Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/26 Family Id: 26
Name of Head of Household: CHEDRAK POHSHNA
Name of Father/Husband: PHEL LITING
Category: ST
Date of Registration: 8/20/2007
Address: 26
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 26
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 CHEDRAK POHSHNA Male 19 Meghalaya Co-operative Apex Bank
2 ADALIN POHSHNA Female 25


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20449 CHEDRAK POHSHNA 05/01/2011~~11/01/2011~~7 7
2 116736 05/01/2011~~11/01/2011~~7 7
3 7352 22/07/2011~~29/07/2011~~8 7
4 13004 09/08/2011~~16/08/2011~~8 7
5 19221 03/10/2011~~10/10/2011~~8 7
6 11427 02/08/2012~~05/08/2012~~4 4
7 2014 ADALIN POHSHNA 10/07/2013~~25/07/2013~~16 14
8 63641 CHEDRAK POHSHNA 19/10/2015~~03/11/2015~~16 14
9 70243 14/12/2015~~29/12/2015~~16 14
10 76000 06/01/2016~~08/01/2016~~3 3
11 101099 24/02/2016~~10/03/2016~~16 14
12 567 28/04/2016~~05/05/2016~~8 7
13 21247 11/08/2016~~26/08/2016~~16 14
14 30075 29/08/2016~~22/09/2016~~25 22
15 57875 30/09/2016~~30/09/2016~~1 1
16 83355 07/11/2016~~08/12/2016~~32 28
17 109752 21/12/2016~~31/12/2016~~11 10
18 154978 02/03/2017~~23/03/2017~~22 19
19 19296 21/06/2017~~24/06/2017~~4 4
20 22089 29/06/2017~~21/07/2017~~23 20
21 64927 27/09/2017~~10/10/2017~~14 12
22 90056 29/11/2017~~30/12/2017~~32 28
23 127121 06/02/2018~~09/03/2018~~32 28
24 18509 07/05/2018~~15/05/2018~~9 8
25 81604 24/09/2018~~04/11/2018~~42 36
26 191585 12/02/2019~~25/03/2019~~42 36
27 103743 23/09/2019~~24/10/2019~~32 28
28 144931 31/10/2019~~24/11/2019~~25 22
29 199247 13/01/2020~~13/01/2020~~1 1
30 202888 15/01/2020~~15/02/2020~~32 28
31 243159 18/02/2020~~13/03/2020~~25 22
32 61578 20/07/2020~~20/08/2020~~32 28
33 134703 24/09/2020~~25/10/2020~~32 28
34 154664 27/10/2020~~24/11/2020~~29 25
35 279501 05/03/2021~~12/03/2021~~8 7
36 84823 27/09/2021~~03/10/2021~~7 6
37 122230 10/11/2021~~11/12/2021~~32 28

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116736 CHEDRAK POHSHNA 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7352 22/07/2011~~29/07/2011~~8 32 const of rcc footpath at Padubad
3 13004 09/08/2011~~16/08/2011~~8 25 const of rcc footpath at Padubad
4 19221 03/10/2011~~10/10/2011~~8 27 const of rcc footpath at Padubad
5 11427 02/08/2012~~05/08/2012~~4 24 const of rcc footpath at Padubad
6 2014 ADALIN POHSHNA 10/07/2013~~25/07/2013~~16 42 2101006024/WC/39
7 63641 CHEDRAK POHSHNA 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 70243 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 76000 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
10 101099 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 567 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
12 21247 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 30075 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 57875 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
15 83355 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 109752 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
17 154978 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
18 19296 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
19 22089 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
20 64927 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
21 90056 29/11/2017~~30/12/2017~~32 28 Construction of C C Footpath cum Railing at Padubah VEC 2017-18
22 127121 06/02/2018~~09/03/2018~~32 28 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
23 18509 07/05/2018~~15/05/2018~~9 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
24 81604 24/09/2018~~04/11/2018~~42 36 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10
25 191585 12/02/2019~~25/03/2019~~42 36 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89
26 103743 23/09/2019~~24/10/2019~~32 28 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
27 144931 31/10/2019~~24/11/2019~~25 22 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
28 199247 13/01/2020~~13/01/2020~~1 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
29 202888 15/01/2020~~15/02/2020~~32 28 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
30 243159 18/02/2020~~13/03/2020~~25 22 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
31 61578 20/07/2020~~20/08/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
32 134703 24/09/2020~~25/10/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
33 154664 27/10/2020~~24/11/2020~~29 25 Construction of R Wall at Padubah WO 2020 21
34 279501 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
35 84823 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
36 122230 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 CHEDRAK POHSHNA 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 CHEDRAK POHSHNA 22/07/2011 7 const of rcc footpath at Padubad 45708 819 0
