S.No Name of Applicant Gender Age Bank/Postoffice
1 Wansuk Pohlong Male 18 NONGBAREH
2 WELLY POHLONG Male 25 Meghalaya Co-operative Apex Bank
3 FARIDA POHLONG Female 23 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 13019 Wansuk Pohlong 01/06/2009~~14/06/2009~~14 14
2 17250 17/09/2009~~23/09/2009~~7 7
3 18028 05/10/2009~~11/10/2009~~7 7
4 18103 17/10/2009~~23/10/2009~~7 7
5 903 22/05/2010~~04/06/2010~~14 14
6 100085 22/05/2010~~04/06/2010~~14 14
7 2084 08/06/2010~~21/06/2010~~14 14
8 101243 08/06/2010~~21/06/2010~~14 14
9 2643 24/06/2010~~30/06/2010~~7 7
10 103028 24/06/2010~~30/06/2010~~7 7
11 8029 20/07/2010~~02/08/2010~~14 14
12 104475 20/07/2010~~02/08/2010~~14 14
13 14062 21/08/2010~~03/09/2010~~14 14
14 109238 21/08/2010~~03/09/2010~~14 14
15 14237 07/09/2010~~12/09/2010~~6 6
16 109373 07/09/2010~~12/09/2010~~6 6
17 25424 22/11/2010~~23/11/2010~~2 2
18 2449 16/05/2011~~31/05/2011~~16 14
19 7571 01/06/2011~~08/06/2011~~8 7
20 11984 17/06/2011~~24/06/2011~~8 7
21 13226 25/06/2011~~10/07/2011~~16 14
22 9437 15/07/2011~~22/07/2011~~8 7
23 10093 23/07/2011~~30/07/2011~~8 7
24 14631 01/08/2011~~08/08/2011~~8 7
25 17372 09/08/2011~~24/08/2011~~16 14
26 27110 06/02/2012~~21/02/2012~~16 14
27 27269 22/02/2012~~26/02/2012~~5 5
28 3068 02/04/2013~~09/04/2013~~8 7
29 3872 10/04/2013~~25/04/2013~~16 14
30 49537 24/06/2014~~01/07/2014~~8 7
31 52135 02/07/2014~~09/07/2014~~8 7
32 124163 16/10/2014~~18/10/2014~~3 3
33 122454 20/01/2015~~11/02/2015~~23 20
34 94142 FARIDA POHLONG 28/11/2016~~13/12/2016~~16 14
35 120036 12/01/2017~~27/01/2017~~16 14
36 150148 23/02/2017~~11/03/2017~~17 15
37 20689 22/06/2017~~22/06/2017~~1 1
38 35346 07/08/2017~~21/09/2017~~46 40
39 95765 11/12/2017~~25/01/2018~~46 40
40 121137 29/01/2018~~29/01/2018~~1 1
41 150527 16/03/2018~~31/03/2018~~16 14
42 3371 04/04/2018~~08/04/2018~~5 5
43 3673 09/04/2018~~09/04/2018~~1 1
44 41493 09/07/2018~~09/08/2018~~32 28
45 88998 01/10/2018~~11/10/2018~~11 10
46 143678 19/12/2018~~19/01/2019~~32 28
47 170390 24/01/2019~~21/02/2019~~29 25
48 61511 29/07/2019~~13/08/2019~~16 14
49 85540 28/08/2019~~28/09/2019~~32 28
50 117200 03/10/2019~~11/10/2019~~9 8
51 142235 29/10/2019~~02/11/2019~~5 5
52 168918 29/11/2019~~30/12/2019~~32 28
53 202512 15/01/2020~~05/02/2020~~22 19
54 19750 19/05/2020~~19/06/2020~~32 28
55 39716 22/06/2020~~16/07/2020~~25 22
56 161688 Wansuk Pohlong 06/11/2020~~07/12/2020~~32 28
57 200114 04/01/2021~~28/01/2021~~25 22
58 13133 13/05/2021~~26/05/2021~~14 12
59 99523 12/10/2021~~12/11/2021~~32 28
60 124991 15/11/2021~~01/12/2021~~17 15
61 155976 16/12/2021~~16/01/2022~~32 28
62 184024 18/01/2022~~31/01/2022~~14 12
63 201272 03/02/2022~~10/02/2022~~8 7

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 13019 Wansuk Pohlong 01/06/2009~~14/06/2009~~14 44 Const of Road at Nongbarehrim
2 17250 17/09/2009~~23/09/2009~~7 17 Const of Road at Nongbarehrim
3 18028 05/10/2009~~11/10/2009~~7 20 Const of Road at Nongbarehrim
4 18103 17/10/2009~~23/10/2009~~7 20 Const of Road at Nongbarehrim
5 100085 22/05/2010~~04/06/2010~~14 14 Construction of Drainage at Nongbarehrim
6 101243 08/06/2010~~21/06/2010~~14 14 Construction of Drainage at Nongbarehrim
