Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/162 Family Id: 162
Name of Head of Household: SHRI DO KHONGLAH
Name of Father/Husband: LATE R KHONGLAH
Category: ST
Date of Registration: 8/20/2007
Address: 162
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 162
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 DO KHONGLAH Male 32
2 HEI KHONGLAH Male 26
3 BIDAL KHONGLAH Female 26


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 21073 BIDAL KHONGLAH 05/01/2011~~11/01/2011~~7 7
2 116661 05/01/2011~~11/01/2011~~7 7
3 7478 DO KHONGLAH 22/07/2011~~29/07/2011~~8 7
4 13131 09/08/2011~~16/08/2011~~8 7
5 19349 03/10/2011~~10/10/2011~~8 7
6 2264 10/07/2013~~25/07/2013~~16 14
7 63810 19/10/2015~~03/11/2015~~16 14
8 70668 14/12/2015~~29/12/2015~~16 14
9 76189 06/01/2016~~08/01/2016~~3 3
10 101238 24/02/2016~~10/03/2016~~16 14
11 681 28/04/2016~~05/05/2016~~8 7
12 21370 11/08/2016~~26/08/2016~~16 14
13 30498 29/08/2016~~22/09/2016~~25 22
14 58251 30/09/2016~~30/09/2016~~1 1
15 83530 07/11/2016~~08/12/2016~~32 28
16 109890 21/12/2016~~31/12/2016~~11 10
17 155103 02/03/2017~~23/03/2017~~22 19
18 19629 21/06/2017~~24/06/2017~~4 4
19 22202 29/06/2017~~21/07/2017~~23 20
20 65037 27/09/2017~~10/10/2017~~14 12
21 92116 04/12/2017~~04/01/2018~~32 28
22 126928 06/02/2018~~09/03/2018~~32 28
23 154143 21/03/2018~~29/03/2018~~9 8
24 171714 28/01/2019~~17/02/2019~~21 18
25 171715 HEI KHONGLAH 28/01/2019~~17/02/2019~~21 18
26 13625 DO KHONGLAH 29/04/2019~~14/05/2019~~16 14
27 13626 HEI KHONGLAH 29/04/2019~~14/05/2019~~16 14
28 21493 DO KHONGLAH 22/05/2019~~25/05/2019~~4 4
29 21494 HEI KHONGLAH 22/05/2019~~25/05/2019~~4 4
30 80686 DO KHONGLAH 22/08/2019~~22/09/2019~~32 28
31 127361 14/10/2019~~07/11/2019~~25 22
32 61505 20/07/2020~~20/08/2020~~32 28
33 135110 24/09/2020~~25/10/2020~~32 28
34 154698 27/10/2020~~24/11/2020~~29 25
35 279555 05/03/2021~~12/03/2021~~8 7
36 85311 27/09/2021~~03/10/2021~~7 6
37 122469 10/11/2021~~11/12/2021~~32 28
38 153444 14/12/2021~~29/12/2021~~16 14
39 166899 05/01/2022~~15/01/2022~~11 10

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116661 BIDAL KHONGLAH 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7478 DO KHONGLAH 22/07/2011~~29/07/2011~~8 34 const of rcc footpath at Padubad
3 13131 09/08/2011~~16/08/2011~~8 34 const of rcc footpath at Padubad
4 19349 03/10/2011~~10/10/2011~~8 34 const of rcc footpath at Padubad
5 2264 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
6 63810 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
7 70668 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 76189 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 101238 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
10 681 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 21370 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
12 30498 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 58251 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 83530 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
15 109890 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 155103 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
17 19629 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
18 22202 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
19 65037 27/09/2017~~10/10/2017~~14 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47
20 92116 04/12/2017~~04/01/2018~~32 28 Construction of R Wall Ph II at Padubah VEC 2017-18
21 126928 06/02/2018~~09/03/2018~~32 28 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
22 154143 21/03/2018~~29/03/2018~~9 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25
23 171714 28/01/2019~~17/02/2019~~21 18 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
24 171715 HEI KHONGLAH 28/01/2019~~17/02/2019~~21 18 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
25 13625 DO KHONGLAH 29/04/2019~~14/05/2019~~16 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
26 13626 HEI KHONGLAH 29/04/2019~~14/05/2019~~16 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
27 21493 DO KHONGLAH 22/05/2019~~25/05/2019~~4 4 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
28 21494 HEI KHONGLAH 22/05/2019~~25/05/2019~~4 4 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83
29 80686 DO KHONGLAH 22/08/2019~~22/09/2019~~32 28 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
30 127361 14/10/2019~~07/11/2019~~25 22 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
31 61505 20/07/2020~~20/08/2020~~32 28 Construction of R Wall at Padubah VEC WO 2020 21
32 135110 24/09/2020~~25/10/2020~~32 28 Construction of R Wall at Padubah VEC WO 2020 21
33 154698 27/10/2020~~24/11/2020~~29 25 Construction of R Wall at Padubah VEC WO 2020 21
34 279555 05/03/2021~~12/03/2021~~8 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21
