Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/226 Family Id: 226
Name of Head of Household: KAMINI SURONG
Name of Father/Husband: L P
Category: ST
Date of Registration: 8/18/2008
Address: 226
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 226
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 KAMINI SURONG Female 20 Meghalaya Co-operative Apex Bank
2 KWIL SURONG Female 50


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20838 KWIL SURONG 05/01/2011~~11/01/2011~~7 7
2 116725 05/01/2011~~11/01/2011~~7 7
3 7538 KAMINI SURONG 22/07/2011~~29/07/2011~~8 7
4 13191 09/08/2011~~16/08/2011~~8 7
5 19409 03/10/2011~~10/10/2011~~8 7
6 2324 10/07/2013~~25/07/2013~~16 14
7 63898 19/10/2015~~03/11/2015~~16 14
8 70747 14/12/2015~~29/12/2015~~16 14
9 76285 06/01/2016~~08/01/2016~~3 3
10 155159 02/03/2017~~23/03/2017~~22 19
11 90091 29/11/2017~~30/12/2017~~32 28
12 127152 06/02/2018~~09/03/2018~~32 28
13 18539 07/05/2018~~15/05/2018~~9 8
14 81754 24/09/2018~~04/11/2018~~42 36
15 191629 12/02/2019~~25/03/2019~~42 36
16 103920 23/09/2019~~24/10/2019~~32 28
17 144982 31/10/2019~~24/11/2019~~25 22
18 199344 13/01/2020~~13/01/2020~~1 1
19 202952 15/01/2020~~15/02/2020~~32 28
20 243111 18/02/2020~~13/03/2020~~25 22
21 61610 20/07/2020~~20/08/2020~~32 28
22 134715 24/09/2020~~25/10/2020~~32 28
23 154673 27/10/2020~~24/11/2020~~29 25
24 233886 01/02/2021~~01/02/2021~~1 1
25 279610 05/03/2021~~12/03/2021~~8 7
26 84858 27/09/2021~~03/10/2021~~7 6
27 121174 09/11/2021~~16/11/2021~~8 7
28 181473 14/01/2022~~14/02/2022~~32 28
29 214762 15/02/2022~~18/03/2022~~32 28
30 266124 21/03/2022~~22/03/2022~~2 2
31 268368 24/03/2022~~24/03/2022~~1 1

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116725 KWIL SURONG 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7538 KAMINI SURONG 22/07/2011~~29/07/2011~~8 32 const of rcc footpath at Padubad
3 13191 09/08/2011~~16/08/2011~~8 34 const of rcc footpath at Padubad
4 19409 03/10/2011~~10/10/2011~~8 30 const of rcc footpath at Padubad
5 2324 10/07/2013~~25/07/2013~~16 56 2101006024/WC/39
6 63898 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
7 70747 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 76285 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 155159 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
10 90091 29/11/2017~~30/12/2017~~32 28 Construction of C C Footpath cum Railing at Padubah VEC 2017-18
11 127152 06/02/2018~~09/03/2018~~32 28 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
12 18539 07/05/2018~~15/05/2018~~9 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111
13 81754 24/09/2018~~04/11/2018~~42 36 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10
14 191629 12/02/2019~~25/03/2019~~42 36 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89
15 103920 23/09/2019~~24/10/2019~~32 28 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
16 144982 31/10/2019~~24/11/2019~~25 22 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
17 199344 13/01/2020~~13/01/2020~~1 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293
18 202952 15/01/2020~~15/02/2020~~32 28 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
19 243111 18/02/2020~~13/03/2020~~25 22 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125
20 61610 20/07/2020~~20/08/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
21 134715 24/09/2020~~25/10/2020~~32 28 Construction of R Wall at Padubah WO 2020 21
22 154673 27/10/2020~~24/11/2020~~29 25 Construction of R Wall at Padubah WO 2020 21
23 233886 01/02/2021~~01/02/2021~~1 1 Construction of R Wall at Padubah WO 2020 21
24 279610 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
25 84858 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
26 121174 09/11/2021~~16/11/2021~~8 7 Construction of side drain at Padubah VEC WO 2021 22
27 181473 14/01/2022~~14/02/2022~~32 28 Construction of side drain at Padubah VEC WO 2021 22
28 214762 15/02/2022~~18/03/2022~~32 28 Construction of side drain at Padubah VEC WO 2021 22
29 266124 21/03/2022~~22/03/2022~~2 2 Construction of side drain at Padubah VEC WO 2021 22
30 268368 24/03/2022~~24/03/2022~~1 1 Construction of side drain at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 KWIL SURONG 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 KAMINI SURONG 22/07/2011 7 const of rcc footpath at Padubad 45727 819 0