7 103028 24/06/2010~~30/06/2010~~7 7 Construction of Drainage at Nongbarehrim
8 104475 20/07/2010~~02/08/2010~~14 14 Construction of Drainage at Nongbarehrim
9 109238 21/08/2010~~03/09/2010~~14 14 Construction of Drainage at Nongbarehrim
10 109373 07/09/2010~~12/09/2010~~6 6 Construction of Drainage at Nongbarehrim
11 25424 22/11/2010~~23/11/2010~~2 14 Construction of Drainage at Nongbarehrim
12 2449 16/05/2011~~31/05/2011~~16 37 Const of Road at Nongbarehrim
13 7571 01/06/2011~~08/06/2011~~8 34 Const of Road at Nongbarehrim
14 11984 17/06/2011~~24/06/2011~~8 30 Const of Road at Nongbarehrim
15 13226 25/06/2011~~10/07/2011~~16 41 Const of Road at Nongbarehrim
16 9437 15/07/2011~~22/07/2011~~8 27 Const of Road at Nongbarehrim
17 10093 23/07/2011~~30/07/2011~~8 34 Const of Road at Nongbarehrim
18 14631 01/08/2011~~08/08/2011~~8 33 Const of Road at Nongbarehrim
19 17372 09/08/2011~~24/08/2011~~16 39 Const of Road at Nongbarehrim
20 27110 06/02/2012~~21/02/2012~~16 51 Const of Road at Nongbarehrim
21 27269 22/02/2012~~26/02/2012~~5 20 Const of Road at Nongbarehrim
22 3068 02/04/2013~~09/04/2013~~8 35 Const of R/Wall at Nongbarehrim
23 3872 10/04/2013~~25/04/2013~~16 54 Const of R/Wall at Nongbarehrim
24 49537 24/06/2014~~01/07/2014~~8 7 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec
25 52135 02/07/2014~~09/07/2014~~8 7 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec
26 124163 16/10/2014~~18/10/2014~~3 3 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec
27 122454 20/01/2015~~11/02/2015~~23 20 Construction of RetainingWall (ECW) at Nongbareh Rim Vec
28 94142 FARIDA POHLONG 28/11/2016~~13/12/2016~~16 14 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104
29 120036 12/01/2017~~27/01/2017~~16 14 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104
30 150148 23/02/2017~~11/03/2017~~17 15 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104
31 20689 22/06/2017~~22/06/2017~~1 1 Block Tree Plantation at Nongbarehrim VEC W/O 2017-18/DP -27
32 35346 07/08/2017~~21/09/2017~~46 40 Construction of R/Wall at Nongbareh Rim VEC Ph-IV L= 280 m W/O 2017-18/FP-20
33 95765 11/12/2017~~25/01/2018~~46 40 Construction of R Wall Ph VI at Nongbareh rim 2017-18
34 121137 29/01/2018~~29/01/2018~~1 1 Construction of R Wall Ph VI at Nongbareh rim 2017-18
35 150527 16/03/2018~~31/03/2018~~16 14 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116
36 3371 04/04/2018~~08/04/2018~~5 5 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116
37 3673 09/04/2018~~09/04/2018~~1 1 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116
38 41493 09/07/2018~~09/08/2018~~32 28 Construction of R Wall Ph X at Nongbareh Rim VEC Length 150 m WO 2018-19/FP-21
39 88998 01/10/2018~~11/10/2018~~11 10 Construction of R Wall Ph X at Nongbareh Rim VEC Length 150 m WO 2018-19/FP-21
40 143678 19/12/2018~~19/01/2019~~32 28 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91
41 170390 24/01/2019~~21/02/2019~~29 25 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91
42 61511 29/07/2019~~13/08/2019~~16 14 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031
