Back

Job card
MAHATMA GANDHI NATIONAL RURAL EMPLOYMENT GUARANTEE ACT
Job card No.: MG-01-006-013-001/64 Family Id: 64
Name of Head of Household: SMT AGNES PALA
Name of Father/Husband: K MUKHIM
Category: ST
Date of Registration: 8/18/2007
Address: 64
Villages:
Panchayat: Khonglah
Block: AMLAREM
District: WEST JAINTIA HILLS(MEGHALAYA)
Whether BPL Family: NO Family Id: 64
Epic No.:
Details of the Applicants of the household willing to work
S.No Name of Applicant Gender Age Bank/Postoffice
1 A.PALA Male 51
2 K.MUKHIM Female 45
3 SHRI KUI MUKHIM Male 62 Meghalaya Co-operative Apex Bank
4 SMT AGNES PALA Female 55 Meghalaya Co-operative Apex Bank


Signature/Thumb impression of Applicant
                  
Seal & Signature of Registering Authority

Requested Period of Employment

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days
1 5781 K.MUKHIM 01/07/2008~~10/07/2008~~10 10
2 12135 A.PALA 17/11/2008~~21/11/2008~~5 5
3 14207 K.MUKHIM 23/09/2009~~29/09/2009~~7 7
4 14915 01/10/2009~~07/10/2009~~7 7
5 23222 A.PALA 08/02/2010~~21/02/2010~~14 14
6 24390 01/03/2010~~14/03/2010~~14 14
7 24648 K.MUKHIM 15/03/2010~~21/03/2010~~7 7
8 25147 22/03/2010~~28/03/2010~~7 7
9 12046 A.PALA 01/04/2010~~14/04/2010~~14 14
10 98402 01/04/2010~~14/04/2010~~14 14
11 27662 K.MUKHIM 20/10/2010~~27/10/2010~~8 8
12 21249 A.PALA 23/11/2010~~06/12/2010~~14 14
13 118268 23/11/2010~~06/12/2010~~14 14
14 23839 09/12/2010~~15/12/2010~~7 7
15 118820 09/12/2010~~15/12/2010~~7 7
16 26656 17/12/2010~~30/12/2010~~14 14
17 1559 01/04/2011~~16/04/2011~~16 14
18 3130 01/05/2011~~14/05/2011~~14 14
19 4236 26/05/2011~~02/06/2011~~8 7
20 4487 16/06/2011~~01/07/2011~~16 14
21 11136 01/09/2011~~16/09/2011~~16 14
22 11623 01/10/2011~~16/10/2011~~16 14
23 16146 17/10/2011~~20/10/2011~~4 4
24 24384 23/01/2012~~30/01/2012~~8 7
25 25252 01/02/2012~~16/02/2012~~16 14
26 26108 03/03/2012~~18/03/2012~~16 14
27 3355 17/05/2012~~24/05/2012~~8 7
28 20663 17/05/2012~~23/05/2012~~7 7
29 4343 25/05/2012~~01/06/2012~~8 7
30 20922 25/05/2012~~31/05/2012~~7 7
31 4904 02/06/2012~~17/06/2012~~16 14
32 23751 02/06/2012~~15/06/2012~~14 14
33 8296 19/06/2012~~26/06/2012~~8 7
34 9276 05/07/2012~~20/07/2012~~16 14
35 1701 27/06/2013~~12/07/2013~~16 14
36 5903 13/07/2013~~20/07/2013~~8 7
37 7268 01/09/2013~~16/09/2013~~16 14
38 10307 17/09/2013~~02/10/2013~~16 14
39 10584 03/10/2013~~18/10/2013~~16 14
40 57155 SMT AGNES PALA 11/08/2014~~18/08/2014~~8 7
41 59270 19/08/2014~~26/08/2014~~8 7
42 62350 27/08/2014~~03/09/2014~~8 7
43 63771 08/09/2014~~12/09/2014~~5 5
44 64043 27/10/2014~~03/11/2014~~8 7
45 64819 04/11/2014~~07/11/2014~~4 4
46 111509 20/11/2014~~27/11/2014~~8 7
47 100699 28/11/2014~~05/12/2014~~8 7
48 114675 06/12/2014~~13/12/2014~~8 7
49 118390 15/12/2014~~07/01/2015~~24 21
50 119975 24/01/2015~~16/02/2015~~24 21
51 10374 13/04/2015~~17/05/2015~~35 30
52 26829 20/07/2015~~23/08/2015~~35 30
53 59130 18/11/2015~~03/12/2015~~16 14
54 67287 07/12/2015~~22/12/2015~~16 14
55 77297 11/01/2016~~12/01/2016~~2 2
56 88379 08/02/2016~~18/02/2016~~11 10
57 16845 04/08/2016~~04/09/2016~~32 28
