Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/31 Family Id: 31
Name of Head of Household: SMT BRAP POHSHNA
Name of Father/Husband: LATE S MUKHIM
Category: ST
Date of Registration: 1/29/2009
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 31
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 CHANBOR DHAR Male 65
2 BRAP POHSHNA Female 30 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20521 BRAP POHSHNA 05/01/2011~~11/01/2011~~7 7
2 116742 05/01/2011~~11/01/2011~~7 7
3 7357 CHANBOR DHAR 22/07/2011~~29/07/2011~~8 7
4 19226 03/10/2011~~10/10/2011~~8 7
5 11432 02/08/2012~~05/08/2012~~4 4
6 2019 10/07/2013~~25/07/2013~~16 14
7 63650 BRAP POHSHNA 19/10/2015~~03/11/2015~~16 14
8 70246 14/12/2015~~29/12/2015~~16 14
9 76008 06/01/2016~~08/01/2016~~3 3
10 101104 24/02/2016~~10/03/2016~~16 14
11 570 28/04/2016~~05/05/2016~~8 7
12 21250 11/08/2016~~26/08/2016~~16 14
13 30078 29/08/2016~~22/09/2016~~25 22
14 57883 30/09/2016~~30/09/2016~~1 1
15 83358 07/11/2016~~08/12/2016~~32 28
16 109755 21/12/2016~~31/12/2016~~11 10
17 154981 02/03/2017~~23/03/2017~~22 19
18 19301 21/06/2017~~24/06/2017~~4 4
19 22093 29/06/2017~~21/07/2017~~23 20
20 64932 27/09/2017~~10/10/2017~~14 12
21 90058 29/11/2017~~30/12/2017~~32 28
22 127124 06/02/2018~~09/03/2018~~32 28
23 18511 07/05/2018~~15/05/2018~~9 8
24 81609 24/09/2018~~04/11/2018~~42 36
25 191587 12/02/2019~~25/03/2019~~42 36
26 103750 23/09/2019~~24/10/2019~~32 28
27 144934 31/10/2019~~24/11/2019~~25 22
28 199253 13/01/2020~~13/01/2020~~1 1
29 199567 14/01/2020~~14/02/2020~~32 28
30 242170 17/02/2020~~12/03/2020~~25 22
31 61589 20/07/2020~~20/08/2020~~32 28
32 134701 24/09/2020~~25/10/2020~~32 28
33 154663 27/10/2020~~24/11/2020~~29 25
34 279504 05/03/2021~~12/03/2021~~8 7
35 84824 27/09/2021~~03/10/2021~~7 6
36 122231 10/11/2021~~11/12/2021~~32 28

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116742 BRAP POHSHNA 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7357 CHANBOR DHAR 22/07/2011~~29/07/2011~~8 32 const of rcc footpath at Padubad
3 19226 03/10/2011~~10/10/2011~~8 34 const of rcc footpath at Padubad
4 11432 02/08/2012~~05/08/2012~~4 24 const of rcc footpath at Padubad
5 2019 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
6 63650 BRAP POHSHNA 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
7 70246 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 76008 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 101104 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
10 570 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 21250 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
12 30078 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 57883 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 83358 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
15 109755 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 154981 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
17 19301 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
18 22093 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
19 64932 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
20 90058 29/11/2017~~30/12/2017~~32 28 Construction of C C Footpath cum Railing at Padubah VEC 2017-18
21 127124 06/02/2018~~09/03/2018~~32 28 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
22 18511 07/05/2018~~15/05/2018~~9 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
23 81609 24/09/2018~~04/11/2018~~42 36 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10
24 191587 12/02/2019~~25/03/2019~~42 36 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89
25 103750 23/09/2019~~24/10/2019~~32 28 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
26 144934 31/10/2019~~24/11/2019~~25 22 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
27 199253 13/01/2020~~13/01/2020~~1 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
28 199567 14/01/2020~~14/02/2020~~32 28 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400
29 242170 17/02/2020~~12/03/2020~~25 22 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400
30 61589 20/07/2020~~20/08/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
31 134701 24/09/2020~~25/10/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
32 154663 27/10/2020~~24/11/2020~~29 25 Construction of R Wall at Padubah WO 2020 21
33 279504 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
34 84824 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
35 122231 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 BRAP POHSHNA 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 CHANBOR DHAR 22/07/2011 7 const of rcc footpath at Padubad 45709 819 0
