S.No Name of Applicant Gender Age Bank/Postoffice
1 DIMAIN POHTHMI Male 24 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 69555 DIMAIN POHTHMI 11/12/2015~~26/12/2015~~16 14
2 78986 14/01/2016~~29/01/2016~~16 14
3 87035 01/02/2016~~02/02/2016~~2 2
4 11524 14/07/2016~~14/08/2016~~32 28
5 33359 01/09/2016~~08/09/2016~~8 7
6 56565 28/09/2016~~28/09/2016~~1 1
7 101891 05/12/2016~~20/12/2016~~16 14
8 120979 16/01/2017~~12/02/2017~~28 24
9 165225 15/03/2017~~28/03/2017~~14 12
10 11581 23/05/2017~~07/06/2017~~16 14
11 22014 28/06/2017~~29/06/2017~~2 2
12 37362 08/08/2017~~25/08/2017~~18 16
13 67082 03/10/2017~~15/11/2017~~44 38
14 119597 25/01/2018~~25/02/2018~~32 28
15 152228 20/03/2018~~22/03/2018~~3 3
16 108285 30/10/2018~~12/12/2018~~44 38
17 195874 15/02/2019~~21/03/2019~~35 30
18 51330 10/07/2019~~18/07/2019~~9 8
19 108098 23/09/2019~~27/10/2019~~35 30
20 213300 22/01/2020~~05/02/2020~~15 13
21 229212 06/02/2020~~08/03/2020~~32 28
22 269628 16/03/2020~~30/03/2020~~15 13
23 165631 11/11/2020~~12/12/2020~~32 28
24 193467 15/12/2020~~01/01/2021~~18 16
25 270192 01/03/2021~~16/03/2021~~16 14
26 103681 25/10/2021~~25/11/2021~~32 28
27 137297 26/11/2021~~11/12/2021~~16 14

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 69555 DIMAIN POHTHMI 11/12/2015~~26/12/2015~~16 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
2 78986 14/01/2016~~29/01/2016~~16 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
3 87035 01/02/2016~~02/02/2016~~2 2 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73
4 11524 14/07/2016~~14/08/2016~~32 28 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
5 33359 01/09/2016~~08/09/2016~~8 7 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
6 56565 28/09/2016~~28/09/2016~~1 1 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13
7 101891 05/12/2016~~20/12/2016~~16 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143
8 120979 16/01/2017~~12/02/2017~~28 24 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143
9 165225 15/03/2017~~28/03/2017~~14 12 Constn of Internal road at Padu Mawsku VEC L=500m W/O 2016-17/189
10 11581 23/05/2017~~07/06/2017~~16 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16
11 22014 28/06/2017~~29/06/2017~~2 2 Roadside Plantation at Padu Mawsku VEC L= 369 m W/O 2017-18/DP-25
12 37362 08/08/2017~~25/08/2017~~18 16 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16
13 67082 03/10/2017~~15/11/2017~~44 38 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46
14 119597 25/01/2018~~25/02/2018~~32 28 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90
15 152228 20/03/2018~~22/03/2018~~3 3 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90
16 108285 30/10/2018~~12/12/2018~~44 38 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55
17 195874 15/02/2019~~21/03/2019~~35 30 Construction of side drain at Padu Mawsku VEC L 160m WO 2018 19 FP 117
18 51330 10/07/2019~~18/07/2019~~9 8 Construction of C C Footpath L 305 m at Padu Mawsku VEC WO 2019 20 RC 3
19 108098 23/09/2019~~27/10/2019~~35 30 Construction of SideDrain L 240 m at Padu Mawsku VEC WO 2019 20 FP 5
20 213300 22/01/2020~~05/02/2020~~15 13 Construction of Check Dam at Padu Mawsku VEC WO 2019 20 WC 16835
21 229212 06/02/2020~~08/03/2020~~32 28 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9097
22 269628 16/03/2020~~30/03/2020~~15 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9097
23 165631 11/11/2020~~12/12/2020~~32 28 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21
24 193467 15/12/2020~~01/01/2021~~18 16 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21
25 270192 01/03/2021~~16/03/2021~~16 14 Construction of Check Dam convergence with MBDA at Padu Mawsku VEC WO 2020 21
26 103681 25/10/2021~~25/11/2021~~32 28 Construction of C C Foothpath Ph III at Padu Mawsku VEC WO 2021 22
27 137297 26/11/2021~~11/12/2021~~16 14 Construction of C C Foothpath Ph III at Padu Mawsku VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 DIMAIN POHTHMI 11/12/2015 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 2958 2282 0
2 DIMAIN POHTHMI 14/01/2016 14 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 3454 2282 0
3 DIMAIN POHTHMI 01/02/2016 2 Construction of Road at Padu Masku Vec Lenth :600 M PH= II FY:2015-16/73 3983 326 0
Sub Total FY 1516 30 4890 0
4 DIMAIN POHTHMI 14/07/2016 14 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 689 2366 0