58 36372 05/09/2016~~15/09/2016~~11 10
59 56624 28/09/2016~~28/09/2016~~1 1
60 85956 09/11/2016~~12/11/2016~~4 4
61 99379 02/12/2016~~17/12/2016~~16 14
62 118564 11/01/2017~~07/02/2017~~28 24
63 147759 21/02/2017~~09/03/2017~~17 15
64 168757 21/03/2017~~24/03/2017~~4 4
65 170357 25/03/2017~~25/03/2017~~1 1
66 20398 22/06/2017~~23/06/2017~~2 2
67 32138 31/07/2017~~14/09/2017~~46 40
68 91452 04/12/2017~~24/12/2017~~21 18
69 129008 09/02/2018~~12/03/2018~~32 28
70 150069 16/03/2018~~29/03/2018~~14 12
71 42578 11/07/2018~~11/08/2018~~32 28
72 58734 SHRI KUI MUKHIM 13/08/2018~~24/08/2018~~12 11
73 58735 SMT AGNES PALA 13/08/2018~~24/08/2018~~12 11
74 164229 SHRI KUI MUKHIM 17/01/2019~~14/02/2019~~29 25
75 164230 SMT AGNES PALA 17/01/2019~~14/02/2019~~29 25
76 65666 05/08/2019~~05/09/2019~~32 28
77 96115 11/09/2019~~12/10/2019~~32 28
78 131277 16/10/2019~~12/11/2019~~28 24
79 159228 19/11/2019~~23/11/2019~~5 5
80 191534 08/01/2020~~24/01/2020~~17 15
81 39362 17/06/2020~~18/07/2020~~32 28
82 64841 21/07/2020~~14/08/2020~~25 22
83 163336 09/11/2020~~15/11/2020~~7 6
84 226449 25/01/2021~~25/02/2021~~32 28
85 268988 01/03/2021~~17/03/2021~~17 15
86 73408 13/09/2021~~22/09/2021~~10 9
87 142173 01/12/2021~~01/01/2022~~32 28
88 163488 04/01/2022~~04/02/2022~~32 28
89 202504 05/02/2022~~08/03/2022~~32 28
90 250215 09/03/2022~~18/03/2022~~10 9
91 15385 11/05/2022~~11/05/2022~~1 1

Period and Work on which Employment Offered

S.No Demand Id Name of Applicant Month & Date from which employment requested No of Days Work Name
1 5781 K.MUKHIM 01/07/2008~~10/07/2008~~10 40 Afforestation and trees plantation at Khonglah
2 12135 A.PALA 17/11/2008~~21/11/2008~~5 15 Afforestation and trees plantation at Khonglah
3 14207 K.MUKHIM 23/09/2009~~29/09/2009~~7 35 Const of CC Footpath at Khonglah VEC
4 14915 01/10/2009~~07/10/2009~~7 35 Const of CC Footpath at Khonglah VEC
5 23222 A.PALA 08/02/2010~~21/02/2010~~14 34 Const of CC Footpath at Khonglah VEC
6 24390 01/03/2010~~14/03/2010~~14 35 Const of CC Footpath at Khonglah VEC
7 24648 K.MUKHIM 15/03/2010~~21/03/2010~~7 27 Const of CC Footpath at Khonglah VEC
8 25147 22/03/2010~~28/03/2010~~7 26 Const of CC Footpath at Khonglah VEC
9 98402 A.PALA 01/04/2010~~14/04/2010~~14 14 Const of CC Footpath at Khonglah VEC
10 27662 K.MUKHIM 20/10/2010~~27/10/2010~~8 58 Const of CC Footpath at Khonglah VEC
11 118268 A.PALA 23/11/2010~~06/12/2010~~14 14 Const of CC Footpath at Khonglah VEC
12 118820 09/12/2010~~15/12/2010~~7 7 Const of CC Footpath at Khonglah VEC
13 26656 17/12/2010~~30/12/2010~~14 48 Const of CC Footpath at Khonglah VEC
14 1559 01/04/2011~~16/04/2011~~16 41 Const of CC Footpath at Khonglah VEC
15 3130 01/05/2011~~14/05/2011~~14 41 Const of CC Footpath at Khonglah VEC
16 4236 26/05/2011~~02/06/2011~~8 34 Const of CC Footpath at Khonglah VEC
17 4487 16/06/2011~~01/07/2011~~16 41 Const of CC Footpath at Khonglah VEC
18 11136 01/09/2011~~16/09/2011~~16 25 Const of CC Footpath at Khonglah VEC
19 11623 01/10/2011~~16/10/2011~~16 34 Const of CC Footpath at Khonglah VEC
20 16146 17/10/2011~~20/10/2011~~4 24 Const of CC Footpath at Khonglah VEC
