Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/47 Family Id: 47
Name of Head of Household: BIPHUL SUMER
Name of Father/Husband: DM
Category: ST
Date of Registration: 9/1/2009
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 47
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 BIPHUL SUMER Female 29 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20832 BIPHUL SUMER 05/01/2011~~11/01/2011~~7 7
2 116758 05/01/2011~~11/01/2011~~7 7
3 7371 22/07/2011~~29/07/2011~~8 7
4 13023 09/08/2011~~16/08/2011~~8 7
5 19241 03/10/2011~~10/10/2011~~8 7
6 11447 02/08/2012~~05/08/2012~~4 4
7 2034 10/07/2013~~25/07/2013~~16 14
8 101392 24/02/2016~~10/03/2016~~16 14
9 819 28/04/2016~~05/05/2016~~8 7
10 21533 11/08/2016~~26/08/2016~~16 14
11 30661 29/08/2016~~22/09/2016~~25 22
12 58453 30/09/2016~~30/09/2016~~1 1
13 83374 07/11/2016~~08/12/2016~~32 28
14 109771 21/12/2016~~31/12/2016~~11 10
15 154997 02/03/2017~~23/03/2017~~22 19
16 19347 21/06/2017~~24/06/2017~~4 4
17 22107 29/06/2017~~21/07/2017~~23 20
18 70244 09/10/2017~~01/11/2017~~24 21
19 151393 19/03/2018~~30/03/2018~~12 11
20 2586 03/04/2018~~04/05/2018~~32 28
21 21164 14/05/2018~~16/05/2018~~3 3
22 27590 28/05/2018~~12/06/2018~~16 14
23 63479 27/08/2018~~27/09/2018~~32 28
24 88946 01/10/2018~~31/10/2018~~31 27
25 13808 30/04/2019~~15/05/2019~~16 14
26 21534 22/05/2019~~30/05/2019~~9 8
27 79764 21/08/2019~~21/09/2019~~32 28
28 127709 14/10/2019~~07/11/2019~~25 22
29 165138 26/11/2019~~26/11/2019~~1 1
30 199645 13/01/2020~~30/01/2020~~18 16
31 61345 20/07/2020~~20/08/2020~~32 28
32 132003 22/09/2020~~23/10/2020~~32 28
33 154458 27/10/2020~~23/11/2020~~28 24
34 277033 04/03/2021~~12/03/2021~~9 8
35 85498 27/09/2021~~01/10/2021~~5 5
36 122035 10/11/2021~~11/12/2021~~32 28
37 152624 14/12/2021~~29/12/2021~~16 14
38 166488 05/01/2022~~15/01/2022~~11 10

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116758 BIPHUL SUMER 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7371 22/07/2011~~29/07/2011~~8 34 const of rcc footpath at Padubad
3 13023 09/08/2011~~16/08/2011~~8 25 const of rcc footpath at Padubad
4 19241 03/10/2011~~10/10/2011~~8 27 const of rcc footpath at Padubad
5 11447 02/08/2012~~05/08/2012~~4 24 const of rcc footpath at Padubad
6 2034 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
7 101392 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
8 819 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
9 21533 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
10 30661 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
11 58453 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
12 83374 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
13 109771 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
14 154997 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
15 19347 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
16 22107 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
17 70244 09/10/2017~~01/11/2017~~24 21 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34
18 151393 19/03/2018~~30/03/2018~~12 11 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
19 2586 03/04/2018~~04/05/2018~~32 28 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
20 21164 14/05/2018~~16/05/2018~~3 3 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
21 27590 28/05/2018~~12/06/2018~~16 14 Construction of IAY House -IAY REG. NO. MG1049626
22 63479 27/08/2018~~27/09/2018~~32 28 Construction of IAY House -IAY REG. NO. MG1049626
23 88946 01/10/2018~~31/10/2018~~31 27 Construction of IAY House -IAY REG. NO. MG1049626
24 13808 30/04/2019~~15/05/2019~~16 14 Construction of IAY House -IAY REG. NO. MG1049626
25 21534 22/05/2019~~30/05/2019~~9 8 Construction of IAY House -IAY REG. NO. MG1049626
26 79764 21/08/2019~~21/09/2019~~32 28 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016
27 127709 14/10/2019~~07/11/2019~~25 22 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016
28 165138 26/11/2019~~26/11/2019~~1 1 Construction of IAY House -IAY REG. NO. MG1049626
29 199645 13/01/2020~~30/01/2020~~18 16 Construction of C C Footpath at Padubah WO 2019 20 RC 43126
30 61345 20/07/2020~~20/08/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
31 132003 22/09/2020~~23/10/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
32 154458 27/10/2020~~23/11/2020~~28 24 Construction of Internal Road at PaduBah VEC WO 2020 21
33 277033 04/03/2021~~12/03/2021~~9 8 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
34 85498 27/09/2021~~01/10/2021~~5 5 Improvement of Community Pond Ph I WO 2021 22
35 122035 10/11/2021~~11/12/2021~~32 28 Construction of Footpath at Padubah VEC WO 2021 22
36 152624 14/12/2021~~29/12/2021~~16 14 Construction of Footpath at Padubah VEC WO 2021 22