5 DIMAIN POHTHMI 30/07/2016 8 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 701 1352 0
6 DIMAIN POHTHMI 09/08/2016 5 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 713 845 0
7 DIMAIN POHTHMI 01/09/2016 7 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 1794 1183 0
8 DIMAIN POHTHMI 28/09/2016 1 Consdt. of Internal Road at Padu Mawsku VEC PH-III L=600 m FY=2016-2017/13 2484 169 0
9 DIMAIN POHTHMI 05/12/2016 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 3946 2366 0
10 DIMAIN POHTHMI 16/01/2017 14 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 4440 2366 0
11 DIMAIN POHTHMI 01/02/2017 10 Const of Earther Road (internal ) at Padu Masku PH- IV W.O 2016-17/143 4453 1690 0
12 DIMAIN POHTHMI 15/03/2017 12 Constn of Internal road at Padu Mawsku VEC L=500m W/O 2016-17/189 5920 2028 0
Sub Total FY 1617 85 14365 0
13 DIMAIN POHTHMI 23/05/2017 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 310 2450 0
14 DIMAIN POHTHMI 28/06/2017 2 Roadside Plantation at Padu Mawsku VEC L= 369 m W/O 2017-18/DP-25 1066 350 0
15 DIMAIN POHTHMI 08/08/2017 14 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 2089 2450 0
16 DIMAIN POHTHMI 24/08/2017 2 Construction of drainage PH-I L = 400 m at Padu Mawsku VEC W/O 2017-18/16 2102 350 0
17 DIMAIN POHTHMI 03/10/2017 14 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4007 2450 0
18 DIMAIN POHTHMI 19/10/2017 14 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4022 2450 0
19 DIMAIN POHTHMI 04/11/2017 10 Construction of Drainage at Padu Mawsku VEC L:560M 2017-18 /FP-46 4381 1750 0
20 DIMAIN POHTHMI 25/01/2018 14 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 5961 2450 0
21 DIMAIN POHTHMI 10/02/2018 13 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 5974 2275 0
22 DIMAIN POHTHMI 20/03/2018 3 Construction of Drainage at Padu mawsku VEC Length 420 m WO:2017-18/FP-90 6969 525 0
Sub Total FY 1718 100 17500 0
23 DIMAIN POHTHMI 30/10/2018 14 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3283 2534 0
24 DIMAIN POHTHMI 15/11/2018 14 Construction of Drainage at Padu Mawsku VEC WO 2018 19 FP 55 3300 2534 0
25 DIMAIN POHTHMI 15/02/2019 14 Construction of side drain at Padu Mawsku VEC L 160m WO 2018 19 FP 117 5764 2534 0
26 DIMAIN POHTHMI 03/03/2019 13 Construction of side drain at Padu Mawsku VEC L 160m WO 2018 19 FP 117 5768 2353 0
27 DIMAIN POHTHMI 19/03/2019 3 Construction of side drain at Padu Mawsku VEC L 160m WO 2018 19 FP 117 6409 543 0
Sub Total FY 1819 58 10498 0
28 DIMAIN POHTHMI 10/07/2019 8 Construction of C C Footpath L 305 m at Padu Mawsku VEC WO 2019 20 RC 3 401 1496 0
29 DIMAIN POHTHMI 23/09/2019 14 Construction of SideDrain L 240 m at Padu Mawsku VEC WO 2019 20 FP 5 1849 2618 0
30 DIMAIN POHTHMI 09/10/2019 14 Construction of SideDrain L 240 m at Padu Mawsku VEC WO 2019 20 FP 5 1855 2618 0
31 DIMAIN POHTHMI 25/10/2019 2 Construction of SideDrain L 240 m at Padu Mawsku VEC WO 2019 20 FP 5 2270 374 0
32 DIMAIN POHTHMI 22/01/2020 13 Construction of Check Dam at Padu Mawsku VEC WO 2019 20 WC 16835 5692 2431 0
33 DIMAIN POHTHMI 06/02/2020 14 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9097 6157 2618 0
34 DIMAIN POHTHMI 22/02/2020 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9097 6164 2431 0
35 DIMAIN POHTHMI 16/03/2020 13 Construction of Retaining Wall at Padu Mawsku VEC WO 2019 20 FP 9097 7425 2431 0
Sub Total FY 1920 91 17017 0
36 DIMAIN POHTHMI 11/11/2020 14 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21 4436 2842 0
37 DIMAIN POHTHMI 27/11/2020 14 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21 4443 2842 0
38 DIMAIN POHTHMI 15/12/2020 14 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21 5185 2842 0
39 DIMAIN POHTHMI 31/12/2020 2 Construction of C C Footpath at Padu Mawsku VEC WO 2020 21 5192 406 0
40 DIMAIN POHTHMI 01/03/2021 14 Construction of Check Dam convergence with MBDA at Padu Mawsku VEC WO 2020 21 7415 2842 0
Sub Total FY 2021 58 11774 0
41 DIMAIN POHTHMI 25/10/2021 14 Construction of C C Foothpath Ph III at Padu Mawsku VEC WO 2021 22 1250 3164 0
42 DIMAIN POHTHMI 10/11/2021 14 Construction of C C Foothpath Ph III at Padu Mawsku VEC WO 2021 22 1327 3164 0
43 DIMAIN POHTHMI 26/11/2021 14 Construction of C C Foothpath Ph III at Padu Mawsku VEC WO 2021 22 2304 3164 0
Sub Total FY 2122 42 9492 0