21 24384 23/01/2012~~30/01/2012~~8 34 Construction of Drainage at Khonglah
22 25252 01/02/2012~~16/02/2012~~16 48 Construction of Drainage at Khonglah
23 26108 03/03/2012~~18/03/2012~~16 48 Construction of Drainage at Khonglah
24 3355 17/05/2012~~24/05/2012~~8 28 Construction of Drainage at Khonglah
25 20663 17/05/2012~~23/05/2012~~7 34 Construction of Drainage at Khonglah
26 4343 25/05/2012~~01/06/2012~~8 35 Construction of Drainage at Khonglah
27 20922 25/05/2012~~31/05/2012~~7 35 Construction of Drainage at Khonglah
28 4904 02/06/2012~~17/06/2012~~16 47 Construction of Drainage at Khonglah
29 23751 02/06/2012~~15/06/2012~~14 34 Construction of Drainage at Khonglah
30 8296 19/06/2012~~26/06/2012~~8 42 Construction of Drainage at Khonglah
31 9276 05/07/2012~~20/07/2012~~16 43 Construction of Drainage at Khonglah
32 1701 27/06/2013~~12/07/2013~~16 42 Const of CC Footpath at Khonglah VEC
33 5903 13/07/2013~~20/07/2013~~8 32 Const of CC Footpath at Khonglah VEC
34 7268 01/09/2013~~16/09/2013~~16 42 Const of CC Footpath at Khonglah VEC Phase II
35 10307 17/09/2013~~02/10/2013~~16 42 Const of CC Footpath at Khonglah VEC Phase II
36 10584 03/10/2013~~18/10/2013~~16 47 Const of CC Footpath at Khonglah VEC Phase II
37 57155 SMT AGNES PALA 11/08/2014~~18/08/2014~~8 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m
38 59270 19/08/2014~~26/08/2014~~8 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m
39 62350 27/08/2014~~03/09/2014~~8 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m
40 63771 08/09/2014~~12/09/2014~~5 5 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m
41 64043 27/10/2014~~03/11/2014~~8 7 Construction of Internal Road at Khonglah Vec
42 64819 04/11/2014~~07/11/2014~~4 4 Construction of Internal Road at Khonglah Vec
43 111509 20/11/2014~~27/11/2014~~8 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I
44 100699 28/11/2014~~05/12/2014~~8 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I
45 114675 06/12/2014~~13/12/2014~~8 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I
46 118390 15/12/2014~~07/01/2015~~24 21 Construction of Check dam/Community Pond at Khonglah Vec PH-I
47 119975 24/01/2015~~16/02/2015~~24 21 Construction of Community Pond at Khonglah Vec Ph-II
48 10374 13/04/2015~~17/05/2015~~35 30 Construction of drainage/R/Wall Phase- I at Khonglah Vec
49 26829 20/07/2015~~23/08/2015~~35 30 Construction of R/Wall (Erosion Control work at Khonglah Vec Phase -II 2015-16
50 59130 18/11/2015~~03/12/2015~~16 14 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC
51 67287 07/12/2015~~22/12/2015~~16 14 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC
52 77297 11/01/2016~~12/01/2016~~2 2 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC
53 88379 08/02/2016~~18/02/2016~~11 10 Construction of R/W( Erosion Control Work) at Khonglah Vec FY 2015-16/116 Ph-IV L=274 M
54 16845 04/08/2016~~04/09/2016~~32 28 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49
55 36372 05/09/2016~~15/09/2016~~11 10 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49
