Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/198 Family Id: 198
Name of Head of Household: SHRI KETAR POHSHNA
Name of Father/Husband: LATE MUKHIM
Category: ST
Date of Registration: 4/1/2013
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 198
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 MM Female 21
2 KETAR POHSHNA Male 20 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 2346 MM 10/07/2013~~25/07/2013~~16 14
2 63860 KETAR POHSHNA 19/10/2015~~03/11/2015~~16 14
3 70718 14/12/2015~~29/12/2015~~16 14
4 76253 06/01/2016~~08/01/2016~~3 3
5 101276 24/02/2016~~10/03/2016~~16 14
6 713 28/04/2016~~05/05/2016~~8 7
7 21403 11/08/2016~~26/08/2016~~16 14
8 30531 29/08/2016~~22/09/2016~~25 22
9 58284 30/09/2016~~30/09/2016~~1 1
10 83564 07/11/2016~~08/12/2016~~32 28
11 109923 21/12/2016~~31/12/2016~~11 10
12 155136 02/03/2017~~23/03/2017~~22 19
13 19675 21/06/2017~~24/06/2017~~4 4
14 22228 29/06/2017~~21/07/2017~~23 20
15 65142 27/09/2017~~10/10/2017~~14 12
16 92180 04/12/2017~~04/01/2018~~32 28
17 26790 28/05/2018~~28/06/2018~~32 28
18 35675 29/06/2018~~07/07/2018~~9 8
19 58304 13/08/2018~~19/08/2018~~7 6
20 172068 28/01/2019~~18/02/2019~~22 19
21 79760 21/08/2019~~21/09/2019~~32 28
22 100786 23/09/2019~~03/10/2019~~11 10
23 127685 14/10/2019~~07/11/2019~~25 22
24 222110 30/01/2020~~01/03/2020~~32 28
25 259853 04/03/2020~~12/03/2020~~9 8
26 61436 20/07/2020~~20/08/2020~~32 28
27 135699 24/09/2020~~25/10/2020~~32 28
28 154799 27/10/2020~~24/11/2020~~29 25
29 279589 05/03/2021~~12/03/2021~~8 7
30 85490 27/09/2021~~01/10/2021~~5 5
31 122022 10/11/2021~~11/12/2021~~32 28
32 152605 14/12/2021~~29/12/2021~~16 14
33 166319 05/01/2022~~18/01/2022~~14 12

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 2346 MM 10/07/2013~~25/07/2013~~16 56 2101006024/WC/39
2 63860 KETAR POHSHNA 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
3 70718 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
4 76253 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
5 101276 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
6 713 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
7 21403 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
8 30531 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
9 58284 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
10 83564 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
11 109923 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
12 155136 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
13 19675 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
14 22228 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
15 65142 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
16 92180 04/12/2017~~04/01/2018~~32 28 Construction of R Wall Ph II at Padubah VEC 2017-18
17 26790 28/05/2018~~28/06/2018~~32 28 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
18 35675 29/06/2018~~07/07/2018~~9 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5
19 58304 13/08/2018~~19/08/2018~~7 6 Construction of Anganwadi Centre at Padubah VEC A=70 msq with ICDS W/O 2018-19/AV-18
20 172068 28/01/2019~~18/02/2019~~22 19 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82
21 79760 21/08/2019~~21/09/2019~~32 28 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016
22 100786 23/09/2019~~03/10/2019~~11 10 Construction of Spring Shed at Padubah VEC WO 2019 20 WC 12150
23 127685 14/10/2019~~07/11/2019~~25 22 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016
24 222110 30/01/2020~~01/03/2020~~32 28 Construction of Drinking Well at Padubah VEC WO 2019 20 WC 17333
25 259853 04/03/2020~~12/03/2020~~9 8 Construction of Drinking Well at Padubah VEC WO 2019 20 WC 17333
26 61436 20/07/2020~~20/08/2020~~32 28 Construction of Railing at Padubah VEC WO 2020 21
27 135699 24/09/2020~~25/10/2020~~32 28 Construction of Railing at Padubah VEC WO 2020 21
28 154799 27/10/2020~~24/11/2020~~29 25 Construction of Railing at Padubah VEC WO 2020 21
29 279589 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
30 85490 27/09/2021~~01/10/2021~~5 5 Improvement of Community Pond Ph I WO 2021 22
31 122022 10/11/2021~~11/12/2021~~32 28 Construction of Footpath at Padubah VEC WO 2021 22
32 152605 14/12/2021~~29/12/2021~~16 14 Construction of Footpath at Padubah VEC WO 2021 22
33 166319 05/01/2022~~18/01/2022~~14 12 Construction of Footpath at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 MM 10/07/2013 14 2101006024/WC/39 109443 2030 0
