S.No Name of Applicant Age Bank/Postoffice
1 H.POHSHNA Male 23
2 ABEL POHSHNA Male 20 Meghalaya Co-operative Apex Bank
3 JARBI DKHAR Female 39 Meghalaya Co-operative Apex Bank


                  



S.No Name of Applicant
1 8485 H.POHSHNA 27/08/2009~~30/08/2009~~4 4
2 10693 01/09/2009~~14/09/2009~~14 14
3 16417 02/11/2009~~08/11/2009~~7 7
4 15429 ABEL POHSHNA 21/09/2010~~27/09/2010~~7 7
5 109523 21/09/2010~~27/09/2010~~7 7
6 9048 H.POHSHNA 13/05/2011~~20/05/2011~~8 7
7 18580 22/11/2011~~29/11/2011~~8 7
8 21014 01/12/2011~~08/12/2011~~8 7
9 28418 06/02/2012~~21/02/2012~~16 14
10 69418 ABEL POHSHNA 11/12/2015~~26/12/2015~~16 14
11 78858 14/01/2016~~29/01/2016~~16 14
12 86941 01/02/2016~~02/02/2016~~2 2
13 11433 14/07/2016~~14/08/2016~~32 28
14 33262 01/09/2016~~08/09/2016~~8 7
15 56474 28/09/2016~~28/09/2016~~1 1
16 101612 05/12/2016~~20/12/2016~~16 14
17 120876 16/01/2017~~12/02/2017~~28 24
18 165125 15/03/2017~~28/03/2017~~14 12
19 11486 23/05/2017~~07/06/2017~~16 14
20 21922 28/06/2017~~29/06/2017~~2 2
21 37206 08/08/2017~~25/08/2017~~18 16
22 66855 03/10/2017~~15/11/2017~~44 38
23 119483 25/01/2018~~25/02/2018~~32 28
24 152106 20/03/2018~~22/03/2018~~3 3
25 108136 30/10/2018~~20/11/2018~~22 19
26 108137 JARBI DKHAR 30/10/2018~~20/11/2018~~22 19
27 199701 ABEL POHSHNA 20/02/2019~~08/03/2019~~17 15
28 199702 JARBI DKHAR 20/02/2019~~08/03/2019~~17 15
29 51171 ABEL POHSHNA 10/07/2019~~18/07/2019~~9 8
30 108005 23/09/2019~~27/10/2019~~35 30
31 213092 22/01/2020~~05/02/2020~~15 13
32 228881 06/02/2020~~08/03/2020~~32 28
33 269404 16/03/2020~~30/03/2020~~15 13
34 165774 11/11/2020~~12/12/2020~~32 28
35 193327 15/12/2020~~15/01/2021~~32 28
36 218047 18/01/2021~~27/01/2021~~10 9
37 269838 01/03/2021~~16/03/2021~~16 14
38 104484 25/10/2021~~25/11/2021~~32 28
39 136597 29/11/2021~~08/12/2021~~10 9


S.No Name of Applicant Work Name
1 8485 H.POHSHNA 27/08/2009~~30/08/2009~~4 20 Const of C.C Footpath at Padumasku
2 10693 01/09/2009~~14/09/2009~~14 47 Const of C.C Footpath at Padumasku
3 16417 02/11/2009~~08/11/2009~~7 21 Const of C.C Footpath at Padumasku
4 109523 ABEL POHSHNA 21/09/2010~~27/09/2010~~7 7 Const of C.C Footpath at Padumasku
5 9048 H.POHSHNA 13/05/2011~~20/05/2011~~8 34 Const of C.C Footpath at Padumasku
6 18580 22/11/2011~~29/11/2011~~8 34 Const of C.C Footpath at Padumasku
7 21014 01/12/2011~~08/12/2011~~8 28 Const of C.C Footpath at Padumasku
8 28418 06/02/2012~~21/02/2012~~16 45 const of rcc footpath at Padubad
9 69418 ABEL POHSHNA 11/12/2015~~26/12/2015~~16 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
10 78858 14/01/2016~~29/01/2016~~16 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
11 86941 01/02/2016~~02/02/2016~~2 2 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
12 11433 14/07/2016~~14/08/2016~~32 28 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
13 33262 01/09/2016~~08/09/2016~~8 7 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
14 56474 28/09/2016~~28/09/2016~~1 1 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
15 101612 05/12/2016~~20/12/2016~~16 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143
16 120876 16/01/2017~~12/02/2017~~28 24 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143
17 165125 15/03/2017~~28/03/2017~~14 12 Constn of Internal road at Padu Mawsku VEC L=500m W/O 2016-17/189
18 11486 23/05/2017~~07/06/2017~~16 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16
19 21922 28/06/2017~~29/06/2017~~2 2 Roadside Plantation at Padu Mawsku VEC L= 369 m W/O 2017-18/DP-25
20 37206 08/08/2017~~25/08/2017~~18 16 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16
21 66855 03/10/2017~~15/11/2017~~44 38 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46
