019~~19/02/2019~~16 14
70 105390 23/09/2019~~08/10/2019~~16 14
71 129277 15/10/2019~~30/10/2019~~16 14
72 258115 02/03/2020~~17/03/2020~~16 14
73 273029 19/03/2020~~26/03/2020~~8 7
74 162244 06/11/2020~~21/11/2020~~16 14
75 175506 27/11/2020~~12/12/2020~~16 14
76 248720 08/03/2022~~23/03/2022~~16 14
77 1508 07/04/2022~~22/04/2022~~16 14

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 37227 Iaraptre Rymbai 18/12/2008~~19/12/2008~~2 2 Construction of Jeepable Road at Moodymmai
2 38627 Temple Rymbai 23/03/2009~~28/03/2009~~6 6 Construction of Jeepable Road at Moodymmai
3 38772 30/03/2009~~31/03/2009~~2 2 Construction of Jeepable Road at Moodymmai
4 62637 Iaraptre Rymbai 07/12/2009~~12/12/2009~~6 6 Construction of Village Road at Modymmai
5 61934 14/12/2009~~19/12/2009~~6 6 Construction of Drinking Well at Mustem
6 61668 Temple Rymbai 01/02/2010~~06/02/2010~~6 6 Construction of Village Road at Modymmai
7 1187 01/04/2010~~04/04/2010~~4 36 Construction of Footpath at Moodymmai
8 5566 09/04/2010~~13/04/2010~~5 45 Construction of Footpath at Moodymmai
9 18306 01/05/2010~~04/05/2010~~4 32 Construction of Village Road at Modymmai
10 19550 08/05/2010~~12/05/2010~~5 35 Construction of Village Road at Modymmai
11 10434 15/05/2010~~19/05/2010~~5 45 Construction of Village Road at Modymmai
12 13922 22/05/2010~~22/05/2010~~1 9 Construction of Village Road at Modymmai
13 26305 18/06/2010~~23/06/2010~~6 36 Construction of Agri Link Road at Moodymmai
14 26926 25/06/2010~~30/06/2010~~6 30 Construction of Agri Link Road at Moodymmai
15 27722 19/07/2010~~22/07/2010~~4 32 Construction of Agri Link Road at Moodymmai
16 33720 Iaraptre Rymbai 26/07/2010~~31/07/2010~~6 24 Construction of Agri Link Road at Moodymmai
17 31129 Temple Rymbai 26/07/2010~~31/07/2010~~6 24 Construction of Agri Link Road at Moodymmai
18 39542 Iaraptre Rymbai 02/08/2010~~07/08/2010~~6 24 Construction of Agri Link Road at Moodymmai
19 36556 Temple Rymbai 02/08/2010~~07/08/2010~~6 24 Construction of Agri Link Road at Moodymmai
20 47120 09/08/2010~~14/08/2010~~6 12 Construction of Agri Link Road at Moodymmai
21 46588 Iaraptre Rymbai 16/08/2010~~21/08/2010~~6 12 Construction of Agri Link Road at Moodymmai
22 57115 Temple Rymbai 21/09/2010~~26/09/2010~~6 12 Construction of Fishery Pond at Moodymmai
23 53805 04/10/2010~~09/10/2010~~6 12 Construction of Fishery Pond at Moodymmai
24 58047 11/10/2010~~16/10/2010~~6 12 Construction of Fishery Pond at Moodymmai
25 58303 18/10/2010~~19/10/2010~~2 4 Construction of Fishery Pond at Moodymmai
26 80589 13/12/2010~~18/12/2010~~6 6 Construction of Fishery Pond at Moodymmai
27 79492 03/01/2011~~06/01/2011~~4 4 Construction of Fishery Pond at Moodymmai
28 2370 04/04/2011~~05/04/2011~~2 10 Construction of Fishery Pond at Moodymmai
29 2019 18/04/2011~~21/04/2011~~4 16 Construction of Fishery Pond at Moodymmai
30 1831 25/04/2011~~26/04/2011~~2 10 Construction of Fishery Pond at Moodymmai
31 12185 13/06/2011~~14/06/2011~~2 10 Construction of Fishery Pond at Moodymmai
32 27385 05/09/2011~~10/09/2011~~6 30 Construction of Village Road at Niriang
33 26694 12/09/2011~~13/09/2011~~2 10 Construction of Village Road at Moodymmai
34 18311 19/09/2011~~20/09/2011~~2 10 Construction of Village Road at Moodymmai
35 25521 05/10/2011~~10/10/2011~~6 24 Construction of Village Road at Moodymmai
36 42517 07/11/2011~~12/11/2011~~6 12 Construction of Internal Road at Moodymmai (Lum Sabah)
37 42251 14/11/2011~~14/11/2011~~1 2 Construction of Internal Road at Moodymmai (Lum Sabah)
38 46736 16/01/2012~~20/01/2012~~5 10 Construction of Internal Road at Moodymmai (Wah Sukha)