Sub Total FY 1314 14 2030 0
2 KETAR POHSHNA 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2738 2282 0
3 KETAR POHSHNA 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3037 2119 0
4 KETAR POHSHNA 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3344 489 0
5 KETAR POHSHNA 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4676 2282 0
Sub Total FY 1516 44 7172 0
6 KETAR POHSHNA 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 54 1183 0
7 KETAR POHSHNA 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1139 2197 0
8 KETAR POHSHNA 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1640 2366 0
9 KETAR POHSHNA 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1672 1352 0
10 KETAR POHSHNA 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2505 169 0
11 KETAR POHSHNA 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3433 2366 0
12 KETAR POHSHNA 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3465 2366 0
13 KETAR POHSHNA 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4256 1690 0
14 KETAR POHSHNA 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5510 2366 0
15 KETAR POHSHNA 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5542 845 0
Sub Total FY 1617 100 16900 0
16 KETAR POHSHNA 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 807 700 0
17 KETAR POHSHNA 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1094 2450 0
18 KETAR POHSHNA 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1123 1050 0
19 KETAR POHSHNA 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3823 2100 0
20 KETAR POHSHNA 04/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5017 2450 0
21 KETAR POHSHNA 20/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5031 2450 0
Sub Total FY 1718 64 11200 0
22 KETAR POHSHNA 28/05/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 880 2534 0
23 KETAR POHSHNA 13/06/2018 14 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 896 2534 0
24 KETAR POHSHNA 29/06/2018 8 Construction of R/W at Padubah VEC PH-III L= 326 m W/O 2018-19/FP-5 1161 1448 0
25 KETAR POHSHNA 13/08/2018 6 Construction of Anganwadi Centre at Padubah VEC A=70 msq with ICDS W/O 2018-19/AV-18 2219 1086 0
26 KETAR POHSHNA 28/01/2019 14 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5080 2534 0
27 KETAR POHSHNA 13/02/2019 5 Construction of R Wall cum fencing at Padubah VEC L 80m WO 2018 19 FP 82 5089 905 0
Sub Total FY 1819 61 11041 0
28 KETAR POHSHNA 21/08/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 937 2618 0
29 KETAR POHSHNA 06/09/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 946 2618 0
30 KETAR POHSHNA 23/09/2019 10 Construction of Spring Shed at Padubah VEC WO 2019 20 WC 12150 1575 1870 0
31 KETAR POHSHNA 14/10/2019 14 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 2308 2618 0
32 KETAR POHSHNA 30/10/2019 8 Construction of Compound fencing PH IV at Padubah VEC WO 2019 20 FP 8016 2317 1496 0
33 KETAR POHSHNA 30/01/2020 14 Construction of Drinking Well at Padubah VEC WO 2019 20 WC 17333 5993 2618 0
34 KETAR POHSHNA 15/02/2020 13 Construction of Drinking Well at Padubah VEC WO 2019 20 WC 17333 5996 2431 0
35 KETAR POHSHNA 04/03/2020 8 Construction of Drinking Well at Padubah VEC WO 2019 20 WC 17333 7292 1496 0
Sub Total FY 1920 95 17765 0
36 KETAR POHSHNA 20/07/2020 14 Construction of Railing at Padubah VEC WO 2020 21 1266 2842 0
37 KETAR POHSHNA 05/08/2020 14 Construction of Railing at Padubah VEC WO 2020 21 1308 2842 0
38 KETAR POHSHNA 24/09/2020 14 Construction of Railing at Padubah VEC WO 2020 21 3332 2842 0
39 KETAR POHSHNA 10/10/2020 13 Construction of Railing at Padubah VEC WO 2020 21 3336 2639 0
40 KETAR POHSHNA 27/10/2020 14 Construction of Railing at Padubah VEC WO 2020 21 4007 2842 0
41 KETAR POHSHNA 12/11/2020 11 Construction of Railing at Padubah VEC WO 2020 21 4011 2233 0
42 KETAR POHSHNA 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7630 1421 0
Sub Total FY 2021 87 17661 0
43 KETAR POHSHNA 27/09/2021 5 Improvement of Community Pond Ph I WO 2021 22 871 1130 0
44 KETAR POHSHNA 10/11/2021 14 Construction of Footpath at Padubah VEC WO 2021 22 1891 3164 0
45 KETAR POHSHNA 26/11/2021 14 Construction of Footpath at Padubah VEC WO 2021 22 1899 3164 0
46 KETAR POHSHNA 14/12/2021 13 Construction of Footpath at Padubah VEC WO 2021 22 2647 2938 0
47 KETAR POHSHNA 05/01/2022 11 Construction of Footpath at Padubah VEC WO 2021 22 3226 2486 0
Sub Total FY 2122 57 12882 0