3 CHANBOR DHAR 03/10/2011 7 const of rcc footpath at Padubad 65636 700 0
Sub Total FY 1112 14 1519 0
4 CHANBOR DHAR 02/08/2012 4 const of rcc footpath at Padubad 86902 512 0
Sub Total FY 1213 4 512 0
5 CHANBOR DHAR 10/07/2013 14 2101006024/WC/39 109427 2030 0
Sub Total FY 1314 14 2030 0
6 BRAP POHSHNA 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2747 2282 0
7 BRAP POHSHNA 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3046 2119 0
8 BRAP POHSHNA 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3353 489 0
9 BRAP POHSHNA 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4685 2282 0
Sub Total FY 1516 44 7172 0
10 BRAP POHSHNA 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 63 1183 0
11 BRAP POHSHNA 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1148 2197 0
12 BRAP POHSHNA 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1649 2366 0
13 BRAP POHSHNA 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1681 1352 0
14 BRAP POHSHNA 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2514 169 0
15 BRAP POHSHNA 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3442 2366 0
16 BRAP POHSHNA 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3474 2366 0
17 BRAP POHSHNA 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4265 1690 0
18 BRAP POHSHNA 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5520 2366 0
19 BRAP POHSHNA 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5552 845 0
Sub Total FY 1617 100 16900 0
20 BRAP POHSHNA 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 817 700 0
21 BRAP POHSHNA 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1103 2450 0
22 BRAP POHSHNA 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1132 1050 0
23 BRAP POHSHNA 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3829 2100 0
24 BRAP POHSHNA 29/11/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4873 2450 0
25 BRAP POHSHNA 15/12/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4878 2450 0
26 BRAP POHSHNA 06/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6247 2450 0
27 BRAP POHSHNA 22/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6251 2450 0
Sub Total FY 1718 92 16100 0
28 BRAP POHSHNA 07/05/2018 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 465 1400 0
29 BRAP POHSHNA 24/09/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2665 2534 0
30 BRAP POHSHNA 10/10/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2684 2534 0
31 BRAP POHSHNA 26/10/2018 8 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 3179 1448 0
32 BRAP POHSHNA 12/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 5639 2534 0
33 BRAP POHSHNA 28/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6077 2534 0
34 BRAP POHSHNA 16/03/2019 8 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6083 1448 0
Sub Total FY 1819 80 14432 0
35 BRAP POHSHNA 23/09/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1819 2618 0
36 BRAP POHSHNA 09/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1825 2618 0
37 BRAP POHSHNA 31/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3047 2618 0
38 BRAP POHSHNA 16/11/2019 7 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3053 1309 0
39 BRAP POHSHNA 13/01/2020 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 5121 187 0
40 BRAP POHSHNA 14/01/2020 14 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400 5142 2618 0
41 BRAP POHSHNA 30/01/2020 14 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400 5179 2618 0
42 BRAP POHSHNA 17/02/2020 14 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400 6677 2618 0
43 BRAP POHSHNA 04/03/2020 8 Construction of 3 nos Poultry Shed at Padubah VEC WO 2019 20 IF 40400 6678 1496 0
Sub Total FY 1920 100 18700 0
44 BRAP POHSHNA 20/07/2020 14 Construction of R Wall at Padubah WO 2020 21 1281 2842 0
45 BRAP POHSHNA 05/08/2020 14 Construction of R Wall at Padubah WO 2020 21 1323 2842 0
46 BRAP POHSHNA 24/09/2020 14 Construction of R Wall at Padubah WO 2020 21 3301 2842 0
47 BRAP POHSHNA 10/10/2020 13 Construction of R Wall at Padubah WO 2020 21 3307 2639 0
48 BRAP POHSHNA 27/10/2020 14 Construction of R Wall at Padubah WO 2020 21 3973 2842 0
49 BRAP POHSHNA 12/11/2020 10 Construction of R Wall at Padubah WO 2020 21 3979 2030 0
50 BRAP POHSHNA 24/11/2020 1 Construction of R Wall at Padubah WO 2020 21 3985 203 0
51 BRAP POHSHNA 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7635 1421 0
Sub Total FY 2021 87 17661 0
52 BRAP POHSHNA 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 877 1356 0
53 BRAP POHSHNA 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1951 3164 0
Sub Total FY 2122 20 4520 0