39 29999 03/11/2012~~09/11/2012~~7 19 Construction of Footpath at Moodymmai
40 30164 12/11/2012~~13/11/2012~~2 6 Construction of Footpath at Moodymmai
41 16886 08/07/2013~~11/07/2013~~4 12 Construction of Fencing at Modymmai (2013-14)
42 16524 16/07/2013~~17/07/2013~~2 4 Construction of Fencing at Modymmai (2013-14)
43 89216 16/01/2014~~21/01/2014~~6 6 Construction of Fishery pond cum retaining wall at
44 88996 24/01/2014~~29/01/2014~~6 6 Construction of Fishery pond cum retaining wall at
45 9887 05/08/2014~~23/08/2014~~19 17 Construction of Fishery pond cum retaining wall at
46 67234 04/10/2017~~19/10/2017~~16 14 Construction of Drinking Well at Moodymmai 2015-16
47 122165 20/11/2018~~05/12/2018~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
48 140213 14/12/2018~~29/12/2018~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
49 151543 08/01/2019~~23/01/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
50 179803 04/02/2019~~19/02/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
51 105390 23/09/2019~~08/10/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
52 129277 15/10/2019~~30/10/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
53 258115 02/03/2020~~17/03/2020~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
54 273029 19/03/2020~~26/03/2020~~8 7 Construcction of Side Drain at Moodymmai Lumsalah 201819
55 162244 06/11/2020~~21/11/2020~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
56 175506 27/11/2020~~12/12/2020~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
57 248720 08/03/2022~~23/03/2022~~16 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22
58 1508 07/04/2022~~22/04/2022~~16 14 Construction of Footpath at Moodymmai 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 Iaraptre Rymbai 18/12/2008 1 Construction of Jeepable Road at Moodymmai 7738 70 0
2 Temple Rymbai 23/03/2009 6 Construction of Jeepable Road at Moodymmai 6270 420 0
3 Temple Rymbai 30/03/2009 2 Construction of Jeepable Road at Moodymmai 6262 140 0
Sub Total FY 0809 9 630 0
4 Iaraptre Rymbai 07/12/2009 6 Construction of Village Road at Modymmai 9467 600 0
5 Iaraptre Rymbai 14/12/2009 6 Construction of Drinking Well at Mustem 8932 600 0
6 Temple Rymbai 01/02/2010 3 Construction of Village Road at Modymmai 17452 300 0
Sub Total FY 0910 15 1500 0
7 Temple Rymbai 01/04/2010 4 Construction of Footpath at Moodymmai 23274 400 0
8 Temple Rymbai 09/04/2010 5 Construction of Footpath at Moodymmai 23312 500 0
9 Temple Rymbai 01/05/2010 2 Construction of Village Road at Modymmai 51 200 0
10 Temple Rymbai 03/05/2010 2 Construction of Village Road at Modymmai 24372 200 0
11 Temple Rymbai 08/05/2010 2 Construction of Village Road at Modymmai 25875 200 0
12 Temple Rymbai 10/05/2010 3 Construction of Village Road at Modymmai 62 300 0
13 Temple Rymbai 15/05/2010 5 Construction of Village Road at Modymmai 25998 500 0
14 Temple Rymbai 22/05/2010 1 Construction of Village Road at Modymmai 26050 100 0
15 Temple Rymbai 18/06/2010 6 Construction of Agri Link Road at Moodymmai 28125 600 0
16 Temple Rymbai 25/06/2010 2 Construction of Agri Link Road at Moodymmai 108 200 0
17 Temple Rymbai 27/06/2010 4 Construction of Agri Link Road at Moodymmai 26322 400 0
18 Temple Rymbai 19/07/2010 4 Construction of Agri Link Road at Moodymmai 28167 400 0
19 Iaraptre Rymbai 26/07/2010 6 Construction of Agri Link Road at Moodymmai 26352 600 0
20 Temple Rymbai 26/07/2010 6 Construction of Agri Link Road at Moodymmai 29930 600 0
21 Iaraptre Rymbai 02/08/2010 6 Construction of Agri Link Road at Moodymmai 26379 600 0
22 Temple Rymbai 02/08/2010 6 Construction of Agri Link Road at Moodymmai 26365 600 0