56 56624 28/09/2016~~28/09/2016~~1 1 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49
57 85956 09/11/2016~~12/11/2016~~4 4 Construction of R wall at Khonglah Vec PH-II L= 161 m W/O 2016-17/142
58 99379 02/12/2016~~17/12/2016~~16 14 Const of Internal Road at Khonglah Vec L= 553.75 m Culvert- 16 nos W/O 2016-17/76
59 118564 11/01/2017~~07/02/2017~~28 24 Const of Internal Road at Khonglah Vec L= 553.75 m Culvert- 16 nos W/O 2016-17/76
60 147759 21/02/2017~~09/03/2017~~17 15 Const of side drain slab cover at Khonglah Vec L= 555.48 m W/O 2016-17/180
61 168757 21/03/2017~~24/03/2017~~4 4 Constn of Railing at Khonglah VEC L=1295m W/O 2016-17/196
62 170357 25/03/2017~~25/03/2017~~1 1 Construction of Side Drain at Khonglah VEC L=53.12 m W/O 2016-17/195
63 20398 22/06/2017~~23/06/2017~~2 2 Roadside Tree Plantation at Khonglah VEC L=0.9 m W/O 2017-18/DP-41
64 32138 31/07/2017~~14/09/2017~~46 40 Construction of Internal Road PH-Bat Khonglah VEC 10 nos Culvert L=1350m W/O 2017-18/RC-8
65 91452 04/12/2017~~24/12/2017~~21 18 Construction of Railing cum Compound Fencing at Khonglah VEC 2017-18
66 129008 09/02/2018~~12/03/2018~~32 28 Construction of Playground at Khonglah VEC Gallery=44.5m Fencing=280m WO:2017-18/LD-5
67 150069 16/03/2018~~29/03/2018~~14 12 Construction of Playground at Khonglah VEC Gallery=44.5m Fencing=280m WO:2017-18/LD-5
68 42578 11/07/2018~~11/08/2018~~32 28 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4
69 58734 SHRI KUI MUKHIM 13/08/2018~~24/08/2018~~12 11 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4
70 58735 SMT AGNES PALA 13/08/2018~~24/08/2018~~12 11 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4
71 164229 SHRI KUI MUKHIM 17/01/2019~~14/02/2019~~29 25 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36
72 164230 SMT AGNES PALA 17/01/2019~~14/02/2019~~29 25 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36
73 65666 05/08/2019~~05/09/2019~~32 28 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14
74 96115 11/09/2019~~12/10/2019~~32 28 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14
75 131277 16/10/2019~~12/11/2019~~28 24 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14
76 159228 19/11/2019~~23/11/2019~~5 5 Construction of Water Tank Convergence A 9msq at Khonglah VEC WO 2019 20 WC 12147
77 191534 08/01/2020~~24/01/2020~~17 15 Construction of Internal Road at Khonglah VEC WO 2019 20 RC 35636
78 39362 17/06/2020~~18/07/2020~~32 28 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21
79 64841 21/07/2020~~14/08/2020~~25 22 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21
80 163336 09/11/2020~~15/11/2020~~7 6 Improvement of Check Dam at Khonglah VEC WO 2020 21 WC 22426
81 226449 25/01/2021~~25/02/2021~~32 28 Construction of Check Dam at Khonglah VEC WO 20020 21 WC
82 268988 01/03/2021~~17/03/2021~~17 15 Construction of Check Dam at Khonglah VEC WO 20020 21 WC
83 73408 13/09/2021~~22/09/2021~~10 9 Construction of Water Drinking Source In Kor Wah Sohrai with MBDA at Khanglah Vec WO 2021 22
84 142173 01/12/2021~~01/01/2022~~32 28 Construction of play field at Khonglah VEC WO 2021 22
