Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/40 Family Id: 40
Name of Head of Household: HAI DHAR
Name of Father/Husband: KJ
Category: ST
Date of Registration: 9/1/2009
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 40
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 HAI DHAR Female 35 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20976 HAI DHAR 05/01/2011~~11/01/2011~~7 7
2 116751 05/01/2011~~11/01/2011~~7 7
3 7364 22/07/2011~~29/07/2011~~8 7
4 13016 09/08/2011~~16/08/2011~~8 7
5 19234 03/10/2011~~10/10/2011~~8 7
6 11440 02/08/2012~~05/08/2012~~4 4
7 2027 10/07/2013~~25/07/2013~~16 14
8 63662 19/10/2015~~03/11/2015~~16 14
9 70255 14/12/2015~~29/12/2015~~16 14
10 76022 06/01/2016~~08/01/2016~~3 3
11 101113 24/02/2016~~10/03/2016~~16 14
12 577 28/04/2016~~05/05/2016~~8 7
13 21259 11/08/2016~~26/08/2016~~16 14
14 30087 29/08/2016~~22/09/2016~~25 22
15 57905 30/09/2016~~30/09/2016~~1 1
16 83367 07/11/2016~~08/12/2016~~32 28
17 109764 21/12/2016~~31/12/2016~~11 10
18 154990 02/03/2017~~23/03/2017~~22 19
19 19329 21/06/2017~~24/06/2017~~4 4
20 22101 29/06/2017~~21/07/2017~~23 20
21 70240 09/10/2017~~01/11/2017~~24 21
22 26805 28/05/2018~~28/06/2018~~32 28
23 35689 29/06/2018~~07/07/2018~~9 8
24 172095 28/01/2019~~18/02/2019~~22 19
25 76100 19/08/2019~~19/09/2019~~32 28
26 122941 09/10/2019~~02/11/2019~~25 22
27 204160 15/01/2020~~15/02/2020~~32 28
28 242216 17/02/2020~~12/03/2020~~25 22
29 61300 20/07/2020~~20/08/2020~~32 28
30 132007 22/09/2020~~23/10/2020~~32 28
31 154446 27/10/2020~~23/11/2020~~28 24
32 279862 08/03/2021~~10/03/2021~~3 3
33 82271 23/09/2021~~24/09/2021~~2 2
34 121118 09/11/2021~~16/11/2021~~8 7
35 184870 18/01/2022~~18/02/2022~~32 28
36 223851 21/02/2022~~24/03/2022~~32 28

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116751 HAI DHAR 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7364 22/07/2011~~29/07/2011~~8 34 const of rcc footpath at Padubad
3 13016 09/08/2011~~16/08/2011~~8 34 const of rcc footpath at Padubad
4 19234 03/10/2011~~10/10/2011~~8 25 const of rcc footpath at Padubad
5 11440 02/08/2012~~05/08/2012~~4 24 const of rcc footpath at Padubad
6 2027 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
7 63662 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 70255 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 76022 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
10 101113 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 577 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
12 21259 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 30087 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 57905 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
15 83367 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 109764 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
17 154990 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
18 19329 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
19 22101 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
20 70240 09/10/2017~~01/11/2017~~24 21 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34
21 26805 28/05/2018~~28/06/2018~~32 28 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
22 35689 29/06/2018~~07/07/2018~~9 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
23 172095 28/01/2019~~18/02/2019~~22 19 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82
24 76100 19/08/2019~~19/09/2019~~32 28 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632
25 122941 09/10/2019~~02/11/2019~~25 22 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632
26 204160 15/01/2020~~15/02/2020~~32 28 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564
27 242216 17/02/2020~~12/03/2020~~25 22 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564
28 61300 20/07/2020~~20/08/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
29 132007 22/09/2020~~23/10/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
30 154446 27/10/2020~~23/11/2020~~28 24 Construction of Internal Road at PaduBah VEC WO 2020 21
31 279862 08/03/2021~~10/03/2021~~3 3 Leveling & Filling of Playground at Padu Bah VEC WO 2020 21
32 82271 23/09/2021~~24/09/2021~~2 2 Construction of Slap Cover at Padubah VEC WO 2021 22
33 121118 09/11/2021~~16/11/2021~~8 7 Construction of side drain at Padubah VEC WO 2021 22
34 184870 18/01/2022~~18/02/2022~~32 28 Construction of Footpath Ph II at Padubah VEC WO 2021 22