22 119483 25/01/2018~~25/02/2018~~32 28 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90
23 152106 20/03/2018~~22/03/2018~~3 3 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90
24 108136 30/10/2018~~20/11/2018~~22 19 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55
25 108137 JARBI DKHAR 30/10/2018~~20/11/2018~~22 19 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55
26 199701 ABEL POHSHNA 20/02/2019~~08/03/2019~~17 15 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121
27 199702 JARBI DKHAR 20/02/2019~~08/03/2019~~17 15 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121
28 51171 ABEL POHSHNA 10/07/2019~~18/07/2019~~9 8 Construction of C C Footpath L 305 m at Padu Mawsku VEC WO 2019 20 RC 3
29 108005 23/09/2019~~27/10/2019~~35 30 Construction of Retaining Wall at Padu Mawsku VEC L 30m WO 2019 20 FP 6
30 213092 22/01/2020~~05/02/2020~~15 13 Construction of Check Dam at Padu Mawsku VEC WO 2019 20 WC 16835
31 228881 06/02/2020~~08/03/2020~~32 28 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9096
32 269404 16/03/2020~~30/03/2020~~15 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9096
33 165774 11/11/2020~~12/12/2020~~32 28 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP
34 193327 15/12/2020~~15/01/2021~~32 28 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP
35 218047 18/01/2021~~27/01/2021~~10 9 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP
36 269838 01/03/2021~~16/03/2021~~16 14 Construction of Check Dam convergence with MBDA at Padu Mawsku VEC WO 2020 21
37 104484 25/10/2021~~25/11/2021~~32 28 Construction of C C Foothpath Ph I at Padu Mawsku VEC WO 2021 22
38 136597 29/11/2021~~08/12/2021~~10 9 Construction of C C Foothpath Ph I at Padu Mawsku VEC WO 2021 22


S.No Name of Applicant Work Name Total Amount of Work Done Payment Due
1 H.POHSHNA 27/08/2009 4 Const of C.C Footpath at Padumasku 12613 280 0
2 H.POHSHNA 01/09/2009 10 Const of C.C Footpath at Padumasku 12618 1000 0
3 H.POHSHNA 02/11/2009 6 Const of C.C Footpath at Padumasku 13067 600 0
Sub Total FY 0910 20 1880 0
4 ABEL POHSHNA 21/09/2010 7 Const of C.C Footpath at Padumasku 38361 700 0
Sub Total FY 1011 7 700 0
5 H.POHSHNA 13/05/2011 7 Const of C.C Footpath at Padumasku 45733 819 0
6 H.POHSHNA 22/11/2011 7 Const of C.C Footpath at Padumasku 64039 819 0
7 H.POHSHNA 01/12/2011 7 Const of C.C Footpath at Padumasku 65891 819 0
8 H.POHSHNA 06/02/2012 14 const of rcc footpath at Padubad 70675 1638 0
Sub Total FY 1112 35 4095 0
9 ABEL POHSHNA 11/12/2015 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 2960 2282 0
10 ABEL POHSHNA 14/01/2016 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 3456 2282 0
11 ABEL POHSHNA 01/02/2016 2 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 3985 326 0
Sub Total FY 1516 30 4890 0
12 ABEL POHSHNA 14/07/2016 14 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 691 2366 0
13 ABEL POHSHNA 30/07/2016 8 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 703 1352 0
14 ABEL POHSHNA 09/08/2016 5 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 715 845 0
15 ABEL POHSHNA 01/09/2016 7 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 1796 1183 0
16 ABEL POHSHNA 28/09/2016 1 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 2486 169 0
17 ABEL POHSHNA 05/12/2016 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 3948 2366 0
18 ABEL POHSHNA 16/01/2017 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 4442 2366 0
19 ABEL POHSHNA 01/02/2017 10 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 4455 1690 0
20 ABEL POHSHNA 15/03/2017 12 Constn of Internal road at Padu Mawsku VEC L=500m W/O 2016-17/189 5922 2028 0
