Job card No.: MG-01-006-024-003/213 Family-Id: 213
Name of Head of Household: RITA MUKHIM
Name of Father/Husband: R SYNGKOR
Category: ST
Date of Registration: 8/18/2008
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
: NO Family-Id: 213
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 RITA MUKHIM Female 28 Meghalaya Co-operative Apex Bank
2 RAJESH SYNKOR Male 27 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Name of Applicant Month & Date from which employment requested No of Days
1 20654 RITA MUKHIM 05/01/2011~~11/01/2011~~7 7
2 116712 05/01/2011~~11/01/2011~~7 7
3 7525 22/07/2011~~29/07/2011~~8 7
4 13178 09/08/2011~~16/08/2011~~8 7
5 19396 03/10/2011~~10/10/2011~~8 7
6 2311 10/07/2013~~25/07/2013~~16 14
7 63879 19/10/2015~~03/11/2015~~16 14
8 70733 14/12/2015~~29/12/2015~~16 14
9 76271 06/01/2016~~08/01/2016~~3 3
10 101291 24/02/2016~~10/03/2016~~16 14
11 726 28/04/2016~~05/05/2016~~8 7
12 21416 11/08/2016~~26/08/2016~~16 14
13 30544 29/08/2016~~22/09/2016~~25 22
14 58319 30/09/2016~~30/09/2016~~1 1
15 83577 07/11/2016~~08/12/2016~~32 28
16 109936 21/12/2016~~31/12/2016~~11 10
17 155148 02/03/2017~~23/03/2017~~22 19
18 19700 21/06/2017~~24/06/2017~~4 4
19 22242 29/06/2017~~21/07/2017~~23 20
20 65151 27/09/2017~~10/10/2017~~14 12
21 92188 04/12/2017~~04/01/2018~~32 28
22 126958 06/02/2018~~09/03/2018~~32 28
23 154167 21/03/2018~~29/03/2018~~9 8
24 25872 24/05/2018~~04/07/2018~~42 36
25 171778 RAJESH SYNKOR 28/01/2019~~17/02/2019~~21 18
26 171777 RITA MUKHIM 28/01/2019~~17/02/2019~~21 18
27 80668 22/08/2019~~22/09/2019~~32 28
28 127350 14/10/2019~~07/11/2019~~25 22
29 197609 13/01/2020~~13/02/2020~~32 28
30 246275 19/02/2020~~14/03/2020~~25 22
31 61840 20/07/2020~~20/08/2020~~32 28
32 135859 24/09/2020~~25/10/2020~~32 28
33 154862 27/10/2020~~24/11/2020~~29 25
34 279602 05/03/2021~~12/03/2021~~8 7
35 85291 27/09/2021~~03/10/2021~~7 6
36 122342 10/11/2021~~11/12/2021~~32 28
37 153243 14/12/2021~~29/12/2021~~16 14
38 166934 05/01/2022~~15/01/2022~~11 10

Period and Work on which Employment Offered

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116712 RITA MUKHIM 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7525 22/07/2011~~29/07/2011~~8 33 const of rcc footpath at Padubad
3 13178 09/08/2011~~16/08/2011~~8 34 const of rcc footpath at Padubad
4 19396 03/10/2011~~10/10/2011~~8 34 const of rcc footpath at Padubad
5 2311 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
6 63879 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
7 70733 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 76271 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 101291 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
10 726 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 21416 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
12 30544 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 58319 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 83577 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
15 109936 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 155148 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
17 19700 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
18 22242 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
19 65151 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
20 92188 04/12/2017~~04/01/2018~~32 28 Construction of R Wall Ph II at Padubah VEC 2017-18
21 126958 06/02/2018~~09/03/2018~~32 28 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
22 154167 21/03/2018~~29/03/2018~~9 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
23 25872 24/05/2018~~04/07/2018~~42 36 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3
24 171778 RAJESH SYNKOR 28/01/2019~~17/02/2019~~21 18 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
25 171777 RITA MUKHIM 28/01/2019~~17/02/2019~~21 18 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
26 80668 22/08/2019~~22/09/2019~~32 28 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
27 127350 14/10/2019~~07/11/2019~~25 22 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
28 197609 13/01/2020~~13/02/2020~~32 28 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565
29 246275 19/02/2020~~14/03/2020~~25 22 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565
30 61840 20/07/2020~~20/08/2020~~32 28 Construction of Compound Fencing at Padubah VEC WO 2020 21
31 135859 24/09/2020~~25/10/2020~~32 28 Construction of Compound Fencing at Padubah VEC WO 2020 21
32 154862 27/10/2020~~24/11/2020~~29 25 Construction of Compound Fencing at Padubah VEC WO 2020 21
33 279602 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
34 85291 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
35 122342 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22
36 153243 14/12/2021~~29/12/2021~~16 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22
