Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-024-003/122 Family Id: 122
Name of Head of Household: SHRI SIANG POHSHNA
Name of Father/Husband: LATE B MUKHIM
Category: ST
Date of Registration: 9/1/2009
Address:
Villages:
Panchayat: Padu Masku
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 122
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 NIK LARPIH Male 22
2 SIANG POHSHNA Male 22 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 20451 SIANG POHSHNA 05/01/2011~~11/01/2011~~7 7
2 116622 05/01/2011~~11/01/2011~~7 7
3 7442 NIK LARPIH 22/07/2011~~29/07/2011~~8 7
4 13094 09/08/2011~~16/08/2011~~8 7
5 19312 03/10/2011~~10/10/2011~~8 7
6 11518 02/08/2012~~05/08/2012~~4 4
7 2227 10/07/2013~~25/07/2013~~16 14
8 63759 SIANG POHSHNA 19/10/2015~~03/11/2015~~16 14
9 70340 14/12/2015~~29/12/2015~~16 14
10 76136 06/01/2016~~08/01/2016~~3 3
11 101198 24/02/2016~~10/03/2016~~16 14
12 648 28/04/2016~~05/05/2016~~8 7
13 21333 11/08/2016~~26/08/2016~~16 14
14 30461 29/08/2016~~22/09/2016~~25 22
15 58214 30/09/2016~~30/09/2016~~1 1
16 83472 07/11/2016~~08/12/2016~~32 28
17 109853 21/12/2016~~31/12/2016~~11 10
18 155067 02/03/2017~~23/03/2017~~22 19
19 19592 21/06/2017~~24/06/2017~~4 4
20 22170 29/06/2017~~21/07/2017~~23 20
21 70268 09/10/2017~~01/11/2017~~24 21
22 151465 19/03/2018~~30/03/2018~~12 11
23 2640 03/04/2018~~04/05/2018~~32 28
24 21146 14/05/2018~~16/05/2018~~3 3
25 58198 13/08/2018~~23/09/2018~~42 36
26 111218 05/11/2018~~13/11/2018~~9 8
27 171545 28/01/2019~~28/02/2019~~32 28
28 215241 11/03/2019~~15/03/2019~~5 5
29 13637 29/04/2019~~01/05/2019~~3 3
30 80624 22/08/2019~~22/09/2019~~32 28
31 127298 14/10/2019~~07/11/2019~~25 22
32 197774 13/01/2020~~13/02/2020~~32 28
33 246008 19/02/2020~~11/03/2020~~22 19

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 116622 SIANG POHSHNA 05/01/2011~~11/01/2011~~7 7 const of rcc footpath at Padubad
2 7442 NIK LARPIH 22/07/2011~~29/07/2011~~8 34 const of rcc footpath at Padubad
3 13094 09/08/2011~~16/08/2011~~8 25 const of rcc footpath at Padubad
4 19312 03/10/2011~~10/10/2011~~8 34 const of rcc footpath at Padubad
5 11518 02/08/2012~~05/08/2012~~4 20 const of rcc footpath at Padubad
6 2227 10/07/2013~~25/07/2013~~16 49 2101006024/WC/39
7 63759 SIANG POHSHNA 19/10/2015~~03/11/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
8 70340 14/12/2015~~29/12/2015~~16 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
9 76136 06/01/2016~~08/01/2016~~3 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16
10 101198 24/02/2016~~10/03/2016~~16 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
11 648 28/04/2016~~05/05/2016~~8 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124
12 21333 11/08/2016~~26/08/2016~~16 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
13 30461 29/08/2016~~22/09/2016~~25 22 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
14 58214 30/09/2016~~30/09/2016~~1 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57
15 83472 07/11/2016~~08/12/2016~~32 28 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
16 109853 21/12/2016~~31/12/2016~~11 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13
17 155067 02/03/2017~~23/03/2017~~22 19 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174
18 19592 21/06/2017~~24/06/2017~~4 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42
19 22170 29/06/2017~~21/07/2017~~23 20 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17
20 70268 09/10/2017~~01/11/2017~~24 21 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34
21 151465 19/03/2018~~30/03/2018~~12 11 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
22 2640 03/04/2018~~04/05/2018~~32 28 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
23 21146 14/05/2018~~16/05/2018~~3 3 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104
24 58198 13/08/2018~~23/09/2018~~42 36 Construction of Compound Fencing at Padubah VEC L=150m W/O 2018-19/FP-29
25 111218 05/11/2018~~13/11/2018~~9 8 Construction of Compound Fencing at Padubah VEC L=150m W/O 2018-19/FP-29
26 171545 28/01/2019~~28/02/2019~~32 28 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60
27 215241 11/03/2019~~15/03/2019~~5 5 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60
28 13637 29/04/2019~~01/05/2019~~3 3 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60
29 80624 22/08/2019~~22/09/2019~~32 28 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
30 127298 14/10/2019~~07/11/2019~~25 22 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836
31 197774 13/01/2020~~13/02/2020~~32 28 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565
