Job card No.: MG-01-009-014-002/153 Family-Id: 153
Name of Head of Household: Shri Hep Muruh
Name of Father/Husband: H.Muruh
Category: ST
Date of Registration: 8/29/2007
Address:
Villages:
Panchayat: Moodymmai
Block: THADLASKEIN
District: WEST JAINTIA HILLS(MEGHALAYA)
: NO Family-Id: 153
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 Shri Hep Muruh Male 35 State Bank of India
2 Trebor Rymbai Male 18
3 Treibor Rymbai Male 25


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Name of Applicant Month & Date from which employment requested No of Days
1 37161 Shri Hep Muruh 18/12/2008~~19/12/2008~~2 2
2 38526 23/03/2009~~28/03/2009~~6 6
3 38671 30/03/2009~~31/03/2009~~2 2
4 5166 11/05/2009~~16/05/2009~~6 6
5 62652 Trebor Rymbai 07/12/2009~~12/12/2009~~6 6
6 61542 Shri Hep Muruh 01/02/2010~~06/02/2010~~6 6
7 1078 01/04/2010~~05/04/2010~~5 5
8 1078 01/04/2010~~05/04/2010~~5 5
9 5437 09/04/2010~~11/04/2010~~3 3
10 5437 09/04/2010~~11/04/2010~~3 3
11 18184 01/05/2010~~02/05/2010~~2 2
12 18184 01/05/2010~~02/05/2010~~2 2
13 10296 15/05/2010~~18/05/2010~~4 4
14 10296 15/05/2010~~18/05/2010~~4 4
15 13787 22/05/2010~~22/05/2010~~1 1
16 13787 22/05/2010~~22/05/2010~~1 1
17 26023 18/06/2010~~21/06/2010~~4 4
18 26023 18/06/2010~~21/06/2010~~4 4
19 26816 25/06/2010~~30/06/2010~~6 6
20 26816 25/06/2010~~30/06/2010~~6 6
21 29368 Trebor Rymbai 12/07/2010~~17/07/2010~~6 6
22 29368 12/07/2010~~17/07/2010~~6 6
23 27580 Shri Hep Muruh 19/07/2010~~21/07/2010~~3 3
24 27580 19/07/2010~~21/07/2010~~3 3
25 27902 Trebor Rymbai 19/07/2010~~22/07/2010~~4 4
26 27902 19/07/2010~~22/07/2010~~4 4
27 30992 Shri Hep Muruh 26/07/2010~~31/07/2010~~6 6
28 30992 26/07/2010~~31/07/2010~~6 6
29 36257 02/08/2010~~02/08/2010~~1 1
30 36257 02/08/2010~~02/08/2010~~1 1
31 46838 09/08/2010~~10/08/2010~~2 2
32 46838 09/08/2010~~10/08/2010~~2 2
33 56753 21/09/2010~~26/09/2010~~6 6
34 56753 21/09/2010~~26/09/2010~~6 6
35 55368 28/09/2010~~29/09/2010~~2 2
36 55368 28/09/2010~~29/09/2010~~2 2
37 80070 13/12/2010~~18/12/2010~~6 6
38 79356 03/01/2011~~08/01/2011~~6 6
39 72526 10/01/2011~~15/01/2011~~6 6
40 46679 Trebor Rymbai 09/01/2012~~11/01/2012~~3 3
41 73085 Shri Hep Muruh 27/02/2012~~01/03/2012~~4 4
42 72924 Trebor Rymbai 27/02/2012~~01/03/2012~~4 4
43 71911 06/03/2012~~07/03/2012~~2 2
44 10112 26/06/2012~~29/06/2012~~4 4
45 29906 03/11/2012~~09/11/2012~~7 7
46 30139 Shri Hep Muruh 12/11/2012~~12/11/2012~~1 1
47 16726 Trebor Rymbai 08/07/2013~~14/07/2013~~7 7
48 16449 16/07/2013~~23/07/2013~~8 7
49 17230 24/07/2013~~25/07/2013~~2 2
50 88200 Shri Hep Muruh 08/01/2014~~14/01/2014~~7 7
51 89322 Trebor Rymbai 16/01/2014~~21/01/2014~~6 6
52 88892 Shri Hep Muruh 24/01/2014~~29/01/2014~~6 6
53 9676 Trebor Rymbai 05/08/2014~~23/08/2014~~19 17
54 121297 Shri Hep Muruh 20/11/2018~~05/12/2018~~16 14
55 139400 14/12/2018~~29/12/2018~~16 14
56 150812 08/01/2019~~23/01/2019~~16 14
57 178993 04/02/2019~~19/02/2019~~16 14
58 104895 23/09/2019~~08/10/2019~~16 14
59 128706 15/10/2019~~30/10/2019~~16 14
60 193711 10/01/2020~~25/01/2020~~16 14
61 234867 12/02/2020~~27/02/2020~~16 14
62 258041 02/03/2020~~17/03/2020~~16 14
63 146842 15/10/2020~~30/10/2020~~16 14
64 161644 06/11/2020~~21/11/2020~~16 14
65 285649 11/03/2021~~26/03/2021~~16 14
66 192 06/04/2021~~21/04/2021~~16 14
67 4492 22/04/2021~~07/05/2021~~16 14
68 11810 13/05/2021~~28/05/2021~~16 14
69 248888 08/03/2022~~23/03/2022~~16 14
70 1310 07/04/2022~~22/04/2022~~16 14