35 85311 27/09/2021~~03/10/2021~~7 6 Improvement of Community Pond Ph I WO 2021 22
36 122469 10/11/2021~~11/12/2021~~32 28 Construction of C C Motorable Road at Padubah VEC WO 2021 22
37 153444 14/12/2021~~29/12/2021~~16 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22
38 166899 05/01/2022~~15/01/2022~~11 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 BIDAL KHONGLAH 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 DO KHONGLAH 22/07/2011 7 const of rcc footpath at Padubad 45721 819 0
3 DO KHONGLAH 09/08/2011 7 const of rcc footpath at Padubad 44450 700 0
4 DO KHONGLAH 03/10/2011 7 const of rcc footpath at Padubad 65648 700 0
Sub Total FY 1112 21 2219 0
5 DO KHONGLAH 10/07/2013 14 2101006024/WC/39 109440 2030 0
Sub Total FY 1314 14 2030 0
6 DO KHONGLAH 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2734 2282 0
7 DO KHONGLAH 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3033 2119 0
8 DO KHONGLAH 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3340 489 0
9 DO KHONGLAH 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4672 2282 0
Sub Total FY 1516 44 7172 0
10 DO KHONGLAH 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 50 1183 0
11 DO KHONGLAH 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1135 2197 0
12 DO KHONGLAH 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1636 2366 0
13 DO KHONGLAH 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1668 1352 0
14 DO KHONGLAH 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2501 169 0
15 DO KHONGLAH 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3429 2366 0
16 DO KHONGLAH 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3461 2366 0
17 DO KHONGLAH 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4252 1690 0
18 DO KHONGLAH 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5507 2366 0
19 DO KHONGLAH 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5539 845 0
Sub Total FY 1617 100 16900 0
20 DO KHONGLAH 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 804 700 0
21 DO KHONGLAH 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1091 2450 0
22 DO KHONGLAH 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1120 1050 0
23 DO KHONGLAH 27/09/2017 12 Cnstruction of R/Wall Ph-I at Padubah VEC L=360 m W/O 2017-18/FP-47 3821 2100 0
24 DO KHONGLAH 04/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5015 2450 0
25 DO KHONGLAH 20/12/2017 14 Construction of R Wall Ph II at Padubah VEC 2017-18 5029 2450 0
26 DO KHONGLAH 06/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6204 2450 0
27 DO KHONGLAH 22/02/2018 14 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 6211 2450 0
28 DO KHONGLAH 21/03/2018 8 Construction of Check Dam at Padubah VEC Length 14 m WO:2017-18/WC-25 7002 1400 0
Sub Total FY 1718 100 17500 0
29 DO KHONGLAH 28/01/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5064 2534 0
30 HEI KHONGLAH 28/01/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 5064 2534 0
Sub Total FY 1819 28 5068 0
31 DO KHONGLAH 29/04/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 105 2618 0
32 HEI KHONGLAH 29/04/2019 14 Construction of Slab Cover at Padubah VEC L 190 m WO 2018 19 FP 83 105 2618 0
33 DO KHONGLAH 22/08/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 973 2618 0
34 DO KHONGLAH 07/09/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 984 2618 0
35 DO KHONGLAH 14/10/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2287 2618 0
36 DO KHONGLAH 30/10/2019 8 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2298 1496 0
Sub Total FY 1920 78 14586 0
37 DO KHONGLAH 20/07/2020 14 Construction of R Wall at Padubah VEC WO 2020 21 1271 2842 0
38 DO KHONGLAH 05/08/2020 14 Construction of R Wall at Padubah VEC WO 2020 21 1313 2842 0
39 DO KHONGLAH 24/09/2020 14 Construction of R Wall at Padubah VEC WO 2020 21 3311 2842 0
40 DO KHONGLAH 10/10/2020 13 Construction of R Wall at Padubah VEC WO 2020 21 3316 2639 0
41 DO KHONGLAH 27/10/2020 14 Construction of R Wall at Padubah VEC WO 2020 21 3990 2842 0
42 DO KHONGLAH 12/11/2020 11 Construction of R Wall at Padubah VEC WO 2020 21 3995 2233 0
43 DO KHONGLAH 05/03/2021 7 Construction of Check Dam convergence with MBDA at Padu Bah VEC WO 2020 21 7628 1421 0
Sub Total FY 2021 87 17661 0
44 DO KHONGLAH 27/09/2021 6 Improvement of Community Pond Ph I WO 2021 22 868 1356 0
45 DO KHONGLAH 10/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1945 3164 0
46 DO KHONGLAH 26/11/2021 14 Construction of C C Motorable Road at Padubah VEC WO 2021 22 1962 3164 0
47 DO KHONGLAH 14/12/2021 13 Construction of C C Motorable Road at Padubah VEC WO 2021 22 2655 2938 0
48 DO KHONGLAH 05/01/2022 10 Construction of C C Motorable Road at Padubah VEC WO 2021 22 3279 2260 0
Sub Total FY 2122 57 12882 0