Sub Total FY 1617 85 14365 0
21 ABEL POHSHNA 23/05/2017 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 312 2450 0
22 ABEL POHSHNA 28/06/2017 2 Roadside Plantation at Padu Mawsku VEC L= 369 m W/O 2017-18/DP-25 1068 350 0
23 ABEL POHSHNA 08/08/2017 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 2091 2450 0
24 ABEL POHSHNA 24/08/2017 2 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 2104 350 0
25 ABEL POHSHNA 03/10/2017 14 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4009 2450 0
26 ABEL POHSHNA 19/10/2017 14 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4024 2450 0
27 ABEL POHSHNA 04/11/2017 10 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4383 1750 0
28 ABEL POHSHNA 25/01/2018 14 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 5963 2450 0
29 ABEL POHSHNA 10/02/2018 13 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 5976 2275 0
30 ABEL POHSHNA 20/03/2018 3 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 6971 525 0
Sub Total FY 1718 100 17500 0
31 ABEL POHSHNA 30/10/2018 14 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3285 2534 0
32 JARBI DKHAR 30/10/2018 14 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3285 2534 0
33 ABEL POHSHNA 30/10/2018 5 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3302 905 0
34 JARBI DKHAR 30/10/2018 5 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3302 905 0
35 ABEL POHSHNA 20/02/2019 14 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121 5930 2534 0
36 JARBI DKHAR 20/02/2019 14 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121 5930 2534 0
37 ABEL POHSHNA 20/02/2019 1 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121 5938 181 0
38 JARBI DKHAR 20/02/2019 1 Construction of R Wall L 46m at Padu Mawsku VEC WO 2018 19 FP 121 5938 181 0
Sub Total FY 1819 68 12308 0
39 ABEL POHSHNA 10/07/2019 8 Construction of C C Footpath L 305 m at Padu Mawsku VEC WO 2019 20 RC 3 403 1496 0
40 ABEL POHSHNA 23/09/2019 14 Construction of Retaining Wall at Padu Mawsku VEC L 30m WO 2019 20 FP 6 1842 2618 0
41 ABEL POHSHNA 09/10/2019 14 Construction of Retaining Wall at Padu Mawsku VEC L 30m WO 2019 20 FP 6 1845 2618 0
42 ABEL POHSHNA 25/10/2019 2 Construction of Retaining Wall at Padu Mawsku VEC L 30m WO 2019 20 FP 6 2275 374 0
43 ABEL POHSHNA 22/01/2020 13 Construction of Check Dam at Padu Mawsku VEC WO 2019 20 WC 16835 5694 2431 0
44 ABEL POHSHNA 06/02/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9096 6148 2618 0
45 ABEL POHSHNA 22/02/2020 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9096 6152 2431 0
46 ABEL POHSHNA 16/03/2020 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9096 7420 2431 0
Sub Total FY 1920 91 17017 0
47 ABEL POHSHNA 11/11/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP 4459 2842 0
48 ABEL POHSHNA 27/11/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP 4463 2842 0
49 ABEL POHSHNA 15/12/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP 5178 2842 0
50 ABEL POHSHNA 31/12/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP 5181 2842 0
51 ABEL POHSHNA 18/01/2021 9 Construction of Retaining Wall at Padu Mawsku VEC WO 2020 21 FP 6069 1827 0
52 ABEL POHSHNA 01/03/2021 14 Construction of Check Dam convergence with MBDA at Padu Mawsku VEC WO 2020 21 7417 2842 0
Sub Total FY 2021 79 16037 0
53 ABEL POHSHNA 25/10/2021 14 Construction of C C Foothpath Ph I at Padu Mawsku VEC WO 2021 22 1305 3164 0
54 ABEL POHSHNA 10/11/2021 14 Construction of C C Foothpath Ph I at Padu Mawsku VEC WO 2021 22 1318 3164 0
55 ABEL POHSHNA 29/11/2021 9 Construction of C C Foothpath Ph I at Padu Mawsku VEC WO 2021 22 2295 2034 0
Sub Total FY 2122 37 8362 0