Period and Work on which Employment Offered

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name
1 37161 Shri Hep Muruh 18/12/2008~~19/12/2008~~2 2 Construction of Jeepable Road at Moodymmai
2 38526 23/03/2009~~28/03/2009~~6 6 Construction of Jeepable Road at Moodymmai
3 38671 30/03/2009~~31/03/2009~~2 2 Construction of Jeepable Road at Moodymmai
4 5166 11/05/2009~~16/05/2009~~6 30 Construction of Drinking Well at Moodymmai
5 62652 Trebor Rymbai 07/12/2009~~12/12/2009~~6 6 Construction of Village Road at Modymmai
6 61542 Shri Hep Muruh 01/02/2010~~06/02/2010~~6 6 Construction of Village Road at Modymmai
7 1078 01/04/2010~~05/04/2010~~5 45 Construction of Footpath at Moodymmai
8 5437 09/04/2010~~11/04/2010~~3 27 Construction of Footpath at Moodymmai
9 18184 01/05/2010~~02/05/2010~~2 16 Construction of Village Road at Modymmai
10 10296 15/05/2010~~18/05/2010~~4 36 Construction of Village Road at Modymmai
11 13787 22/05/2010~~22/05/2010~~1 9 Construction of Village Road at Modymmai
12 26023 18/06/2010~~21/06/2010~~4 20 Construction of Agri Link Road at Moodymmai
13 26816 25/06/2010~~30/06/2010~~6 30 Construction of Agri Link Road at Moodymmai
14 29368 Trebor Rymbai 12/07/2010~~17/07/2010~~6 24 Construction of Agri Link Road at Moodymmai
15 27580 Shri Hep Muruh 19/07/2010~~21/07/2010~~3 24 Construction of Agri Link Road at Moodymmai
16 27902 Trebor Rymbai 19/07/2010~~22/07/2010~~4 32 Construction of Agri Link Road at Moodymmai
17 30992 Shri Hep Muruh 26/07/2010~~31/07/2010~~6 24 Construction of Agri Link Road at Moodymmai
18 36257 02/08/2010~~02/08/2010~~1 4 Construction of Agri Link Road at Moodymmai
19 46838 09/08/2010~~10/08/2010~~2 4 Construction of Agri Link Road at Moodymmai
20 56753 21/09/2010~~26/09/2010~~6 12 Construction of Fishery Pond at Moodymmai
21 55368 28/09/2010~~29/09/2010~~2 4 Construction of Fishery Pond at Moodymmai
22 80070 13/12/2010~~18/12/2010~~6 6 Construction of Fishery Pond at Moodymmai
23 79356 03/01/2011~~08/01/2011~~6 6 Construction of Fishery Pond at Moodymmai
24 72526 10/01/2011~~15/01/2011~~6 6 Construction of Fishery Pond at Moodymmai
25 46679 Trebor Rymbai 09/01/2012~~11/01/2012~~3 6 Construction of Internal Road at Moodymmai (Wah Sukha)
26 73085 Shri Hep Muruh 27/02/2012~~01/03/2012~~4 4 Internal road at moodymmai
27 72924 Trebor Rymbai 27/02/2012~~01/03/2012~~4 4 Internal road at moodymmai
28 71911 06/03/2012~~07/03/2012~~2 4 Internal road at moodymmai
29 10112 26/06/2012~~29/06/2012~~4 24 Construction of Footpath at Moodymmai
30 29906 03/11/2012~~09/11/2012~~7 20 Construction of Footpath at Moodymmai
31 30139 Shri Hep Muruh 12/11/2012~~12/11/2012~~1 3 Construction of Footpath at Moodymmai
32 16726 Trebor Rymbai 08/07/2013~~14/07/2013~~7 21 Construction of Fencing at Modymmai (2013-14)
33 16449 16/07/2013~~23/07/2013~~8 21 Construction of Fencing at Modymmai (2013-14)
34 17230 24/07/2013~~25/07/2013~~2 6 Construction of Fencing at Modymmai (2013-14)
35 88200 Shri Hep Muruh 08/01/2014~~14/01/2014~~7 7 Construction of Fishery pond cum retaining wall at
36 89322 Trebor Rymbai 16/01/2014~~21/01/2014~~6 6 Construction of Fishery pond cum retaining wall at
37 88892 Shri Hep Muruh 24/01/2014~~29/01/2014~~6 6 Construction of Fishery pond cum retaining wall at
38 9676 Trebor Rymbai 05/08/2014~~23/08/2014~~19 17 Construction of Fishery pond cum retaining wall at
39 121297 Shri Hep Muruh 20/11/2018~~05/12/2018~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