43 85540 28/08/2019~~28/09/2019~~32 28 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031
44 117200 03/10/2019~~11/10/2019~~9 8 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031
45 142235 29/10/2019~~02/11/2019~~5 5 Construction of Check Dam at Nongbarehrim VEC Length 17.5m2 WO 2019 20 WC 9646
46 168918 29/11/2019~~30/12/2019~~32 28 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493
47 202512 15/01/2020~~05/02/2020~~22 19 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493
48 19750 19/05/2020~~19/06/2020~~32 28 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008
49 39716 22/06/2020~~16/07/2020~~25 22 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008
50 161688 Wansuk Pohlong 06/11/2020~~07/12/2020~~32 28 Construction of R Wall at NongbarehRim VEC WO 2020 21
51 200114 04/01/2021~~28/01/2021~~25 22 Construction of R Wall at NongbarehRim VEC WO 2020 21
52 13133 13/05/2021~~26/05/2021~~14 12 Construction of Check Dam in convergence with MBDA at Nongbareh Rim VEC WO 2021 22
53 99523 12/10/2021~~12/11/2021~~32 28 Construction of side drain at Nongbareh Rim VEC WO 2021 22
54 124991 15/11/2021~~01/12/2021~~17 15 Construction of side drain at Nongbareh Rim VEC WO 2021 22
55 155976 16/12/2021~~16/01/2022~~32 28 Construction of Internal road at Nongbareh Rim VEC WO 2021 22 RC 64705
56 184024 18/01/2022~~31/01/2022~~14 12 Construction of Internal road at Nongbareh Rim VEC WO 2021 22 RC 64705
57 201272 03/02/2022~~10/02/2022~~8 7 Construction of Drainage at Nongbareh Rim VEC WO 2021 22 FP 13671

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 Wansuk Pohlong 01/06/2009 14 Const of Road at Nongbarehrim 8101 980 0
2 Wansuk Pohlong 17/09/2009 7 Const of Road at Nongbarehrim 8649 700 0
3 Wansuk Pohlong 05/10/2009 7 Const of Road at Nongbarehrim 13164 700 0
Sub Total FY 0910 28 2380 0
4 Wansuk Pohlong 22/05/2010 14 Construction of Drainage at Nongbarehrim 22047 1400 0
5 Wansuk Pohlong 08/06/2010 14 Construction of Drainage at Nongbarehrim 22298 1400 0
6 Wansuk Pohlong 24/06/2010 7 Construction of Drainage at Nongbarehrim 28529 700 0
7 Wansuk Pohlong 20/07/2010 14 Construction of Drainage at Nongbarehrim 30320 1400 0
8 Wansuk Pohlong 21/08/2010 14 Construction of Drainage at Nongbarehrim 38320 1400 0
9 Wansuk Pohlong 07/09/2010 6 Construction of Drainage at Nongbarehrim 38348 600 0
10 Wansuk Pohlong 22/11/2010 1 Construction of Drainage at Nongbarehrim 39086 100 0
Sub Total FY 1011 70 7000 0
11 Wansuk Pohlong 16/05/2011 14 Const of Road at Nongbarehrim 45351 1638 0
12 Wansuk Pohlong 01/06/2011 7 Const of Road at Nongbarehrim 453653 819 0
13 Wansuk Pohlong 17/06/2011 7 Const of Road at Nongbarehrim 62367 819 0
14 Wansuk Pohlong 25/06/2011 14 Const of Road at Nongbarehrim 65103 1638 0
15 Wansuk Pohlong 15/07/2011 7 Const of Road at Nongbarehrim 457453 819 0
16 Wansuk Pohlong 23/07/2011 7 Const of Road at Nongbarehrim 61797 819 0
17 Wansuk Pohlong 01/08/2011 7 Const of Road at Nongbarehrim 65365 819 0
18 Wansuk Pohlong 09/08/2011 14 Const of Road at Nongbarehrim 65512 1638 0
19 Wansuk Pohlong 06/02/2012 14 Const of Road at Nongbarehrim 71192 1638 0
20 Wansuk Pohlong 22/02/2012 5 Const of Road at Nongbarehrim 71208 585 0