37 166934 05/01/2022~~15/01/2022~~11 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 RITA MUKHIM 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 RITA MUKHIM 22/07/2011 7 const of rcc footpath at Padubad 45725 819 0
3 RITA MUKHIM 09/08/2011 7 const of rcc footpath at Padubad 44451 700 0
4 RITA MUKHIM 03/10/2011 7 const of rcc footpath at Padubad 65653 700 0
Sub Total FY 1112 21 2219 0
5 RITA MUKHIM 10/07/2013 14 2101006024/WC/39 109445 2030 0
Sub Total FY 1314 14 2030 0
6 RITA MUKHIM 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2740 2282 0
7 RITA MUKHIM 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3039 2119 0
8 RITA MUKHIM 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3346 489 0
9 RITA MUKHIM 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4678 2282 0
Sub Total FY 1516 44 7172 0
10 RITA MUKHIM 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 56 1183 0
11 RITA MUKHIM 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1140 2197 0
12 RITA MUKHIM 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1641 2366 0
13 RITA MUKHIM 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1673 1352 0
14 RITA MUKHIM 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2506 169 0
15 RITA MUKHIM 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3434 2366 0
16 RITA MUKHIM 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3466 2366 0
17 RITA MUKHIM 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4257 1690 0
18 RITA MUKHIM 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5512 2366 0
19 RITA MUKHIM 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5544 845 0
Sub Total FY 1617 100 16900 0
20 RITA MUKHIM 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 809 700 0
21 RITA MUKHIM 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1095 2450 0
22 RITA MUKHIM 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1124 1050 0
23 RITA MUKHIM 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3824 2100 0
24 RITA MUKHIM 04/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5017 2450 0
25 RITA MUKHIM 20/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5031 2450 0
26 RITA MUKHIM 06/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6205 2450 0
27 RITA MUKHIM 22/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6212 2450 0
28 RITA MUKHIM 21/03/2018 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 7004 1400 0
Sub Total FY 1718 100 17500 0
29 RITA MUKHIM 24/05/2018 14 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 838 2534 0
30 RITA MUKHIM 09/06/2018 13 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 844 2353 0
31 RITA MUKHIM 24/06/2018 9 Construction of Drainage PH-III at Padu Bah Vec L=133 Mtrs /2018-19/FP-3 1034 1629 0
32 RAJESH SYNKOR 28/01/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5066 2534 0
33 RITA MUKHIM 28/01/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5066 2534 0
34 RAJESH SYNKOR 28/01/2019 4 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5073 724 0
35 RITA MUKHIM 28/01/2019 4 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5073 724 0
Sub Total FY 1819 72 13032 0
36 RITA MUKHIM 22/08/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 975 2618 0
37 RITA MUKHIM 07/09/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 986 2618 0
38 RITA MUKHIM 14/10/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2289 2618 0
39 RITA MUKHIM 30/10/2019 8 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2300 1496 0
40 RITA MUKHIM 13/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5019 2618 0
41 RITA MUKHIM 29/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5029 2618 0
42 RITA MUKHIM 19/02/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6888 2618 0
43 RITA MUKHIM 06/03/2020 8 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6898 1496 0
Sub Total FY 1920 100 18700 0
44 RITA MUKHIM 20/07/2020 14 Construction of Compound Fencing at Padubah VEC WO 2020 21 1286 2842 0
45 RITA MUKHIM 05/08/2020 14 Construction of Compound Fencing at Padubah VEC WO 2020 21 1328 2842 0
46 RITA MUKHIM 24/09/2020 14 Construction of Compound Fencing at Padubah VEC WO 2020 21 3343 2842 0
47 RITA MUKHIM 10/10/2020 13 Construction of Compound Fencing at Padubah VEC WO 2020 21 3349 2639 0
48 RITA MUKHIM 27/10/2020 14 Construction of Compound Fencing at Padubah VEC WO 2020 21 4016 2842 0
49 RITA MUKHIM 12/11/2020 11 Construction of Compound Fencing at Padubah VEC WO 2020 21 4022 2233 0
50 RITA MUKHIM 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7631 1421 0
Sub Total FY 2021 87 17661 0
51 RITA MUKHIM 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 872 1356 0
52 RITA MUKHIM 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1948 3164 0
53 RITA MUKHIM 26/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1965 3164 0
54 RITA MUKHIM 14/12/2021 13 Construction of C C Motorable Road at Padubah VEC WO 2021 22 2658 2938 0
55 RITA MUKHIM 05/01/2022 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22 3282 2260 0
Sub Total FY 2122 57 12882 0