Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/54 Family Id: 54
Name of Head of Household: IBAWANROI POHTHMI
Name of Father/Husband: T S
Category: ST
Date of Registration: 9/1/2009
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 54
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 EBAWANROI POHTHMI Female 33
2 Ibawanroi Pohthmi Female 20 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20887 EBAWANROI POHTHMI 05/01/2011~~11/01/2011~~7 7
2 116766 05/01/2011~~11/01/2011~~7 7
3 7378 22/07/2011~~29/07/2011~~8 7
4 13030 09/08/2011~~16/08/2011~~8 7
5 19248 03/10/2011~~10/10/2011~~8 7
6 11454 02/08/2012~~05/08/2012~~4 4
7 2042 10/07/2013~~25/07/2013~~16 14
8 63675 Ibawanroi Pohthmi 19/10/2015~~03/11/2015~~16 14
9 70268 14/12/2015~~29/12/2015~~16 14
10 76038 06/01/2016~~08/01/2016~~3 3
11 101127 24/02/2016~~10/03/2016~~16 14
12 588 28/04/2016~~05/05/2016~~8 7
13 21271 11/08/2016~~26/08/2016~~16 14
14 30099 29/08/2016~~22/09/2016~~25 22
15 57938 30/09/2016~~30/09/2016~~1 1
16 83381 07/11/2016~~08/12/2016~~32 28
17 109778 21/12/2016~~31/12/2016~~11 10
18 155003 02/03/2017~~23/03/2017~~22 19
19 19372 21/06/2017~~24/06/2017~~4 4
20 22111 29/06/2017~~21/07/2017~~23 20
21 64969 27/09/2017~~10/10/2017~~14 12
22 90064 29/11/2017~~30/12/2017~~32 28
23 127129 06/02/2018~~09/03/2018~~32 28
24 18516 07/05/2018~~15/05/2018~~9 8
25 81628 24/09/2018~~04/11/2018~~42 36
26 191593 12/02/2019~~25/03/2019~~42 36
27 103796 23/09/2019~~24/10/2019~~32 28
28 144941 31/10/2019~~24/11/2019~~25 22
29 199282 13/01/2020~~13/01/2020~~1 1
30 202901 15/01/2020~~15/02/2020~~32 28
31 243277 18/02/2020~~13/03/2020~~25 22
32 58074 15/07/2020~~15/08/2020~~32 28
33 99597 24/08/2020~~17/09/2020~~25 22
34 277933 04/03/2021~~26/03/2021~~23 20
35 84828 27/09/2021~~03/10/2021~~7 6
36 122239 10/11/2021~~11/12/2021~~32 28

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116766 EBAWANROI POHTHMI 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7378 22/07/2011~~29/07/2011~~8 34 const of rcc footpath at Padubad
3 13030 09/08/2011~~16/08/2011~~8 34 const of rcc footpath at Padubad
4 19248 03/10/2011~~10/10/2011~~8 27 const of rcc footpath at Padubad
5 11454 02/08/2012~~05/08/2012~~4 24 const of rcc footpath at Padubad
6 2042 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
7 63675 Ibawanroi Pohthmi 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 70268 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 76038 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
10 101127 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 588 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
12 21271 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 30099 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 57938 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
15 83381 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 109778 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
17 155003 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
18 19372 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
19 22111 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
20 64969 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
21 90064 29/11/2017~~30/12/2017~~32 28 Construction of C C Footpath cum Railing at Padubah VEC 2017-18
22 127129 06/02/2018~~09/03/2018~~32 28 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
23 18516 07/05/2018~~15/05/2018~~9 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
24 81628 24/09/2018~~04/11/2018~~42 36 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10
25 191593 12/02/2019~~25/03/2019~~42 36 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89
26 103796 23/09/2019~~24/10/2019~~32 28 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
27 144941 31/10/2019~~24/11/2019~~25 22 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
28 199282 13/01/2020~~13/01/2020~~1 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
29 202901 15/01/2020~~15/02/2020~~32 28 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
30 243277 18/02/2020~~13/03/2020~~25 22 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
31 58074 15/07/2020~~15/08/2020~~32 28 Construction of Poultry Shed at Padubah VEC WO 2020 21
32 99597 24/08/2020~~17/09/2020~~25 22 Construction of Poultry Shed at Padubah VEC WO 2020 21
33 277933 04/03/2021~~26/03/2021~~23 20 Construction of Dug Out Pond at Padubah VEC WO 2020 2021
34 84828 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
35 122239 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 EBAWANROI POHTHMI 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 EBAWANROI POHTHMI 22/07/2011 7 const of rcc footpath at Padubad 45711 819 0