3 KAMINI SURONG 09/08/2011 7 const of rcc footpath at Padubad 44451 700 0
4 KAMINI SURONG 03/10/2011 7 const of rcc footpath at Padubad 65654 700 0
Sub Total FY 1112 21 2219 0
5 KAMINI SURONG 10/07/2013 14 2101006024/WC/39 109446 2030 0
Sub Total FY 1314 14 2030 0
6 KAMINI SURONG 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2741 2282 0
7 KAMINI SURONG 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3040 2119 0
8 KAMINI SURONG 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3347 489 0
Sub Total FY 1516 30 4890 0
9 KAMINI SURONG 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5513 2366 0
10 KAMINI SURONG 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5545 845 0
Sub Total FY 1617 19 3211 0
11 KAMINI SURONG 29/11/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4872 2450 0
12 KAMINI SURONG 15/12/2017 14 Construction of C C Footpath cum Railing at Padubah VEC 2017-18 4877 2450 0
13 KAMINI SURONG 06/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6245 2450 0
14 KAMINI SURONG 22/02/2018 14 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 6249 2450 0
Sub Total FY 1718 56 9800 0
15 KAMINI SURONG 07/05/2018 8 Construction of Railing at Padubah VEC Length - 288 m WO:2017-18/FP-111 463 1400 0
16 KAMINI SURONG 24/09/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2664 2534 0
17 KAMINI SURONG 10/10/2018 14 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 2683 2534 0
18 KAMINI SURONG 26/10/2018 8 Construction of Footpath Ph II at Padubah VEC L=120 m W/O 2018-19/RC-10 3177 1448 0
19 KAMINI SURONG 12/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 5638 2534 0
20 KAMINI SURONG 28/02/2019 14 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6075 2534 0
21 KAMINI SURONG 16/03/2019 8 Construction of R Wall Ph IV at Padubah VEC L 100m WO 2018 19 FP 89 6081 1448 0
Sub Total FY 1819 80 14432 0
22 KAMINI SURONG 23/09/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1817 2618 0
23 KAMINI SURONG 09/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 1823 2618 0
24 KAMINI SURONG 31/10/2019 14 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3045 2618 0
25 KAMINI SURONG 16/11/2019 7 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 3051 1309 0
26 KAMINI SURONG 13/01/2020 1 Construction of Compound fencing PH III L 168m at Padubah VEC WO 2019 20 FP 8293 5119 187 0
27 KAMINI SURONG 15/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5378 2618 0
28 KAMINI SURONG 31/01/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 5385 2618 0
29 KAMINI SURONG 18/02/2020 14 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6743 2618 0
30 KAMINI SURONG 05/03/2020 8 Construction of CC Motorable Road L 420m at Padubah VEC WO 2019 20 RC 43125 6750 1496 0
Sub Total FY 1920 100 18700 0
31 KAMINI SURONG 20/07/2020 14 Construction of R Wall at Padubah WO 2020 21 1280 2842 0
32 KAMINI SURONG 05/08/2020 14 Construction of R Wall at Padubah WO 2020 21 1322 2842 0
33 KAMINI SURONG 24/09/2020 14 Construction of R Wall at Padubah WO 2020 21 3300 2842 0
34 KAMINI SURONG 10/10/2020 13 Construction of R Wall at Padubah WO 2020 21 3306 2639 0
35 KAMINI SURONG 27/10/2020 14 Construction of R Wall at Padubah WO 2020 21 3972 2842 0
36 KAMINI SURONG 12/11/2020 10 Construction of R Wall at Padubah WO 2020 21 3978 2030 0
37 KAMINI SURONG 24/11/2020 1 Construction of R Wall at Padubah WO 2020 21 3984 203 0
38 KAMINI SURONG 01/02/2021 1 Construction of R Wall at Padubah WO 2020 21 6570 203 0
39 KAMINI SURONG 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7632 1421 0
Sub Total FY 2021 88 17864 0
40 KAMINI SURONG 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 873 1356 0
41 KAMINI SURONG 09/11/2021 7 Construction of side drain at Padubah VEC WO 2021 22 1815 1582 0
42 KAMINI SURONG 14/01/2022 15 Construction of side drain at Padubah VEC WO 2021 22 3690 3390 0
43 KAMINI SURONG 30/01/2022 16 Construction of side drain at Padubah VEC WO 2021 22 3693 3616 0
44 KAMINI SURONG 15/02/2022 14 Construction of side drain at Padubah VEC WO 2021 22 4848 3164 0
45 KAMINI SURONG 03/03/2022 16 Construction of side drain at Padubah VEC WO 2021 22 4851 3616 0
46 KAMINI SURONG 21/03/2022 2 Construction of side drain at Padubah VEC WO 2021 22 5960 452 0
47 KAMINI SURONG 24/03/2022 1 Construction of side drain at Padubah VEC WO 2021 22 6082 226 0
Sub Total FY 2122 77 17402 0