40 139400 14/12/2018~~29/12/2018~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
41 150812 08/01/2019~~23/01/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
42 178993 04/02/2019~~19/02/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
43 104895 23/09/2019~~08/10/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
44 128706 15/10/2019~~30/10/2019~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819
45 193711 10/01/2020~~25/01/2020~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
46 234867 12/02/2020~~27/02/2020~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
47 258041 02/03/2020~~17/03/2020~~16 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819
48 146842 15/10/2020~~30/10/2020~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
49 161644 06/11/2020~~21/11/2020~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
50 285649 11/03/2021~~26/03/2021~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
51 192 06/04/2021~~21/04/2021~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
52 4492 22/04/2021~~07/05/2021~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
53 11810 13/05/2021~~28/05/2021~~16 14 Construction of improvement of playfield at Moodymmai Phase I 2021
54 248888 08/03/2022~~23/03/2022~~16 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22
55 1310 07/04/2022~~22/04/2022~~16 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 Shri Hep Muruh 18/12/2008 1 Construction of Jeepable Road at Moodymmai 7735 70 0
2 Shri Hep Muruh 23/03/2009 6 Construction of Jeepable Road at Moodymmai 6265 420 0
3 Shri Hep Muruh 30/03/2009 2 Construction of Jeepable Road at Moodymmai 6257 140 0
Sub Total FY 0809 9 630 0
4 Shri Hep Muruh 11/05/2009 6 Construction of Drinking Well at Moodymmai 6518 420 0
5 Trebor Rymbai 07/12/2009 3 Construction of Village Road at Modymmai 9468 300 0
6 Shri Hep Muruh 01/02/2010 6 Construction of Village Road at Modymmai 16031 600 0
Sub Total FY 0910 15 1320 0
7 Shri Hep Muruh 01/04/2010 5 Construction of Footpath at Moodymmai 23258 500 0
8 Shri Hep Muruh 09/04/2010 3 Construction of Footpath at Moodymmai 23298 300 0
9 Shri Hep Muruh 01/05/2010 2 Construction of Village Road at Modymmai 49 200 0
10 Shri Hep Muruh 15/05/2010 4 Construction of Village Road at Modymmai 25984 400 0
11 Shri Hep Muruh 22/05/2010 1 Construction of Village Road at Modymmai 26036 100 0
12 Shri Hep Muruh 18/06/2010 4 Construction of Agri Link Road at Moodymmai 28111 400 0
13 Shri Hep Muruh 25/06/2010 2 Construction of Agri Link Road at Moodymmai 26308 200 0
14 Shri Hep Muruh 27/06/2010 4 Construction of Agri Link Road at Moodymmai 93 400 0
15 Trebor Rymbai 12/07/2010 6 Construction of Agri Link Road at Moodymmai 28193 600 0
16 Shri Hep Muruh 19/07/2010 3 Construction of Agri Link Road at Moodymmai 28153 300 0
17 Trebor Rymbai 19/07/2010 4 Construction of Agri Link Road at Moodymmai 28197 400 0
18 Shri Hep Muruh 26/07/2010 6 Construction of Agri Link Road at Moodymmai 29929 600 0
19 Shri Hep Muruh 02/08/2010 1 Construction of Agri Link Road at Moodymmai 26364 100 0
20 Shri Hep Muruh 09/08/2010 2 Construction of Agri Link Road at Moodymmai 26574 200 0
21 Shri Hep Muruh 21/09/2010 6 Construction of Fishery Pond at Moodymmai 26620 600 0
22 Shri Hep Muruh 28/09/2010 2 Construction of Fishery Pond at Moodymmai 26662 200 0
23 Shri Hep Muruh 13/12/2010 6 Construction of Fishery Pond at Moodymmai 50373 600 0