23 Temple Rymbai 09/08/2010 6 Construction of Agri Link Road at Moodymmai 26575 600 0
24 Iaraptre Rymbai 16/08/2010 6 Construction of Agri Link Road at Moodymmai 33054 600 0
25 Temple Rymbai 21/09/2010 6 Construction of Fishery Pond at Moodymmai 26626 600 0
26 Temple Rymbai 04/10/2010 6 Construction of Fishery Pond at Moodymmai 33062 600 0
27 Temple Rymbai 11/10/2010 6 Construction of Fishery Pond at Moodymmai 39880 600 0
28 Temple Rymbai 18/10/2010 2 Construction of Fishery Pond at Moodymmai 39885 200 0
29 Temple Rymbai 13/12/2010 6 Construction of Fishery Pond at Moodymmai 50386 600 0
Sub Total FY 1011 102 10200 0
30 Temple Rymbai 04/04/2011 2 Construction of Fishery Pond at Moodymmai 54568 200 0
31 Temple Rymbai 18/04/2011 4 Construction of Fishery Pond at Moodymmai 54596 400 0
32 Temple Rymbai 25/04/2011 2 Construction of Fishery Pond at Moodymmai 54602 200 0
33 Temple Rymbai 13/06/2011 2 Construction of Fishery Pond at Moodymmai 54624 234 0
34 Temple Rymbai 05/09/2011 6 Construction of Village Road at Niriang 57225 702 0
35 Temple Rymbai 12/09/2011 2 Construction of Village Road at Moodymmai 59850 234 0
36 Temple Rymbai 19/09/2011 2 Construction of Village Road at Moodymmai 59898 234 0
37 Temple Rymbai 07/11/2011 6 Construction of Internal Road at Moodymmai (Lum Sabah) 60685 702 0
38 Temple Rymbai 14/11/2011 1 Construction of Internal Road at Moodymmai (Lum Sabah) 68425 117 0
39 Temple Rymbai 16/01/2012 5 Construction of Internal Road at Moodymmai (Wah Sukha) 68821 585 0
Sub Total FY 1112 32 3608 0
40 Temple Rymbai 03/11/2012 7 Construction of Footpath at Moodymmai 101299 896 0
41 Temple Rymbai 12/11/2012 2 Construction of Footpath at Moodymmai 94318 256 0
Sub Total FY 1213 9 1152 0
42 Temple Rymbai 08/07/2013 4 Construction of Fencing at Modymmai (2013-14) 116378 580 0
43 Temple Rymbai 16/07/2013 2 Construction of Fencing at Modymmai (2013-14) 116420 290 0
44 Temple Rymbai 16/01/2014 6 Construction of Fishery pond cum retaining wall at 136261 870 0
45 Temple Rymbai 24/01/2014 6 Construction of Fishery pond cum retaining wall at 136285 870 0
Sub Total FY 1314 18 2610 0
46 Temple Rymbai 05/08/2014 10 Construction of Fishery pond cum retaining wall at 21 1530 0
47 Temple Rymbai 16/08/2014 7 Construction of Fishery pond cum retaining wall at 63 1071 0
Sub Total FY 1415 17 2601 0
48 Temple Rymbai 04/10/2017 13 Construction of Drinking Well at Moodymmai 2015-16 1756 2275 0
Sub Total FY 1718 13 2275 0
49 Temple Rymbai 20/11/2018 12 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 4439 2172 0
50 Temple Rymbai 14/12/2018 4 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 5281 724 0
51 Temple Rymbai 08/01/2019 9 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 5824 1629 0
52 Temple Rymbai 04/02/2019 6 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 6474 1086 0
Sub Total FY 1819 31 5611 0
53 Temple Rymbai 23/09/2019 13 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 3242 2431 0
54 Temple Rymbai 15/10/2019 13 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 4247 2431 0
55 Temple Rymbai 19/03/2020 7 Construcction of Side Drain at Moodymmai Lumsalah 201819 9886 1309 0
Sub Total FY 1920 33 6171 0
56 Temple Rymbai 06/11/2020 14 Construction of improvement of playfield at Moodymmai Phase I 2021 4503 2842 0
57 Temple Rymbai 27/11/2020 8 Construction of improvement of playfield at Moodymmai Phase I 2021 5002 1624 0
Sub Total FY 2021 22 4466 0
58 Temple Rymbai 08/03/2022 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22 10397 3164 0
Sub Total FY 2122 14 3164 0
59 Temple Rymbai 07/04/2022 5 Construction of Footpath at Moodymmai 2021 22 89 1150 0
Sub Total FY 2223 5 1150 0