Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 SAPPNA MUKHIM Female 22 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Name of Applicant Month & Date from which employment requested No of Days
1 63920 SAPPNA MUKHIM 19/10/2015~~03/11/2015~~16 14
2 70763 14/12/2015~~29/12/2015~~16 14
3 76300 06/01/2016~~08/01/2016~~3 3
4 101319 24/02/2016~~10/03/2016~~16 14
5 749 28/04/2016~~05/05/2016~~8 7
6 21440 11/08/2016~~26/08/2016~~16 14
7 30568 29/08/2016~~22/09/2016~~25 22
8 58360 30/09/2016~~30/09/2016~~1 1
9 83618 07/11/2016~~08/12/2016~~32 28
10 109959 21/12/2016~~31/12/2016~~11 10
11 155173 02/03/2017~~23/03/2017~~22 19
12 19758 21/06/2017~~24/06/2017~~4 4
13 22264 29/06/2017~~21/07/2017~~23 20
14 65147 27/09/2017~~10/10/2017~~14 12
15 92186 04/12/2017~~04/01/2018~~32 28
16 126955 06/02/2018~~09/03/2018~~32 28
17 154165 21/03/2018~~29/03/2018~~9 8
18 25871 24/05/2018~~04/07/2018~~42 36
19 171775 28/01/2019~~10/03/2019~~42 36
20 216253 11/03/2019~~19/03/2019~~9 8
21 80667 22/08/2019~~22/09/2019~~32 28
22 127349 14/10/2019~~07/11/2019~~25 22
23 197608 13/01/2020~~13/02/2020~~32 28
24 246280 19/02/2020~~14/03/2020~~25 22
25 58085 15/07/2020~~15/08/2020~~32 28
26 99593 24/08/2020~~17/09/2020~~25 22
27 278313 04/03/2021~~27/03/2021~~24 21
28 85287 27/09/2021~~03/10/2021~~7 6
29 122341 10/11/2021~~11/12/2021~~32 28
30 153242 14/12/2021~~29/12/2021~~16 14
31 166950 05/01/2022~~15/01/2022~~11 10

Period and Work on which Employment Offered

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name
1 63920 SAPPNA MUKHIM 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
2 70763 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
3 76300 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
4 101319 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
5 749 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
6 21440 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
7 30568 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
8 58360 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
9 83618 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
10 109959 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
11 155173 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
12 19758 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
13 22264 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
14 65147 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
15 92186 04/12/2017~~04/01/2018~~32 28 Construction of R Wall Ph II at Padubah VEC 2017-18
16 126955 06/02/2018~~09/03/2018~~32 28 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
17 154165 21/03/2018~~29/03/2018~~9 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
18 25871 24/05/2018~~04/07/2018~~42 36 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3
19 171775 28/01/2019~~10/03/2019~~42 36 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
20 216253 11/03/2019~~19/03/2019~~9 8 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
21 80667 22/08/2019~~22/09/2019~~32 28 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
22 127349 14/10/2019~~07/11/2019~~25 22 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
23 197608 13/01/2020~~13/02/2020~~32 28 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565
24 246280 19/02/2020~~14/03/2020~~25 22 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565
25 58085 15/07/2020~~15/08/2020~~32 28 Construction of Poultry Shed at Padubah VEC WO 2020 21
26 99593 24/08/2020~~17/09/2020~~25 22 Construction of Poultry Shed at Padubah VEC WO 2020 21
27 278313 04/03/2021~~27/03/2021~~24 21 Construction of Dug Out Pond at Padubah VEC WO 2020 2021
28 85287 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
29 122341 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22
30 153242 14/12/2021~~29/12/2021~~16 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22
31 166950 05/01/2022~~15/01/2022~~11 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 SAPPNA MUKHIM 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2742 2282 0
2 SAPPNA MUKHIM 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3041 2119 0
3 SAPPNA MUKHIM 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3348 489 0
4 SAPPNA MUKHIM 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4680 2282 0
Sub Total FY 1516 44 7172 0
5 SAPPNA MUKHIM 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 58 1183 0
6 SAPPNA MUKHIM 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1143 2197 0
7 SAPPNA MUKHIM 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1644 2366 0
8 SAPPNA MUKHIM 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1676 1352 0
9 SAPPNA MUKHIM 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2509 169 0
10 SAPPNA MUKHIM 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3437 2366 0
11 SAPPNA MUKHIM 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3469 2366 0
12 SAPPNA MUKHIM 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4260 1690 0
13 SAPPNA MUKHIM 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5515 2366 0
14 SAPPNA MUKHIM 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5547 845 0
Sub Total FY 1617 100 16900 0
15 SAPPNA MUKHIM 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 811 700 0
16 SAPPNA MUKHIM 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1098 2450 0
17 SAPPNA MUKHIM 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1127 1050 0
18 SAPPNA MUKHIM 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3826 2100 0
19 SAPPNA MUKHIM 04/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5018 2450 0
20 SAPPNA MUKHIM 20/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5032 2450 0
21 SAPPNA MUKHIM 06/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6206 2450 0
22 SAPPNA MUKHIM 22/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6213 2450 0
23 SAPPNA MUKHIM 21/03/2018 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 7004 1400 0
Sub Total FY 1718 100 17500 0
24 SAPPNA MUKHIM 24/05/2018 14 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 838 2534 0
25 SAPPNA MUKHIM 09/06/2018 13 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 844 2353 0
26 SAPPNA MUKHIM 24/06/2018 9 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 1034 1629 0
27 SAPPNA MUKHIM 28/01/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5066 2534 0
28 SAPPNA MUKHIM 13/02/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5073 2534 0
29 SAPPNA MUKHIM 11/03/2019 8 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 6423 1448 0
Sub Total FY 1819 72 13032 0
30 SAPPNA MUKHIM 22/08/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 976 2618 0
31 SAPPNA MUKHIM 07/09/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 987 2618 0
32 SAPPNA MUKHIM 14/10/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2290 2618 0
33 SAPPNA MUKHIM 30/10/2019 8 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2301 1496 0
34 SAPPNA MUKHIM 13/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5019 2618 0
35 SAPPNA MUKHIM 29/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5029 2618 0
36 SAPPNA MUKHIM 19/02/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6888 2618 0
37 SAPPNA MUKHIM 06/03/2020 8 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6898 1496 0
Sub Total FY 1920 100 18700 0
38 SAPPNA MUKHIM 15/07/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 1192 2842 0
39 SAPPNA MUKHIM 31/07/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 1193 2842 0
40 SAPPNA MUKHIM 24/08/2020 14 Construction of Poultry Shed at Padubah VEC WO 2020 21 2423 2842 0
41 SAPPNA MUKHIM 09/09/2020 8 Construction of Poultry Shed at Padubah VEC WO 2020 21 2424 1624 0
42 SAPPNA MUKHIM 04/03/2021 14 Construction of Dug Out Pond at Padubah VEC WO 2020 2021 7592 2842 0
43 SAPPNA MUKHIM 20/03/2021 7 Construction of Dug Out Pond at Padubah VEC WO 2020 2021 7600 1421 0
Sub Total FY 2021 71 14413 0
44 SAPPNA MUKHIM 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 874 1356 0
45 SAPPNA MUKHIM 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1949 3164 0
46 SAPPNA MUKHIM 26/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1966 3164 0
47 SAPPNA MUKHIM 14/12/2021 13 Construction of C C Motorable Road at Padubah VEC WO 2021 22 2659 2938 0
48 SAPPNA MUKHIM 05/01/2022 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22 3283 2260 0
Sub Total FY 2122 57 12882 0