Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/267 Family Id: 267
Name of Head of Household: SMT RILANG DHAR
Name of Father/Husband: H MUKHIM
Category: ST
Date of Registration: 4/2/2014
Address: 267
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 267
Epic No.: BZX0555771
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 RILANG DHAR Female 26 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 63950 RILANG DHAR 19/10/2015~~03/11/2015~~16 14
2 70787 14/12/2015~~29/12/2015~~16 14
3 76322 06/01/2016~~08/01/2016~~3 3
4 101340 24/02/2016~~10/03/2016~~16 14
5 768 28/04/2016~~05/05/2016~~8 7
6 21460 11/08/2016~~26/08/2016~~16 14
7 30588 29/08/2016~~22/09/2016~~25 22
8 58380 30/09/2016~~30/09/2016~~1 1
9 83684 07/11/2016~~08/12/2016~~32 28
10 109979 21/12/2016~~31/12/2016~~11 10
11 155194 02/03/2017~~23/03/2017~~22 19
12 19800 21/06/2017~~24/06/2017~~4 4
13 22284 29/06/2017~~21/07/2017~~23 20
14 63841 25/09/2017~~29/10/2017~~35 30
15 127208 06/02/2018~~06/03/2018~~29 25
16 26816 28/05/2018~~28/06/2018~~32 28
17 35697 29/06/2018~~07/07/2018~~9 8
18 172137 28/01/2019~~18/02/2019~~22 19
19 76176 19/08/2019~~19/09/2019~~32 28
20 122956 09/10/2019~~02/11/2019~~25 22
21 204168 15/01/2020~~15/02/2020~~32 28
22 242245 17/02/2020~~12/03/2020~~25 22
23 61309 20/07/2020~~20/08/2020~~32 28
24 132066 22/09/2020~~23/10/2020~~32 28
25 154427 27/10/2020~~23/11/2020~~28 24
26 279881 08/03/2021~~09/03/2021~~2 2
27 82283 23/09/2021~~24/09/2021~~2 2
28 121128 09/11/2021~~16/11/2021~~8 7
29 184924 18/01/2022~~18/02/2022~~32 28
30 223873 21/02/2022~~24/03/2022~~32 28

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 63950 RILANG DHAR 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
2 70787 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
3 76322 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
4 101340 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
5 768 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
6 21460 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
7 30588 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
8 58380 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
9 83684 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
10 109979 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
11 155194 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
12 19800 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
13 22284 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
14 63841 25/09/2017~~29/10/2017~~35 30 Construction of Internal Road Ph. III at Padubah VEC L= 150m W/O 2017-18/RC-32
15 127208 06/02/2018~~06/03/2018~~29 25 Construction of Side Drain at Padubah VEC Length 270m WO 2017-18/FP-96
16 26816 28/05/2018~~28/06/2018~~32 28 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
17 35697 29/06/2018~~07/07/2018~~9 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
18 172137 28/01/2019~~18/02/2019~~22 19 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82
19 76176 19/08/2019~~19/09/2019~~32 28 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632
20 122956 09/10/2019~~02/11/2019~~25 22 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632
21 204168 15/01/2020~~15/02/2020~~32 28 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564
22 242245 17/02/2020~~12/03/2020~~25 22 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564
23 61309 20/07/2020~~20/08/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
24 132066 22/09/2020~~23/10/2020~~32 28 Construction of Internal Road at PaduBah VEC WO 2020 21
25 154427 27/10/2020~~23/11/2020~~28 24 Construction of Internal Road at PaduBah VEC WO 2020 21
26 279881 08/03/2021~~09/03/2021~~2 2 Leveling & Filling of Playground at Padu Bah VEC WO 2020 21
27 82283 23/09/2021~~24/09/2021~~2 2 Construction of Slap Cover at Padubah VEC WO 2021 22
28 121128 09/11/2021~~16/11/2021~~8 7 Construction of side drain at Padubah VEC WO 2021 22
29 184924 18/01/2022~~18/02/2022~~32 28 Construction of Footpath Ph II at Padubah VEC WO 2021 22
30 223873 21/02/2022~~24/03/2022~~32 28 Construction of Footpath Ph II at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 RILANG DHAR 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2744 2282 0
2 RILANG DHAR 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3043 2119 0
3 RILANG DHAR 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3350 489 0