35 223851 21/02/2022~~24/03/2022~~32 28 Construction of Footpath Ph II at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 HAI DHAR 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 HAI DHAR 22/07/2011 7 const of rcc footpath at Padubad 45709 819 0
3 HAI DHAR 09/08/2011 7 const of rcc footpath at Padubad 44441 700 0
4 HAI DHAR 03/10/2011 7 const of rcc footpath at Padubad 65636 700 0
Sub Total FY 1112 21 2219 0
5 HAI DHAR 02/08/2012 4 const of rcc footpath at Padubad 86902 512 0
Sub Total FY 1213 4 512 0
6 HAI DHAR 10/07/2013 14 2101006024/WC/39 109427 2030 0
Sub Total FY 1314 14 2030 0
7 HAI DHAR 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2750 2282 0
8 HAI DHAR 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3049 2119 0
9 HAI DHAR 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3356 489 0
10 HAI DHAR 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4689 2282 0
Sub Total FY 1516 44 7172 0
11 HAI DHAR 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 66 1183 0
12 HAI DHAR 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1154 2197 0
13 HAI DHAR 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1655 2366 0
14 HAI DHAR 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1687 1352 0
15 HAI DHAR 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2520 169 0
16 HAI DHAR 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3448 2366 0
17 HAI DHAR 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3480 2366 0
18 HAI DHAR 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4271 1690 0
19 HAI DHAR 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5526 2366 0
20 HAI DHAR 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5558 845 0
Sub Total FY 1617 100 16900 0
21 HAI DHAR 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 823 700 0
22 HAI DHAR 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1108 2450 0
23 HAI DHAR 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1137 1050 0
24 HAI DHAR 09/10/2017 14 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4097 2450 0
25 HAI DHAR 25/10/2017 7 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4099 1225 0
Sub Total FY 1718 45 7875 0
26 HAI DHAR 28/05/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 884 2534 0
27 HAI DHAR 13/06/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 900 2534 0
28 HAI DHAR 29/06/2018 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 1165 1448 0
29 HAI DHAR 28/01/2019 14 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5085 2534 0
30 HAI DHAR 13/02/2019 5 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5094 905 0
Sub Total FY 1819 55 9955 0
31 HAI DHAR 19/08/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 896 2618 0
32 HAI DHAR 04/09/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 900 2618 0
33 HAI DHAR 09/10/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 2188 2618 0
34 HAI DHAR 25/10/2019 8 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 2192 1496 0
35 HAI DHAR 15/01/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 5393 2618 0
36 HAI DHAR 31/01/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 5397 2618 0
37 HAI DHAR 17/02/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 6694 2618 0
38 HAI DHAR 04/03/2020 8 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 6698 1496 0
Sub Total FY 1920 100 18700 0
39 HAI DHAR 20/07/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1255 2842 0
40 HAI DHAR 05/08/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1297 2842 0
41 HAI DHAR 22/09/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3230 2842 0
42 HAI DHAR 08/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3237 2842 0
43 HAI DHAR 27/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3945 2842 0
44 HAI DHAR 12/11/2020 10 Construction of Internal Road at PaduBah VEC WO 2020 21 3952 2030 0
45 HAI DHAR 08/03/2021 3 Leveling & Filling of Playground at Padu Bah VEC WO 2020 21 7646 609 0
Sub Total FY 2021 83 16849 0
46 HAI DHAR 23/09/2021 2 Construction of Slap Cover at Padubah VEC WO 2021 22 833 452 0
47 HAI DHAR 09/11/2021 7 Construction of side drain at Padubah VEC WO 2021 22 1820 1582 0
48 HAI DHAR 18/01/2022 15 Construction of Footpath Ph II at Padubah VEC WO 2021 22 3814 3390 0
49 HAI DHAR 03/02/2022 16 Construction of Footpath Ph II at Padubah VEC WO 2021 22 3820 3616 0
50 HAI DHAR 21/02/2022 14 Construction of Footpath Ph II at Padubah VEC WO 2021 22 4944 3164 0
51 HAI DHAR 09/03/2022 15 Construction of Footpath Ph II at Padubah VEC WO 2021 22 5001 3390 0
Sub Total FY 2122 69 15594 0