Sub Total FY 1112 96 11232 0
21 Wansuk Pohlong 02/04/2013 7 Const of R/Wall at Nongbarehrim 109004 1015 0
22 Wansuk Pohlong 10/04/2013 14 Const of R/Wall at Nongbarehrim 114167 2030 0
Sub Total FY 1314 21 3045 0
23 Wansuk Pohlong 24/06/2014 7 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec 142449 1071 0
24 Wansuk Pohlong 02/07/2014 7 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec 142468 1071 0
25 Wansuk Pohlong 16/10/2014 3 Construction of Retaining Wall (Erosion Control Work at Nongbarehrim Vec 145937 459 0
26 Wansuk Pohlong 20/01/2015 7 Construction of RetainingWall (ECW) at Nongbareh Rim Vec 147777 1071 0
27 Wansuk Pohlong 28/01/2015 7 Construction of RetainingWall (ECW) at Nongbareh Rim Vec 147792 1071 0
28 Wansuk Pohlong 05/02/2015 6 Construction of RetainingWall (ECW) at Nongbareh Rim Vec 147807 918 0
Sub Total FY 1415 37 5661 0
29 FARIDA POHLONG 28/11/2016 14 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104 3784 2366 0
30 FARIDA POHLONG 12/01/2017 14 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104 4417 2366 0
31 FARIDA POHLONG 23/02/2017 14 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104 5366 2366 0
32 FARIDA POHLONG 11/03/2017 1 Const of R/Wall at Nongbareh Rim VEC Phase - III L=500 m W/O 2016-17/104 5378 169 0
Sub Total FY 1617 43 7267 0
33 FARIDA POHLONG 22/06/2017 1 Block Tree Plantation at Nongbarehrim VEC W/O 2017-18/DP -27 892 175 0
34 FARIDA POHLONG 07/08/2017 14 Construction of R/Wall at Nongbareh Rim VEC Ph-IV L= 280 m W/O 2017-18/FP-20 1879 2450 0
35 FARIDA POHLONG 23/08/2017 14 Construction of R/Wall at Nongbareh Rim VEC Ph-IV L= 280 m W/O 2017-18/FP-20 1977 2450 0
36 FARIDA POHLONG 08/09/2017 12 Construction of R/Wall at Nongbareh Rim VEC Ph-IV L= 280 m W/O 2017-18/FP-20 2822 2100 0
37 FARIDA POHLONG 11/12/2017 13 Construction of R Wall Ph VI at Nongbareh rim 2017-18 5168 2275 0
38 FARIDA POHLONG 27/12/2017 14 Construction of R Wall Ph VI at Nongbareh rim 2017-18 5180 2450 0
39 FARIDA POHLONG 12/01/2018 12 Construction of R Wall Ph VI at Nongbareh rim 2017-18 5534 2100 0
40 FARIDA POHLONG 29/01/2018 1 Construction of R Wall Ph VI at Nongbareh rim 2017-18 5998 175 0
41 FARIDA POHLONG 16/03/2018 14 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116 6923 2450 0
Sub Total FY 1718 95 16625 0
42 FARIDA POHLONG 04/04/2018 4 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116 115 700 0
43 FARIDA POHLONG 09/04/2018 1 Construction of R Wall Ph VIII at Nongbareh Rim VEC Length 136 m WO:2017-18/FP-116 125 175 0
44 FARIDA POHLONG 09/07/2018 14 Construction of R Wall Ph X at Nongbareh Rim VEC Length 150 m WO 2018-19/FP-21 1521 2534 0
45 FARIDA POHLONG 25/07/2018 14 Construction of R Wall Ph X at Nongbareh Rim VEC Length 150 m WO 2018-19/FP-21 1527 2534 0
46 FARIDA POHLONG 01/10/2018 10 Construction of R Wall Ph X at Nongbareh Rim VEC Length 150 m WO 2018-19/FP-21 2811 1810 0
47 FARIDA POHLONG 19/12/2018 13 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91 4013 2353 0
48 FARIDA POHLONG 04/01/2019 14 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91 4024 2534 0