32 246008 19/02/2020~~11/03/2020~~22 19 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 SIANG POHSHNA 05/01/2011 7 const of rcc footpath at Padubad 41941 700 0
Sub Total FY 1011 7 700 0
2 NIK LARPIH 22/07/2011 7 const of rcc footpath at Padubad 45717 819 0
3 NIK LARPIH 09/08/2011 7 const of rcc footpath at Padubad 44449 700 0
4 NIK LARPIH 03/10/2011 7 const of rcc footpath at Padubad 65644 700 0
Sub Total FY 1112 21 2219 0
5 NIK LARPIH 02/08/2012 4 const of rcc footpath at Padubad 86911 512 0
Sub Total FY 1213 4 512 0
6 NIK LARPIH 10/07/2013 14 2101006024/WC/39 109436 2030 0
Sub Total FY 1314 14 2030 0
7 SIANG POHSHNA 19/10/2015 14 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 2731 2282 0
8 SIANG POHSHNA 14/12/2015 13 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3030 2119 0
9 SIANG POHSHNA 06/01/2016 3 CONSTRUCTION OF SIDE DRAIN LENGTH=1440M PH- I AT PADUBAH VEC FY : 2015-16 3337 489 0
10 SIANG POHSHNA 24/02/2016 14 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 4669 2282 0
Sub Total FY 1516 44 7172 0
11 SIANG POHSHNA 28/04/2016 7 Construction of drainage at padubah Vec L= 1055 M PH-II FY 2015-16/124 47 1183 0
12 SIANG POHSHNA 11/08/2016 13 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1131 2197 0
13 SIANG POHSHNA 29/08/2016 14 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1632 2366 0
14 SIANG POHSHNA 14/09/2016 8 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 1664 1352 0
15 SIANG POHSHNA 30/09/2016 1 Const.internal road at Padubah VEC L= 690 m R/W= 450 m & Culvert 16 nos FY 2016-17/57 2497 169 0
16 SIANG POHSHNA 07/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3425 2366 0
17 SIANG POHSHNA 23/11/2016 14 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 3457 2366 0
18 SIANG POHSHNA 21/12/2016 10 Construction of Earthern Road (Internal) at Padu Bah Vec PH-II W/O 2016-17/13 4248 1690 0
19 SIANG POHSHNA 02/03/2017 14 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5503 2366 0
20 SIANG POHSHNA 18/03/2017 5 Const of Side Drain along with 10 Nos culvert at Padubah VEC L= 1299.70 m W/O 2016-17/174 5535 845 0
Sub Total FY 1617 100 16900 0
21 SIANG POHSHNA 21/06/2017 4 Roadside Tree Plantation at Padubah VEC L= 1.89 Km W/O 2017-18/DP 42 800 700 0
22 SIANG POHSHNA 29/06/2017 14 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1088 2450 0
23 SIANG POHSHNA 15/07/2017 6 Construction of Side Drain at PadubahVEC PH-II L=1858 m W/O 2017-18/FP-17 1117 1050 0
24 SIANG POHSHNA 09/10/2017 14 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4096 2450 0
25 SIANG POHSHNA 25/10/2017 7 Construction of 20 Individual Household Latrine at Padubah VEC W/O 2017-18/RS-34 4098 1225 0
26 SIANG POHSHNA 19/03/2018 11 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 6945 1925 0
Sub Total FY 1718 56 9800 0
27 SIANG POHSHNA 03/04/2018 14 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 46 2450 0
28 SIANG POHSHNA 19/04/2018 14 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 49 2450 0
29 SIANG POHSHNA 14/05/2018 3 Construction of Side Drain at padubah VEC Length 370m WO 2017-18/FP-104 516 525 0
30 SIANG POHSHNA 13/08/2018 14 Construction of Compound Fencing at Padubah VEC L=150m W/O 2018-19/FP-29 2206 2534 0
31 SIANG POHSHNA 29/08/2018 14 Construction of Compound Fencing at Padubah VEC L=150m W/O 2018-19/FP-29 2213 2534 0
32 SIANG POHSHNA 05/11/2018 8 Construction of Compound Fencing at Padubah VEC L=150m W/O 2018-19/FP-29 3404 1448 0
33 SIANG POHSHNA 28/01/2019 14 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60 5037 2534 0
34 SIANG POHSHNA 13/02/2019 14 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60 5044 2534 0
35 SIANG POHSHNA 11/03/2019 5 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60 6418 905 0
Sub Total FY 1819 100 17914 0
36 SIANG POHSHNA 29/04/2019 3 Construction of C C Motorable Road at Padubah VEC Wo 2018 19 RC 60 106 561 0
37 SIANG POHSHNA 22/08/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 971 2618 0
38 SIANG POHSHNA 07/09/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 982 2618 0
39 SIANG POHSHNA 14/10/2019 14 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2285 2618 0
40 SIANG POHSHNA 30/10/2019 8 Construction of Compound Fencing at Padubah VEC PH V L 290 m WO 2019 20 FP 6836 2296 1496 0
41 SIANG POHSHNA 13/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5016 2618 0
42 SIANG POHSHNA 29/01/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 5026 2618 0
43 SIANG POHSHNA 19/02/2020 14 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6885 2618 0
44 SIANG POHSHNA 06/03/2020 5 Construction of Compound Fencing L 430m at Padubah VEC WO 2019 20 FP 8565 6895 935 0
Sub Total FY 1920 100 18700 0