3 EBAWANROI POHTHMI 09/08/2011 7 const of rcc footpath at Padubad 44443 700 0
4 EBAWANROI POHTHMI 03/10/2011 7 const of rcc footpath at Padubad 65638 700 0
Sub Total FY 1112 21 2219 0
5 EBAWANROI POHTHMI 02/08/2012 4 const of rcc footpath at Padubad 86904 512 0
Sub Total FY 1213 4 512 0
6 EBAWANROI POHTHMI 10/07/2013 14 2101006024/WC/39 109429 2030 0
Sub Total FY 1314 14 2030 0
7 Ibawanroi Pohthmi 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2751 2282 0
8 Ibawanroi Pohthmi 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3050 2119 0
9 Ibawanroi Pohthmi 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3357 489 0
10 Ibawanroi Pohthmi 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4690 2282 0
Sub Total FY 1516 44 7172 0
11 Ibawanroi Pohthmi 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 68 1183 0
12 Ibawanroi Pohthmi 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1155 2197 0
13 Ibawanroi Pohthmi 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1656 2366 0
14 Ibawanroi Pohthmi 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1688 1352 0
15 Ibawanroi Pohthmi 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2521 169 0
16 Ibawanroi Pohthmi 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3449 2366 0
17 Ibawanroi Pohthmi 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3481 2366 0
18 Ibawanroi Pohthmi 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4272 1690 0
19 Ibawanroi Pohthmi 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5527 2366 0
20 Ibawanroi Pohthmi 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5559 845 0
Sub Total FY 1617 100 16900 0
21 Ibawanroi Pohthmi 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 824 700 0
22 Ibawanroi Pohthmi 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1109 2450 0
23 Ibawanroi Pohthmi 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1138 1050 0
24 Ibawanroi Pohthmi 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3834 2100 0
25 Ibawanroi Pohthmi 29/11/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4875 2450 0
26 Ibawanroi Pohthmi 15/12/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4880 2450 0
27 Ibawanroi Pohthmi 06/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6248 2450 0
28 Ibawanroi Pohthmi 22/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6252 2450 0
Sub Total FY 1718 92 16100 0
29 Ibawanroi Pohthmi 07/05/2018 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 466 1400 0
30 Ibawanroi Pohthmi 24/09/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2668 2534 0
31 Ibawanroi Pohthmi 10/10/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2687 2534 0
32 Ibawanroi Pohthmi 26/10/2018 8 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 3180 1448 0
33 Ibawanroi Pohthmi 12/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 5642 2534 0
34 Ibawanroi Pohthmi 28/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6080 2534 0
35 Ibawanroi Pohthmi 16/03/2019 8 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6084 1448 0
Sub Total FY 1819 80 14432 0
36 Ibawanroi Pohthmi 23/09/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1821 2618 0
37 Ibawanroi Pohthmi 09/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1827 2618 0
38 Ibawanroi Pohthmi 31/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3049 2618 0
39 Ibawanroi Pohthmi 16/11/2019 7 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3055 1309 0
40 Ibawanroi Pohthmi 13/01/2020 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 5123 187 0
41 Ibawanroi Pohthmi 15/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5383 2618 0
42 Ibawanroi Pohthmi 31/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5390 2618 0
43 Ibawanroi Pohthmi 18/02/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6748 2618 0
44 Ibawanroi Pohthmi 05/03/2020 8 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6755 1496 0
Sub Total FY 1920 100 18700 0
45 Ibawanroi Pohthmi 15/07/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 1180 2842 0
46 Ibawanroi Pohthmi 31/07/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 1181 2842 0
47 Ibawanroi Pohthmi 24/08/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 2437 2842 0
48 Ibawanroi Pohthmi 09/09/2020 8 Construction of Poultry Shed at Padubah VEC WO 2020 21 2438 1624 0
49 Ibawanroi Pohthmi 04/03/2021 14 Construction of Dug Out Pond at Padubah VEC WO 2020 2021 7595 2842 0
50 Ibawanroi Pohthmi 20/03/2021 6 Construction of Dug Out Pond at Padubah VEC WO 2020 2021 7603 1218 0
Sub Total FY 2021 70 14210 0
51 Ibawanroi Pohthmi 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 892 1356 0
52 Ibawanroi Pohthmi 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1958 3164 0
Sub Total FY 2122 20 4520 0