49 FARIDA POHLONG 24/01/2019 14 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91 4973 2534 0
50 FARIDA POHLONG 09/02/2019 11 Construction of R Wall Ph XII at Nongbarehrim VEC Length 125 m WO 2018 19 FP 91 4984 1991 0
Sub Total FY 1819 95 17165 0
51 FARIDA POHLONG 29/07/2019 14 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031 592 2618 0
52 FARIDA POHLONG 28/08/2019 14 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031 1021 2618 0
53 FARIDA POHLONG 13/09/2019 14 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031 1033 2618 0
54 FARIDA POHLONG 03/10/2019 8 Construction of Retaining Wall Ph XIV at Nongbarehrim VEC Length 166 m WO 2019 20 FP 8031 2051 1496 0
55 FARIDA POHLONG 29/10/2019 5 Construction of Check Dam at Nongbarehrim VEC Length 17.5m2 WO 2019 20 WC 9646 2958 935 0
56 FARIDA POHLONG 29/11/2019 1 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493 3761 187 0
57 FARIDA POHLONG 30/11/2019 13 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493 3773 2431 0
58 FARIDA POHLONG 15/12/2019 12 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493 3785 2244 0
59 FARIDA POHLONG 15/01/2020 14 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493 5301 2618 0
60 FARIDA POHLONG 31/01/2020 5 Construction of R Wall cum Fencing at Nongbarehrim VEC WO 2019 20 FP 8493 5313 935 0
Sub Total FY 1920 100 18700 0
61 FARIDA POHLONG 19/05/2020 14 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008 550 2842 0
62 FARIDA POHLONG 04/06/2020 14 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008 558 2842 0
63 FARIDA POHLONG 22/06/2020 14 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008 915 2842 0
64 FARIDA POHLONG 08/07/2020 8 Construction of R Wall at Nongbareh Rim VEC WO 2020 21 FP 9008 922 1624 0
65 Wansuk Pohlong 06/11/2020 14 Construction of R Wall at NongbarehRim VEC WO 2020 21 4207 2842 0
66 Wansuk Pohlong 22/11/2020 13 Construction of R Wall at NongbarehRim VEC WO 2020 21 4219 2639 0
67 Wansuk Pohlong 04/01/2021 14 Construction of R Wall at NongbarehRim VEC WO 2020 21 5417 2842 0
68 Wansuk Pohlong 20/01/2021 8 Construction of R Wall at NongbarehRim VEC WO 2020 21 5433 1624 0
Sub Total FY 2021 99 20097 0
69 Wansuk Pohlong 13/05/2021 12 Construction of Check Dam in convergence with MBDA at Nongbareh Rim VEC WO 2021 22 130 2712 0
70 Wansuk Pohlong 12/10/2021 14 Construction of side drain at Nongbareh Rim VEC WO 2021 22 1180 3164 0
71 Wansuk Pohlong 28/10/2021 14 Construction of side drain at Nongbareh Rim VEC WO 2021 22 1184 3164 0
72 Wansuk Pohlong 15/11/2021 10 Construction of side drain at Nongbareh Rim VEC WO 2021 22 2070 2260 0
73 Wansuk Pohlong 26/11/2021 5 Construction of side drain at Nongbareh Rim VEC WO 2021 22 2074 1130 0
74 Wansuk Pohlong 16/12/2021 13 Construction of Internal road at Nongbareh Rim VEC WO 2021 22 RC 64705 2720 2938 0
75 Wansuk Pohlong 01/01/2022 13 Construction of Internal road at Nongbareh Rim VEC WO 2021 22 RC 64705 2730 2938 0
76 Wansuk Pohlong 18/01/2022 12 Construction of Internal road at Nongbareh Rim VEC WO 2021 22 RC 64705 3800 2712 0
77 Wansuk Pohlong 03/02/2022 7 Construction of Drainage at Nongbareh Rim VEC WO 2021 22 FP 13671 4384 1582 0
Sub Total FY 2122 100 22600 0