85 163488 04/01/2022~~04/02/2022~~32 28 Construction of play field at Khonglah VEC WO 2021 22
86 202504 05/02/2022~~08/03/2022~~32 28 Construction of play field at Khonglah VEC WO 2021 22
87 250215 09/03/2022~~18/03/2022~~10 9 Construction of play field at Khonglah VEC WO 2021 22
88 15385 11/05/2022~~11/05/2022~~1 1 Construction of Internal Road at Khonglah VEC WO 2021 22

Period and Work on which Employment Given

S.No Name of Applicant Month & Date from which employment requested No of Days Work Name MSR No. Total Amount of Work Done Payment Due
1 K.MUKHIM 01/07/2008 8 Afforestation and trees plantation at Khonglah -13 560 0
2 A.PALA 17/11/2008 5 Afforestation and trees plantation at Khonglah 5959 350 0
Sub Total FY 0809 13 910 0
3 K.MUKHIM 23/09/2009 7 Const of CC Footpath at Khonglah VEC 12639 700 0
4 K.MUKHIM 01/10/2009 7 Const of CC Footpath at Khonglah VEC 12926 700 0
5 A.PALA 08/02/2010 14 Const of CC Footpath at Khonglah VEC 20146 1400 0
6 A.PALA 01/03/2010 14 Const of CC Footpath at Khonglah VEC 15104 1400 0
7 K.MUKHIM 15/03/2010 7 Const of CC Footpath at Khonglah VEC 21381 700 0
8 K.MUKHIM 22/03/2010 7 Const of CC Footpath at Khonglah VEC 21468 700 0
Sub Total FY 0910 56 5600 0
9 A.PALA 01/04/2010 14 Const of CC Footpath at Khonglah VEC 21474 1400 0
10 K.MUKHIM 20/10/2010 7 Const of CC Footpath at Khonglah VEC 45001 700 700
11 A.PALA 23/11/2010 14 Const of CC Footpath at Khonglah VEC 43891 1400 0
12 A.PALA 09/12/2010 7 Const of CC Footpath at Khonglah VEC 44065 700 0
13 A.PALA 17/12/2010 14 Const of CC Footpath at Khonglah VEC 44452 1400 0
Sub Total FY 1011 56 5600 700
14 A.PALA 01/04/2011 14 Const of CC Footpath at Khonglah VEC 45001 1638 0
15 A.PALA 26/05/2011 7 Const of CC Footpath at Khonglah VEC 45300 700 0
16 A.PALA 16/06/2011 14 Const of CC Footpath at Khonglah VEC 45688 1400 0
17 A.PALA 01/09/2011 14 Const of CC Footpath at Khonglah VEC 62094 1638 0
18 A.PALA 01/10/2011 14 Const of CC Footpath at Khonglah VEC 62119 1638 0
19 A.PALA 17/10/2011 4 Const of CC Footpath at Khonglah VEC 62044 468 0
20 A.PALA 23/01/2012 7 Construction of Drainage at Khonglah 71004 819 0
21 A.PALA 01/02/2012 14 Construction of Drainage at Khonglah 71031 1638 0
Sub Total FY 1112 88 9939 0
22 A.PALA 17/05/2012 7 Construction of Drainage at Khonglah 86093 896 0
23 A.PALA 25/05/2012 7 Construction of Drainage at Khonglah 86120 896 0
24 A.PALA 02/06/2012 14 Construction of Drainage at Khonglah 86382 1792 0
25 A.PALA 19/06/2012 7 Construction of Drainage at Khonglah 86509 896 0
26 A.PALA 05/07/2012 14 Construction of Drainage at Khonglah 86542 1792 0
Sub Total FY 1213 49 6272 0
27 A.PALA 27/06/2013 14 Const of CC Footpath at Khonglah VEC 109226 2030 0
28 A.PALA 13/07/2013 7 Const of CC Footpath at Khonglah VEC 114578 1015 0
29 A.PALA 01/09/2013 14 Const of CC Footpath at Khonglah VEC Phase II 119163 2030 0
30 A.PALA 17/09/2013 14 Const of CC Footpath at Khonglah VEC Phase II 119219 2030 0
31 A.PALA 03/10/2013 14 Const of CC Footpath at Khonglah VEC Phase II 119247 2030 0
Sub Total FY 1314 63 9135 0