24 Shri Hep Muruh 03/01/2011 6 Construction of Fishery Pond at Moodymmai 50414 600 0
25 Shri Hep Muruh 10/01/2011 6 Construction of Fishery Pond at Moodymmai 50449 600 0
Sub Total FY 1011 73 7300 0
26 Trebor Rymbai 09/01/2012 3 Construction of Internal Road at Moodymmai (Wah Sukha) 72047 351 0
27 Shri Hep Muruh 27/02/2012 4 Internal road at moodymmai 73765 468 0
28 Trebor Rymbai 27/02/2012 4 Internal road at moodymmai 73766 468 0
29 Trebor Rymbai 06/03/2012 2 Internal road at moodymmai 74957 234 0
Sub Total FY 1112 13 1521 0
30 Trebor Rymbai 26/06/2012 4 Construction of Footpath at Moodymmai 88042 512 0
31 Trebor Rymbai 03/11/2012 7 Construction of Footpath at Moodymmai 101296 896 0
32 Shri Hep Muruh 12/11/2012 1 Construction of Footpath at Moodymmai 94315 128 0
Sub Total FY 1213 12 1536 0
33 Trebor Rymbai 08/07/2013 7 Construction of Fencing at Modymmai (2013-14) 116366 1015 0
34 Trebor Rymbai 16/07/2013 7 Construction of Fencing at Modymmai (2013-14) 116414 1015 0
35 Trebor Rymbai 24/07/2013 2 Construction of Fencing at Modymmai (2013-14) 116437 290 0
36 Shri Hep Muruh 08/01/2014 7 Construction of Fishery pond cum retaining wall at 136203 1015 0
37 Trebor Rymbai 16/01/2014 6 Construction of Fishery pond cum retaining wall at 136237 870 0
38 Shri Hep Muruh 24/01/2014 6 Construction of Fishery pond cum retaining wall at 136273 870 0
Sub Total FY 1314 35 5075 0
39 Trebor Rymbai 05/08/2014 10 Construction of Fishery pond cum retaining wall at 11 1530 0
40 Trebor Rymbai 16/08/2014 7 Construction of Fishery pond cum retaining wall at 53 1071 0
Sub Total FY 1415 17 2601 0
41 Shri Hep Muruh 20/11/2018 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 4402 2534 0
42 Shri Hep Muruh 14/12/2018 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 5250 2534 0
43 Shri Hep Muruh 08/01/2019 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 5789 2534 0
44 Shri Hep Muruh 04/02/2019 14 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 6449 2534 0
Sub Total FY 1819 56 10136 0
45 Shri Hep Muruh 23/09/2019 8 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 3217 1496 0
46 Shri Hep Muruh 15/10/2019 11 Construction of Side Drain at Moodymmai Lumwahsukha One 201819 4222 2057 0
47 Shri Hep Muruh 10/01/2020 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 7064 2618 0
48 Shri Hep Muruh 12/02/2020 14 Construction of Side Drain at Moodymmai Lumwahsukha Two 201819 8431 2618 0
Sub Total FY 1920 47 8789 0
49 Shri Hep Muruh 15/10/2020 14 Construction of improvement of playfield at Moodymmai Phase I 2021 4106 2842 0
50 Shri Hep Muruh 06/11/2020 7 Construction of improvement of playfield at Moodymmai Phase I 2021 4497 1421 0
51 Shri Hep Muruh 11/03/2021 14 Construction of improvement of playfield at Moodymmai Phase I 2021 9863 2842 0
Sub Total FY 2021 35 7105 0
52 Shri Hep Muruh 06/04/2021 14 Construction of improvement of playfield at Moodymmai Phase I 2021 8 3164 0
53 Shri Hep Muruh 22/04/2021 14 Construction of improvement of playfield at Moodymmai Phase I 2021 473 3164 0
54 Shri Hep Muruh 13/05/2021 14 Construction of improvement of playfield at Moodymmai Phase I 2021 1245 3164 0
55 Shri Hep Muruh 08/03/2022 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22 10408 3164 0
Sub Total FY 2122 56 12656 0
56 Shri Hep Muruh 07/04/2022 14 Construction of Internal Cement Concrete Road at Moodymmai 2021-22 75 3220 0
Sub Total FY 2223 14 3220 0