3 CHEDRAK POHSHNA 09/08/2011 7 const of rcc footpath at Padubad 44440 700 0
4 CHEDRAK POHSHNA 03/10/2011 7 const of rcc footpath at Padubad 65635 700 0
Sub Total FY 1112 21 2219 0
5 CHEDRAK POHSHNA 02/08/2012 4 const of rcc footpath at Padubad 86901 512 0
Sub Total FY 1213 4 512 0
6 ADALIN POHSHNA 10/07/2013 14 2101006024/WC/39 109426 2030 0
Sub Total FY 1314 14 2030 0
7 CHEDRAK POHSHNA 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2744 2282 0
8 CHEDRAK POHSHNA 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3043 2119 0
9 CHEDRAK POHSHNA 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3350 489 0
10 CHEDRAK POHSHNA 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4682 2282 0
Sub Total FY 1516 44 7172 0
11 CHEDRAK POHSHNA 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 60 1183 0
12 CHEDRAK POHSHNA 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1145 2197 0
13 CHEDRAK POHSHNA 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1646 2366 0
14 CHEDRAK POHSHNA 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1678 1352 0
15 CHEDRAK POHSHNA 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2511 169 0
16 CHEDRAK POHSHNA 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3439 2366 0
17 CHEDRAK POHSHNA 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3471 2366 0
18 CHEDRAK POHSHNA 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4262 1690 0
19 CHEDRAK POHSHNA 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5517 2366 0
20 CHEDRAK POHSHNA 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5549 845 0
Sub Total FY 1617 100 16900 0
21 CHEDRAK POHSHNA 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 813 700 0
22 CHEDRAK POHSHNA 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1100 2450 0
23 CHEDRAK POHSHNA 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1129 1050 0
24 CHEDRAK POHSHNA 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3827 2100 0
25 CHEDRAK POHSHNA 29/11/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4872 2450 0
26 CHEDRAK POHSHNA 15/12/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4877 2450 0
27 CHEDRAK POHSHNA 06/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6246 2450 0
28 CHEDRAK POHSHNA 22/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6250 2450 0
Sub Total FY 1718 92 16100 0
29 CHEDRAK POHSHNA 07/05/2018 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 464 1400 0
30 CHEDRAK POHSHNA 24/09/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2665 2534 0
31 CHEDRAK POHSHNA 10/10/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2684 2534 0
32 CHEDRAK POHSHNA 26/10/2018 8 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 3178 1448 0
33 CHEDRAK POHSHNA 12/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 5639 2534 0
34 CHEDRAK POHSHNA 28/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6076 2534 0
35 CHEDRAK POHSHNA 16/03/2019 8 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6082 1448 0
Sub Total FY 1819 80 14432 0
36 CHEDRAK POHSHNA 23/09/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1818 2618 0
37 CHEDRAK POHSHNA 09/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1824 2618 0
38 CHEDRAK POHSHNA 31/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3046 2618 0
39 CHEDRAK POHSHNA 16/11/2019 7 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3052 1309 0
40 CHEDRAK POHSHNA 13/01/2020 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 5120 187 0
41 CHEDRAK POHSHNA 15/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5379 2618 0
42 CHEDRAK POHSHNA 31/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5386 2618 0
43 CHEDRAK POHSHNA 18/02/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6744 2618 0
44 CHEDRAK POHSHNA 05/03/2020 8 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6751 1496 0
Sub Total FY 1920 100 18700 0
45 CHEDRAK POHSHNA 20/07/2020 14 Construction of R Wall at Padubah WO 2020 21 1281 2842 0
46 CHEDRAK POHSHNA 05/08/2020 14 Construction of R Wall at Padubah WO 2020 21 1323 2842 0
47 CHEDRAK POHSHNA 24/09/2020 14 Construction of R Wall at Padubah WO 2020 21 3301 2842 0
48 CHEDRAK POHSHNA 10/10/2020 13 Construction of R Wall at Padubah WO 2020 21 3307 2639 0
49 CHEDRAK POHSHNA 27/10/2020 14 Construction of R Wall at Padubah WO 2020 21 3973 2842 0
50 CHEDRAK POHSHNA 12/11/2020 10 Construction of R Wall at Padubah WO 2020 21 3979 2030 0
51 CHEDRAK POHSHNA 24/11/2020 1 Construction of R Wall at Padubah WO 2020 21 3985 203 0
52 CHEDRAK POHSHNA 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7634 1421 0
Sub Total FY 2021 87 17661 0
53 CHEDRAK POHSHNA 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 875 1356 0
54 CHEDRAK POHSHNA 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1950 3164 0
Sub Total FY 2122 20 4520 0