32 SMT AGNES PALA 11/08/2014 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m 142838 1071 0
33 SMT AGNES PALA 19/08/2014 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m 142865 1071 0
34 SMT AGNES PALA 27/08/2014 7 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m 144405 1071 0
35 SMT AGNES PALA 08/09/2014 5 Construction of Internal Road ( Including S/T, R/W , Culvert & S/ D) Leng=400m ,SD= Nos 8 SD =300m 144432 765 0
36 SMT AGNES PALA 27/10/2014 7 Construction of Internal Road at Khonglah Vec 145781 1071 0
37 SMT AGNES PALA 04/11/2014 4 Construction of Internal Road at Khonglah Vec 145809 612 0
38 SMT AGNES PALA 20/11/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146229 1071 0
39 SMT AGNES PALA 28/11/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146258 1071 0
40 SMT AGNES PALA 06/12/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146305 1071 0
41 SMT AGNES PALA 15/12/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146310 1071 0
42 SMT AGNES PALA 23/12/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146363 1071 0
43 SMT AGNES PALA 31/12/2014 7 Construction of Check dam/Community Pond at Khonglah Vec PH-I 146873 1071 0
44 SMT AGNES PALA 24/01/2015 7 Construction of Community Pond at Khonglah Vec Ph-II 146768 1071 0
45 SMT AGNES PALA 01/02/2015 7 Construction of Community Pond at Khonglah Vec Ph-II 146797 1071 0
46 SMT AGNES PALA 09/02/2015 7 Construction of Community Pond at Khonglah Vec Ph-II 146826 1071 0
Sub Total FY 1415 100 15300 0
47 SMT AGNES PALA 13/04/2015 7 Construction of drainage/R/Wall Phase- I at Khonglah Vec 231 1141 0
48 SMT AGNES PALA 21/04/2015 7 Construction of drainage/R/Wall Phase- I at Khonglah Vec 260 1141 0
49 SMT AGNES PALA 29/04/2015 7 Construction of drainage/R/Wall Phase- I at Khonglah Vec 289 1141 0
50 SMT AGNES PALA 07/05/2015 7 Construction of drainage/R/Wall Phase- I at Khonglah Vec 318 1141 0
51 SMT AGNES PALA 15/05/2015 2 Construction of drainage/R/Wall Phase- I at Khonglah Vec 347 326 0
52 SMT AGNES PALA 20/07/2015 14 Construction of R/Wall (Erosion Control work at Khonglah Vec Phase -II 2015-16 1085 2282 0
53 SMT AGNES PALA 05/08/2015 14 Construction of R/Wall (Erosion Control work at Khonglah Vec Phase -II 2015-16 1328 2282 0
54 SMT AGNES PALA 21/08/2015 2 Construction of R/Wall (Erosion Control work at Khonglah Vec Phase -II 2015-16 1357 326 0
55 SMT AGNES PALA 18/11/2015 14 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC 2597 2282 0
56 SMT AGNES PALA 07/12/2015 14 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC 2833 2282 0
57 SMT AGNES PALA 11/01/2016 2 CONSTRUCTION OF R/WALL ( EROSION ) LENGTH =828 AREA H==3M/4M FY=2015-16 AT KHONGLAH VEC 3425 326 0
58 SMT AGNES PALA 08/02/2016 10 Construction of R/W( Erosion Control Work) at Khonglah Vec FY 2015-16/116 Ph-IV L=274 M 4102 1630 0
Sub Total FY 1516 100 16300 0
59 SMT AGNES PALA 04/08/2016 14 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49 1038 2366 0
60 SMT AGNES PALA 20/08/2016 13 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49 1064 2197 0
61 SMT AGNES PALA 05/09/2016 10 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49 1968 1690 0