4 RILANG DHAR 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4682 2282 0
Sub Total FY 1516 44 7172 0
5 RILANG DHAR 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 60 1183 0
6 RILANG DHAR 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1145 2197 0
7 RILANG DHAR 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1646 2366 0
8 RILANG DHAR 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1678 1352 0
9 RILANG DHAR 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2511 169 0
10 RILANG DHAR 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3439 2366 0
11 RILANG DHAR 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3471 2366 0
12 RILANG DHAR 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4262 1690 0
13 RILANG DHAR 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5517 2366 0
14 RILANG DHAR 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5549 845 0
Sub Total FY 1617 100 16900 0
15 RILANG DHAR 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 814 700 0
16 RILANG DHAR 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1100 2450 0
17 RILANG DHAR 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1129 1050 0
18 RILANG DHAR 25/09/2017 14 Construction of Internal Road Ph. III at Padubah VEC L= 150m W/O 2017-18/RC-32 3784 2450 0
19 RILANG DHAR 11/10/2017 14 Construction of Internal Road Ph. III at Padubah VEC L= 150m W/O 2017-18/RC-32 3786 2450 0
20 RILANG DHAR 27/10/2017 2 Construction of Internal Road Ph. III at Padubah VEC L= 150m W/O 2017-18/RC-32 4217 350 0
21 RILANG DHAR 06/02/2018 14 Construction of Side Drain at Padubah VEC Length 270m WO 2017-18/FP-96 6266 2450 0
22 RILANG DHAR 22/02/2018 11 Construction of Side Drain at Padubah VEC Length 270m WO 2017-18/FP-96 6270 1925 0
Sub Total FY 1718 79 13825 0
23 RILANG DHAR 28/05/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 881 2534 0
24 RILANG DHAR 13/06/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 897 2534 0
25 RILANG DHAR 29/06/2018 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 1162 1448 0
26 RILANG DHAR 28/01/2019 14 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5081 2534 0
27 RILANG DHAR 13/02/2019 5 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5090 905 0
Sub Total FY 1819 55 9955 0
28 RILANG DHAR 19/08/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 894 2618 0
29 RILANG DHAR 04/09/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 898 2618 0
30 RILANG DHAR 09/10/2019 14 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 2186 2618 0
31 RILANG DHAR 25/10/2019 8 Construction of CC Footpath PH III at Padubah VEC L 594.8m WO 2019 20 RC 35632 2190 1496 0
32 RILANG DHAR 15/01/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 5392 2618 0
33 RILANG DHAR 31/01/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 5396 2618 0
34 RILANG DHAR 17/02/2020 14 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 6693 2618 0
35 RILANG DHAR 04/03/2020 8 Construction of R Wall L 85m at Padubah VEC WO 2019 20 FP 8564 6697 1496 0
Sub Total FY 1920 100 18700 0
36 RILANG DHAR 20/07/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1253 2842 0
37 RILANG DHAR 05/08/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 1295 2842 0
38 RILANG DHAR 22/09/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3228 2842 0
39 RILANG DHAR 08/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3235 2842 0
40 RILANG DHAR 27/10/2020 14 Construction of Internal Road at PaduBah VEC WO 2020 21 3943 2842 0
41 RILANG DHAR 12/11/2020 10 Construction of Internal Road at PaduBah VEC WO 2020 21 3950 2030 0
42 RILANG DHAR 08/03/2021 2 Leveling & Filling of Playground at Padu Bah VEC WO 2020 21 7645 406 0
Sub Total FY 2021 82 16646 0
43 RILANG DHAR 23/09/2021 2 Construction of Slap Cover at Padubah VEC WO 2021 22 832 452 0
44 RILANG DHAR 09/11/2021 7 Construction of side drain at Padubah VEC WO 2021 22 1816 1582 0
45 RILANG DHAR 18/01/2022 15 Construction of Footpath Ph II at Padubah VEC WO 2021 22 3813 3390 0
46 RILANG DHAR 03/02/2022 16 Construction of Footpath Ph II at Padubah VEC WO 2021 22 3819 3616 0
47 RILANG DHAR 21/02/2022 14 Construction of Footpath Ph II at Padubah VEC WO 2021 22 4943 3164 0
48 RILANG DHAR 09/03/2022 15 Construction of Footpath Ph II at Padubah VEC WO 2021 22 5000 3390 0
Sub Total FY 2122 69 15594 0