37 166488 05/01/2022~~15/01/2022~~11 10 Construction of Footpath at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 BIPHUL SUMER 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 BIPHUL SUMER 22/07/2011 7 const of rcc footpath at Padubad 45710 819 0
3 BIPHUL SUMER 09/08/2011 7 const of rcc footpath at Padubad 44442 700 0
4 BIPHUL SUMER 03/10/2011 7 const of rcc footpath at Padubad 65637 700 0
Sub Total FY 1112 21 2219 0
5 BIPHUL SUMER 02/08/2012 4 const of rcc footpath at Padubad 86903 512 0
Sub Total FY 1213 4 512 0
6 BIPHUL SUMER 10/07/2013 14 2101006024/WC/39 109428 2030 0
Sub Total FY 1314 14 2030 0
7 BIPHUL SUMER 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4689 2282 0
Sub Total FY 1516 14 2282 0
8 BIPHUL SUMER 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 67 1183 0
9 BIPHUL SUMER 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1154 2197 0
10 BIPHUL SUMER 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1655 2366 0
11 BIPHUL SUMER 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1687 1352 0
12 BIPHUL SUMER 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2520 169 0
13 BIPHUL SUMER 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3448 2366 0
14 BIPHUL SUMER 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3480 2366 0
15 BIPHUL SUMER 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4271 1690 0
16 BIPHUL SUMER 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5526 2366 0
17 BIPHUL SUMER 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5558 845 0
Sub Total FY 1617 100 16900 0
18 BIPHUL SUMER 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 823 700 0
19 BIPHUL SUMER 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1109 2450 0
20 BIPHUL SUMER 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1138 1050 0
21 BIPHUL SUMER 09/10/2017 14 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4097 2450 0
22 BIPHUL SUMER 25/10/2017 7 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4099 1225 0
23 BIPHUL SUMER 19/03/2018 11 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 6947 1925 0
Sub Total FY 1718 56 9800 0
24 BIPHUL SUMER 03/04/2018 14 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 48 2450 0
25 BIPHUL SUMER 19/04/2018 14 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 51 2450 0
26 BIPHUL SUMER 14/05/2018 3 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 518 525 0
27 BIPHUL SUMER 28/05/2018 14 Construction of IAY House -IAY REG. NO. MG1049626 923 2534 0
28 BIPHUL SUMER 27/08/2018 14 Construction of IAY House -IAY REG. NO. MG1049626 2372 2534 0
29 BIPHUL SUMER 12/09/2018 14 Construction of IAY House -IAY REG. NO. MG1049626 2373 2534 0
30 BIPHUL SUMER 01/10/2018 14 Construction of IAY House -IAY REG. NO. MG1049626 2806 2534 0
31 BIPHUL SUMER 17/10/2018 13 Construction of IAY House -IAY REG. NO. MG1049626 2807 2353 0
Sub Total FY 1819 100 17914 0
32 BIPHUL SUMER 30/04/2019 14 Construction of IAY House -IAY REG. NO. MG1049626 115 2618 0
33 BIPHUL SUMER 22/05/2019 8 Construction of IAY House -IAY REG. NO. MG1049626 210 1496 0
34 BIPHUL SUMER 21/08/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 942 2618 0
35 BIPHUL SUMER 06/09/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 951 2618 0
36 BIPHUL SUMER 14/10/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 2313 2618 0
37 BIPHUL SUMER 30/10/2019 8 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 2322 1496 0
38 BIPHUL SUMER 26/11/2019 1 Construction of IAY House -IAY REG. NO. MG1049626 3619 187 0
39 BIPHUL SUMER 13/01/2020 14 Construction of C C Footpath at Padubah WO 2019 20 RC 43126 5144 2618 0
40 BIPHUL SUMER 29/01/2020 2 Construction of C C Footpath at Padubah WO 2019 20 RC 43126 5151 374 0
Sub Total FY 1920 89 16643 0
41 BIPHUL SUMER 20/07/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1256 2842 0
42 BIPHUL SUMER 05/08/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1298 2842 0
43 BIPHUL SUMER 22/09/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3231 2842 0
44 BIPHUL SUMER 08/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3238 2842 0
45 BIPHUL SUMER 27/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3946 2842 0
46 BIPHUL SUMER 12/11/2020 10 Construction of Internal Road at PaduBah VEC WO 2020 21 3953 2030 0
47 BIPHUL SUMER 04/03/2021 8 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7561 1624 0
Sub Total FY 2021 88 17864 0
48 BIPHUL SUMER 27/09/2021 5 Improvement of Community Pond Ph I WO 2021 22 888 1130 0
49 BIPHUL SUMER 10/11/2021 14 Construction of Footpath at Padubah VEC WO 2021 22 1895 3164 0
50 BIPHUL SUMER 26/11/2021 14 Construction of Footpath at Padubah VEC WO 2021 22 1903 3164 0
51 BIPHUL SUMER 14/12/2021 13 Construction of Footpath at Padubah VEC WO 2021 22 2651 2938 0
52 BIPHUL SUMER 05/01/2022 10 Construction of Footpath at Padubah VEC WO 2021 22 3230 2260 0
Sub Total FY 2122 56 12656 0