62 SMT AGNES PALA 28/09/2016 1 Const. of R/Wall Ph V at khonglah VEC L=341 m FY 2016-17/49 2476 169 0
63 SMT AGNES PALA 09/11/2016 4 Construction of R wall at Khonglah Vec PH-II L= 161 m W/O 2016-17/142 3520 676 0
64 SMT AGNES PALA 02/12/2016 14 Const of Internal Road at Khonglah Vec L= 553.75 m Culvert- 16 nos W/O 2016-17/76 3916 2366 0
65 SMT AGNES PALA 11/01/2017 14 Const of Internal Road at Khonglah Vec L= 553.75 m Culvert- 16 nos W/O 2016-17/76 4359 2366 0
66 SMT AGNES PALA 27/01/2017 10 Const of Internal Road at Khonglah Vec L= 553.75 m Culvert- 16 nos W/O 2016-17/76 4387 1690 0
67 SMT AGNES PALA 21/02/2017 14 Const of side drain slab cover at Khonglah Vec L= 555.48 m W/O 2016-17/180 5266 2366 0
68 SMT AGNES PALA 09/03/2017 1 Const of side drain slab cover at Khonglah Vec L= 555.48 m W/O 2016-17/180 5292 169 0
69 SMT AGNES PALA 21/03/2017 4 Constn of Railing at Khonglah VEC L=1295m W/O 2016-17/196 6015 676 0
70 SMT AGNES PALA 25/03/2017 1 Construction of Side Drain at Khonglah VEC L=53.12 m W/O 2016-17/195 6114 169 0
Sub Total FY 1617 100 16900 0
71 SMT AGNES PALA 22/06/2017 2 Roadside Tree Plantation at Khonglah VEC L=0.9 m W/O 2017-18/DP-41 878 350 0
72 SMT AGNES PALA 31/07/2017 14 Construction of Internal Road PH-Bat Khonglah VEC 10 nos Culvert L=1350m W/O 2017-18/RC-8 1707 2450 0
73 SMT AGNES PALA 16/08/2017 14 Construction of Internal Road PH-Bat Khonglah VEC 10 nos Culvert L=1350m W/O 2017-18/RC-8 1834 2450 0
74 SMT AGNES PALA 01/09/2017 12 Construction of Internal Road PH-Bat Khonglah VEC 10 nos Culvert L=1350m W/O 2017-18/RC-8 2489 2100 0
75 SMT AGNES PALA 04/12/2017 7 Construction of Railing cum Compound Fencing at Khonglah VEC 2017-18 4934 1225 0
76 SMT AGNES PALA 12/12/2017 7 Construction of Railing cum Compound Fencing at Khonglah VEC 2017-18 4955 1225 0
77 SMT AGNES PALA 20/12/2017 4 Construction of Railing cum Compound Fencing at Khonglah VEC 2017-18 4976 700 0
78 SMT AGNES PALA 09/02/2018 14 Construction of Playground at Khonglah VEC Gallery=44.5m Fencing=280m WO:2017-18/LD-5 6288 2450 0
79 SMT AGNES PALA 25/02/2018 14 Construction of Playground at Khonglah VEC Gallery=44.5m Fencing=280m WO:2017-18/LD-5 6300 2450 0
80 SMT AGNES PALA 16/03/2018 12 Construction of Playground at Khonglah VEC Gallery=44.5m Fencing=280m WO:2017-18/LD-5 6913 2100 0
Sub Total FY 1718 100 17500 0
81 SMT AGNES PALA 11/07/2018 14 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4 1648 2534 0
82 SMT AGNES PALA 27/07/2018 14 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4 1658 2534 0
83 SHRI KUI MUKHIM 13/08/2018 11 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4 2273 1991 0
84 SMT AGNES PALA 13/08/2018 11 Construction of Internal Road PH-IV L= 810 m at Khonglah VEC W/O 2018-19/RC-4 2273 1991 0
85 SHRI KUI MUKHIM 17/01/2019 14 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36 4619 2534 0
86 SMT AGNES PALA 17/01/2019 14 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36 4619 2534 0
87 SHRI KUI MUKHIM 17/01/2019 11 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36 4629 1991 0
88 SMT AGNES PALA 17/01/2019 11 Construction of Internal Road at Khonglah VEC WO 2018 19 RC 36 4629 1991 0
Sub Total FY 1819 100 18100 0
89 SMT AGNES PALA 05/08/2019 14 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 636 2618 0
90 SMT AGNES PALA 21/08/2019 14 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 642 2618 0
91 SMT AGNES PALA 11/09/2019 14 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 1305 2618 0
92 SMT AGNES PALA 27/09/2019 14 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 1311 2618 0
93 SMT AGNES PALA 16/10/2019 14 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 2468 2618 0
94 SMT AGNES PALA 01/11/2019 10 Construction of Compound Fencing Cum Side Drain L 346m at Khonglah VEC WO 2019 20 FP 14 2474 1870 0
95 SMT AGNES PALA 19/11/2019 5 Construction of Water Tank Convergence A 9msq at Khonglah VEC WO 2019 20 WC 12147 3522 935 0
96 SMT AGNES PALA 08/01/2020 14 Construction of Internal Road at Khonglah VEC WO 2019 20 RC 35636 4702 2618 0
97 SMT AGNES PALA 24/01/2020 1 Construction of Internal Road at Khonglah VEC WO 2019 20 RC 35636 4729 187 0
Sub Total FY 1920 100 18700 0
98 SMT AGNES PALA 17/06/2020 14 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21 842 2842 0
99 SMT AGNES PALA 03/07/2020 14 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21 849 2842 0
100 SMT AGNES PALA 21/07/2020 14 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21 1459 2842 0
101 SMT AGNES PALA 06/08/2020 8 Construction of Compound Fencing Cum Side drain at Khonglah VEC WO 2020 21 1466 1624 0
102 SMT AGNES PALA 09/11/2020 6 Improvement of Check Dam at Khonglah VEC WO 2020 21 WC 22426 4340 1218 0
103 SMT AGNES PALA 25/01/2021 14 Construction of Check Dam at Khonglah VEC WO 20020 21 WC 6343 2842 0
104 SMT AGNES PALA 10/02/2021 14 Construction of Check Dam at Khonglah VEC WO 20020 21 WC 6357 2842 0
105 SMT AGNES PALA 01/03/2021 14 Construction of Check Dam at Khonglah VEC WO 20020 21 WC 7371 2842 0
106 SMT AGNES PALA 17/03/2021 1 Construction of Check Dam at Khonglah VEC WO 20020 21 WC 7385 203 0
Sub Total FY 2021 99 20097 0
107 SMT AGNES PALA 13/09/2021 9 Construction of Water Drinking Source In Kor Wah Sohrai with MBDA at Khanglah Vec WO 2021 22 578 2034 0
108 SMT AGNES PALA 01/12/2021 14 Construction of play field at Khonglah VEC WO 2021 22 2401 3164 0
109 SMT AGNES PALA 17/12/2021 13 Construction of play field at Khonglah VEC WO 2021 22 2409 2938 0
110 SMT AGNES PALA 04/01/2022 14 Construction of play field at Khonglah VEC WO 2021 22 3007 3164 0
111 SMT AGNES PALA 20/01/2022 14 Construction of play field at Khonglah VEC WO 2021 22 3015 3164 0
112 SMT AGNES PALA 05/02/2022 13 Construction of play field at Khonglah VEC WO 2021 22 4446 2938 0
113 SMT AGNES PALA 21/02/2022 14 Construction of play field at Khonglah VEC WO 2021 22 4459 3164 0
114 SMT AGNES PALA 09/03/2022 9 Construction of play field at Khonglah VEC WO 2021 22 5689 2034 0
Sub Total FY 2122 100 22600 0
115 SMT AGNES PALA 11/05/2022 1 Construction of Internal Road at Khonglah VEC WO 2021 22 7 230 0
Sub Total FY 2223 1 230 0